0  12 Jan, 2026
Listen in 2:00 mins | Read in 70:00 mins
EN
HI

Delhi Jal Board Vs. M/S Mohini Electricals Ltd

  Delhi High Court FAO(OS)(COMM) 210/2022
Link copied!

Case Background

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

FAO(OS)(COMM) 210/2022 Page 1 of 57

$~

* IN THE HIGH COURT OF DELHI AT NEW DELHI

+ FAO(OS)(COMM) 210/2022 & CM APPL. 36624/2022

Judgment reserved on: 08.12.2025

Judgment pronounced on: 12.01.2026

DELHI JAL BOARD .....Appellant

Through: Mr. Sanjay Jain, Sr. Adv. with

Ms. Sangeeta Bharti, SC for DJB with Ms.

Malvi Balyan, Adv.

versus

M/S MOHINI ELECTRICALS LTD .....Respondent

Through: Mr. Amit Sibal, Sr. Adv. with

Ms. Anusuya Salwan, Mr. Bankim Garg, Mr.

Rachit Wadhwa and Mr. Ankit Handa, Advs.

CORAM:

HON'BLE MR. JUSTICE C. HARI SHANKAR

HON'BLE MR. JUSTICE OM PRAKASH SHUKLA

JUDGMENT

% 12.01.2026

OM PRAKASH SHUKLA , J.

1. The appellant has filed the present intra-court appeal under

Section 37(1)(c) of the Arbitration and Conciliation Act, 1996

1

, read

with Section 13 of the Commercial Courts Act, 2015 and Section 151

of Civil Procedure Code, 1908, assailing the impugned judgment dated

04.07.2022 passed by the learned Single Judge in O.M.P. (COMM) No.

22/2020 titled as “Delhi Jal Board (DJB) v. M/s Mohini Electricals

Ltd.”. The appellant had earlier filed the petition under Section 34 of

the A&C Act before the learned Single Judge seeking setting aside of

1

“A&C Act”, hereinafter

FAO(OS)(COMM) 210/2022 Page 2 of 57

the arbitral award dated 02.09.2019

2

rendered by the learned Sole

Arbitrator.

2. By the said impugned award, the learned Arbitral Tribunal

allowed the majority of the claims preferred by the respondent

(claimant before the Arbitral Tribunal) while rejecting certain claim 3,

6A, 7, 11 and 14. The arbitral proceedings emanate from disputes

arising out of the contract dated 28.11.2003, executed between the

parties for the “Construction of various reservoirs at different location

in TYA Areas, Delhi of Delhi Jal Board

3

”.

FACTS

3. The brief factual matrix necessary for the purposes of

adjudication of the present appeal is delineated below.

4. The Delhi Jal Board

4

(appellant hereinafter) invited tenders vide

NIT No.8(2002-2003) for construction of Underground Reservoirs

5

and

Booster Pump Stations

6

across multiple sites in the Trans Yamuna Area,

Delhi

7

. The work was to be executed on a turnkey basis covering civil

construction and supply, installation, testing and commissioning of

Electrical and Mechanical

8

systems. Construction of UGRs with

associated BPSs was required at five specified locations within the

TYA area. At the sixth location, Tahirpur (Nand Nagri), the scope was

2

“Impugned Award”, hereinafter

3

“the Project”, hereinafter

4

“DJB”, hereinafter

5

“UGR”, hereinafter

6

“BPS”, hereinafter

7

“TYA”, hereinafter

8

“E&M”, hereinafter

FAO(OS)(COMM) 210/2022 Page 3 of 57

limited to the construction of a UGR only.

5. For the aforesaid project, M/s Mohini Electrical Ltd. (respondent

hereinafter) entered into a consortium arrangement dated 20.01.2003

with M/s Jes Engineering Co. Pvt. Ltd. and M/s GSJ Envo Ltd., with

the respondent designated as the Consortium Leader.

6. Upon completion of the pre-qualification process, the respondent

submitted its technical and financial bids. A Work Order dated

30.09.2003

9

was thereafter issued for a total value of Rs. 28,49,72,521/-

comprising civil works of Rs. 18,63,11,936/- and E&M works of Rs.

9,86,60,583/-. The scope of the E&M works further envisaged an

Operation and Maintenance

10

obligation for five years following the

completion of the trial run.

7. The Work Order stipulated commencement of work on the 14th

day from the issuance of the Work Order and completion within 18

months, including 15 months for execution and 3 months for the trial,

fixing 14.10.2003 as the commencement date and 13.04.2005 as the

scheduled completion date.

8. Thereafter, the parties executed a formal contract on

28.11.2003

11

, incorporating the FIDIC Conditions of Contract for

Construction for Building and Engineering Works, First Edition 1999,

as modified by Part II – Conditions of Particular Application.

9

“Work Order”, hereinafter

10

“O&M”, hereinafter

11

“contract”, hereinafter

FAO(OS)(COMM) 210/2022 Page 4 of 57

9. Disputes arose soon thereafter concerning commencement and

pace of work. According to the appellant, the respondent started work

only on 19.11.2003, and even then, at only one site, with negligible

progress, despite the clear stipulation of 14.10.2003 as the effective

commencement date. Dissatisfaction over delayed commencement was

recorded vide letter dated 03.12.2003.

10. The respondent, however, vide letter dated 19.01.2004,

contended that commencement was delayed only because the

mobilization advance of 10% was withheld despite furnishing of a

performance bank guarantee dated 28.10.2003 for Rs.1,86,31,194/-.

The respondent alleged expenditure exceeding Rs.1 crore and attributed

delay to financial hardship caused by the non-release of the advance.

11. The appellant refuted the allegation by its communication dated

01.04.2004, pointing out that the bank guarantee securing the

mobilization advance had itself been furnished belatedly on 10.12.2003

and, therefore, the respondent could not shift the burden of delay on the

appellant.

12. As progress continued to lag, a delay notice dated 15.07.2004

was issued, recording that only about 21% of the work had been

completed in nine months, whereas contractual expectations required

nearly 60% progress by that stage. The respondent was called upon to

show cause as to why, in terms of the contract, compensation should

not be levied for the delay and slow progress of the work solely

attributable to the respondent.

FAO(OS)(COMM) 210/2022 Page 5 of 57

13. Between April 2004 and March 2006, the appellant and

respondent exchanged a series of communications recording

deficiencies and delays in execution. The respondent sought extensions

on grounds of escalation and financial constraints. The appellant

granted extensions though expressly reserving its right to impose

liquidated damages and penalties.

14. Due to persistent disputes regarding delay, mobilization advance

recovery, and release of payments, the respondent invoked Clause 20

of the contract and sought the constitution of a Dispute Adjudication

Board

12

on 29.08.2005.

15. Initially, the appellant appointed Mr. Rakesh Seth, former

Member (Drainage), DJB, as DAB member on 03.03.2006. However,

the respondent objected to the said unilateral appointment, and

requested that a panel of three names be proposed for consideration for

appointment of a single-member DAB.

16. Subsequently, the appellant appointed Mr. I.M. Singh as the

single-member DAB, and the respondent conveyed its consent to the

said appointment. On 07.01.2009, Mr. Singh requested both parties to

attend his office for execution of the Dispute Adjudication

Agreement

13

. However, the respondent did not participate in the signing

of the DAA.

12

“DAB”, hereinafter.

13

“DAA”, hereinafter.

FAO(OS)(COMM) 210/2022 Page 6 of 57

17. By its letter dated 28.01.2009, the respondent stated that both

parties had agreed to explore an amicable resolution of the disputes and,

in that context, had mutually decided to defer execution of the DAA.

18. According to the appellant, no effective progress took place

thereafter until 10.10.2013, when the respondent sought to revive the

DAB process seeking execution of the DAA.

19. Meanwhile, the timeline for completing the project was extended

on multiple occasions and the final extension was granted up to

31.10.2008 by the letter dated 08.02.2013, subject to a token penalty of

Rs.40,000/- for the delay. Also, the performance certificates dated

11.08.2008 recorded that execution of the works had been completed

by August 2008.

20. Alleging continued inaction regarding the DAB, Jes Engineering

Co. Pvt. Ltd. (a member of the consortium) filed W.P.(C) 5337/2015

before this Court seeking directions for execution of the DAA. Pursuant

to order dated 27.05.2015, a single member DAB was constituted with

the consent of both the parties, and Mr. Anand Kumar was appointed

on 05.09.2016.

21. In a joint meeting held on 27.10.2017, the parties agreed to close

the DAB process and refer the disputes to arbitration. By mutual

consent, Mr. Anand Kumar was appointed as the Sole Arbitrator, and

DAB proceedings were terminated on 05.03.2018.

FAO(OS)(COMM) 210/2022 Page 7 of 57

PROCEEDINGS BEFORE ARBIT RAL TRIBUNAL AND

IMPUGNED AWARD

22. The respondent had raised as many as twenty distinct claims

before the learned Arbitral Tribunal. Upon a detailed consideration of

the pleadings, documentary evidence, and submissions advanced by

both parties, the learned Arbitral Tribunal proceeded to allow a

substantial majority of the said claims. In addition, it also awarded

financing charges on the amounts found due and payable.

23. The respondent in its Statement of Claim, categorically asserted

that during execution of the contract works, various hindrances were

caused by the appellant, which materially impeded timely performance.

According to the respondent, although it was ready and willing to

execute the work in accordance with the contractual schedule, persistent

delays attributable to the appellant resulted in prolongation of the

project and eventual completion only in the year 2008. The respondent,

therefore, pleaded that it had incurred substantial financial losses,

overheads, and escalation costs due to prolongation, which were wholly

attributable to the defaults of the appellant.

24. Upon appreciation of the contemporaneous correspondence and

record, the learned Arbitral Tribunal recorded a categorical finding that

the primary cause of delay was attributable to the appellant. The

Tribunal noted that there was considerable delay in handing over clear

and encumbrance free site, in issuance and approval of designs and

drawings, in release of payments legitimately due, and in appointment

of the third-party inspection agency. Each of these lapses had a

FAO(OS)(COMM) 210/2022 Page 8 of 57

cumulative and cascading effect on the progress of work, rendering

adherence to the original timeline impossible. The learned Arbitral

Tribunal, therefore, rejected the appellant’s attempt to attribute delay to

the respondent.

25. The learned Arbitral Tribunal thereafter, considered the

preliminary objection raised by the appellant regarding limitation. In its

Statement of Defense, the appellant submitted that the claims were

barred by limitation as they were filed beyond three years from the

alleged accrual of cause of action. It was contended that the respondent

was aware of the alleged disputes at least from 2004, yet chose not to

initiate proceedings within the prescribed period. According to the

appellant, though the respondent attempted to invoke the DAB

mechanism, it failed to meaningfully pursue the same, despite repeated

reminders from the appellant.

26. The appellant further argued that the respondent sought

constitution of the DAB only in 2016, which was far beyond the

contractual period of 42 days contemplated under the dispute resolution

clause for raising disputes. On this basis, it was contended that the

arbitral proceedings themselves were not maintainable, being ex facie

barred by limitation.

27. The learned Arbitral Tribunal, however, rejected the plea of

limitation. It held that the limitation period does not commence merely

on occurrence of a dispute in abstract, but only when the right to invoke

arbitration effectively accrues. It was noted that the parties were

continuously engaged in discussions, negotiations and attempts at

FAO(OS)(COMM) 210/2022 Page 9 of 57

amicable settlement from the inception of the dispute until 2018.

Reliance was placed on the principle laid down in Hari Shankar

Singhania v. Gaur Hari Singhania

14

, wherein it was held that

limitation begins to run only from the date when assertion of claim by

one party is clearly denied by the other.

28. Applying the above principle, the learned Arbitral Tribunal

concluded that the right to seek arbitration accrued only on 05.03.2018,

when both parties mutually agreed to close the DAB process, in terms

of Clause 20 of the contract, and proceed to arbitration. Accordingly,

the learned Arbitral Tribunal held that the claims were well within

limitation.

29. With respect to financing charges, the learned Arbitral Tribunal

undertook an exhaustive examination of the contractual framework

relating to payments and delayed payments, particularly sub-Clauses

14.3, 14.6, 14.7, 14.8, and 20.1 of the contract. The learned Arbitral

Tribunal emphasized that the contractual provisions clearly delineated

the rights and obligations of the parties in relation to interim payments

and the consequences of delayed release.

30. The learned Arbitral Tribunal found that under clause 14.3(b)–

(f), all additions, deductions and claims were required to be

incorporated in the running bills. Since the appellant failed to honour

payments due under these running bills, it became liable, by operation

of clause 14.8, to pay financing charges on delayed amounts. Upon

14

(2006) 4 SCC 658

FAO(OS)(COMM) 210/2022 Page 10 of 57

examining the pleadings, supporting statements, and Chartered

Accountant certified documents filed on 07.08.2019, the learned

Arbitral Tribunal concluded that the appellant had failed to abide by the

contractual stipulations governing financing charges. Consequently, it

was held that the respondent was entitled to financing charges on all

amounts wrongfully withheld.

31. A detailed tabular statement setting out each claim, the amount

awarded, together with the computation of financing charges payable,

thereby formed an integral part of the impugned award, as below:

Claim Principal

Awarded

Finance Charge

(FC) Awarded

Total Amount

Awarded

CNo.1: Addition to

contract price due to

intro of VAT Tax in

place of Work Contract

Tax for Rs.1,20,54,368/-.

Rs. 63,81,699/-

Rs. 2,39,19,679/- Rs.

3,03,01,378/-

CNo.2: Addition To

Contract Price Due to

Intro of Service Tax on

Erection &

Commissioning (E&C)

Works and Operation

and Maintenance

(O&M) Works for

Rs.6,04,384/-

Rs. 6,04,384/- Rs. 19,11,312/- Rs. 25,15,696/-

CNo.3: Addition to

Contract Price on

Account of Levy of

Labour Cess for

Rs.10,42,930/-

NIL NIL NIL

CNo.4(A): Excess

Amount Retained from

RA Bills amounting to

Rs.23,53,806/-

Rs. 23,53,806/- Rs. 75,32,918/- Rs. 98,86,724/-

CNo.4(B): Excess

Retention on pretext of

Extension of Time

Rs. 1,95,924/- Rs. 59,28,146/- Rs. 61,24,070/-

CNo.4(C): Excess

Recovery of

Mobilization Advance

beyond the Provision of

the Contract.

— Rs. 1,78,12,198/- Rs.

1,78,12,198/-

CNo.5: Refund of Rs. 41,55,780/- Rs. 17,21,552/- Rs. 58,77,332/-

FAO(OS)(COMM) 210/2022 Page 11 of 57

Amount wrongly

recovered on the excuse

of use of different Brand

of Steel, Though 'ISl'

Marked for

Rs.41,55,780/-

CNo.6(A): Addition to

Contract Price in Wages

for the Labour deployed

for Civil Works &

Installation Works of

F&M for Rs.97,47,230/-

NIL NIL NIL

CNo.6(B): Addition to

Contract Price in Wages

for the Manpower

deployed for O&M

Works for Rs.64,41,467/-

Rs. 64,41,467/- Rs. 98,15,574/- Rs.

1,62,57,041/-

CNo.7: Addition to

Contract Price on

account of Increased

Prices of Input Materials

during the Stipulated

Period of Completion for

Rs.81,56,564/-

NIL NIL NIL

CNo.8: Addition to

Contract Price on

Account of Increased

Prices of Cement, Steel

and Other input

Materials after the

Stipulated Date Of

Completion for

Rs.2,98,73,338/-

Rs.

2,66,72,624/-

NIL Rs.

2,66,72,624/-

CNo.9A:AmountPayable

on Account of Non-

Payment of Work Done /

Final Bill as per the

terms of the Contract

For Rs.5,56,95,810/-

Rs.

4,97,28,402/-

— Rs.

4,97,28,402/-

CNo.9B: Amount

Payable by way of FC

under Clause 14.8 on

Delayed Payments as per

the Terms of the

Contract.

— Rs. 10,98,93,606/- Rs.

10,98,93,606/-

CNo.9C: Amount

Payable on Account of

FC Due to Delay in

Release of Mobilization

Advance

— Rs. 13,12,205/- Rs. 13,12,205/-

CNo.10: Addition to

Contract Price on

Account of Delay in

Appointment of Third-

Party Inspection Agency

(TPJA)

Rs. 2,67,192/- Rs. 11,59,371/- Rs. 14,26,563/-

CNo.11: On Account of NIL NIL NIL

FAO(OS)(COMM) 210/2022 Page 12 of 57

Deferred Profitability

CNo.12A: Manpower

costs and plant and

machineries during

overrun period

Rs.

3,68,43,750/-

— Rs.

3,68,43,750/-

CNo.12B:

Overhead/Head Office

Profits

Rs.

1,06,03,186/-

— Rs.

1,06,03,186/-

CNo.13: On Account of

FC beyond the Dates as

stated against each

Dispute

— Rs. 5,48,43,184/-

Rs.

5,48,43,184/-

CNo.14 : Costs towards

Arbitration Proceedings

Rs.29,00,000/-

NIL NIL NIL

TOTAL Rs.

15,40,63,788/-

Rs. 22,60,34,141/- Rs.

38,00,97,929/-

IMPUGNED JUDGMENT

32. Aggrieved by the impugned award, the appellant filed a petition

under Section 34 of the A&C Act. The challenge to the impugned award

was primarily premised on the following grounds: i) the claims were

barred by limitation; (ii) the delay in execution of the project was not

attributable to the petitioner/appellant; (iii) the learned Arbitral

Tribunal erred in awarding financing charges/interest on the claims; and

iv) the impugned award was contrary to the express terms of the

contract and therefore liable to be set aside.

33. The learned Single Judge, upon consideration of the rival

contentions and the material on record, dismissed the petition and found

no ground to interfere with the impugned award within the limited

scope of Section 34 of the A&C Act.

34. On the issue of limitation, the learned Single Judge held that

Clause 20 of the contract envisaged a mandatory multi-tier dispute

FAO(OS)(COMM) 210/2022 Page 13 of 57

resolution mechanism, requiring disputes to be placed, in the first

instance, before the DAB. It was found that the respondent had invoked

the DAB mechanism as early as 29.08.2005 and had thereafter

consistently pursued the constitution and functioning of the DAB.

35. However, the learned Single Judge noted, that the DAB remained

non-functional for a prolonged period, constraining one of the

consortium partners to approach this Court by way of a writ petition in

May 2015. By order dated 25.05.2015, this Court directed the parties to

execute DAA within stipulated timelines and further permitted

substitution of the DAB member, if necessary, in order to operationalize

the mechanism contemplated under the contract.

36. Although the DAB ultimately came to be constituted, the learned

Single Judge recorded that it failed to render any decision. The DAB

proceedings were mutually closed on 05.03.2018, whereafter the parties

proceeded to arbitration in terms of the contract. In view of Clause 20,

the learned Single Judge held that the cause of action to invoke

arbitration accrued only upon the closure of the DAB in 2018, and not

at any prior point of time. Consequently, the arbitral claims could not

be said to be barred by limitation.

37. The learned Single Judge also took note of the fact that the

appellant itself had, on 08.02.2013, granted an extension of time for

completion of the project, thereby acknowledging that disputes between

the parties were live and subsisting. In these circumstances, it was

concluded that the view taken by the learned Arbitral Tribunal on

limitation was both plausible and consistent with the contractual

FAO(OS)(COMM) 210/2022 Page 14 of 57

scheme, and therefore did not disclose any patent illegality warranting

interference.

38. With regard to delay, the learned Single Judge observed that the

learned Arbitral Tribunal, on a comprehensive appraisal of the

evidence, found that several factors leading to delay were attributable

to the appellant. The learned Arbitral Tribunal also noticed that the

extensions of time granted were accompanied only by nominal penalties

of Rs.20,000/- and Rs.40,000/-, despite the contract providing for

significantly higher liquidated damages. This conduct in view of the

Court indicated that the appellant itself did not treat the delay as being

attributable to the respondent. The Court held that such findings were

factual in nature, and fell squarely within the domain of the Arbitral

Tribunal as the final adjudicator of facts, and therefore could not be re-

appreciated under Section 34 of the A&C Act.

39. On the question of financing charges/interest, the learned Single

Judge rejected the contention of the appellant that the contract imposed

a blanket prohibition on the award of interest. Upon a plain reading of

Clauses 14.7 and 14.8, the Court held that there was no proscription

against interest; rather, Clause 14.8 positively conferred upon the

contractor an entitlement to financing charges, compounded monthly,

in the event of delayed payments. The argument that the contract barred

interest was therefore held to be misconceived.

40. The learned Single Judge further recorded that the Arbitral

Tribunal had found certain amounts payable to the respondent, to have

remained unpaid. In respect of such delayed payments, the entitlement

FAO(OS)(COMM) 210/2022 Page 15 of 57

to financing charges flowed directly from Clause 14.8 as per the learned

Arbitral Tribunal. The learned Single Judge found merit in the

contention of the respondent that financing charges are payable only in

respect of admitted/certified payments that remained unpaid. However,

the learned Arbitral Tribunal’s decision to award interest even on

amounts that ought properly to have been included in Interim Payment

Certificates

15

was held to be a possible interpretation based on the

contractual provisions and could not be characterized as perverse or

irrational.

41. The plea that the learned Arbitral Tribunal was legally prohibited

from awarding compound interest was also repelled. The Court

observed that not only did the contractual framework itself envisage

compound financing charges, but the respondent had also produced

material demonstrating that it had incurred compound interest on its

borrowings. In this background, the award of compound interest could

not be said to suffer from patent illegality.

42. The reliance placed by the appellant on M/s Hyder Consulting

(UK) Ltd. v. Governor, State of Orissa

16

was held to be misplaced. The

learned Single Judge observed that the said decision, in fact, recognized

that arbitral tribunals may grant interest on interest under Section 31(7)

of the Act. Reference was made to UHL Power Company Ltd. v. State

of Himachal Pradesh with State of Himachal Pradesh v. UHL Power

Company Ltd

17

, wherein the Hon’ble Supreme Court clarified that there

15

“IPCs”, hereinafter

16

(2015) 2 SCC 189

17

(2022) 4 SCC 116

FAO(OS)(COMM) 210/2022 Page 16 of 57

is no absolute bar on the grant of compound interest by arbitral tribunal

where the contract so provides or where circumstances justify such

award.

43. In light of the above discussion, the learned Single Judge

concluded that the impugned award did not disclose any infirmity

within the narrow grounds of interference under Section 34 of the Act.

The petition was accordingly dismissed.

RIVAL CONTENTIONS BEFORE THIS COURT

44. Mr. Sanjay Jain, learned Senior Counsel appearing for the

appellant, submitted that the award in respect of claims 12A and 12B

suffers from patent illegality and is liable to be set aside. It was

contended that both claims were allowed in the absence of any primary

or contemporaneous evidence establishing that the expenditure claimed

was in actual incurred by the respondent. The award, therefore, travels

beyond the record and warrants interference by this Court.

45. Learned Senior Counsel submitted that claim 12A was allowed

solely on the basis of Annexure 12A appended to the Statement of

Claims, which was merely a self-prepared document based entirely on

unilateral calculations. In the absence of supporting material such as

bank statements, payment records or vouchers, etc., such a document

could not constitute proof of expenditure incurred. Reliance was placed

on SJVN v. Jaiprakash Hyundai Consortium and Others

18

, wherein it

18

2023 SCC OnLine Del 4039

FAO(OS)(COMM) 210/2022 Page 17 of 57

was held that arbitral awards founded merely on mathematical

assumptions or theoretical models without supporting pleadings or

cogent evidence are unsustainable.

46. With respect to claim 12B, learned Senior Counsel submitted that

the award proceeds purely on the application of the Emden Formula to

charts appended as Annexures 12B and 12C, which were again prepared

unilaterally by the respondent to demonstrate actual loss suffered on

account of delay attributable to the appellant. Reliance was placed on

Unibros v. All India Radio

19

, Batliboi Environmental Engineers Ltd.

v. Hindustan Petroleum Corporation. Ltd.

20

, K.R. Builders Pvt. Ltd.

v. DDA

21

, to contend that formulae such as Hudson or Emden cannot

be applied in vacuum, and that the contractor must prove availability of

alternative business opportunities and actual diversion of resources.

47. It was further submitted that the award of financing charges in

respect of claims 1, 2, 4A, 4B, 4C, 5, 6B, 9C 10 and 13 is patently

illegal, contrary to the contract terms and amounts to re-writing its

terms. Clause 14.8 cannot be read in isolation; it must be read along

with clauses 14.3, 14.6 and 14.7 forming part of the payment

mechanism under clause 14.

48. Upon a holistic reading of the clauses14.3, 14.6, 14.7 and 14.8, it

was submitted that the contractor becomes entitled to financing charges

only where, (i) an application for payment is submitted under Clause

19

2023 SCC OnLine SC 1366

20

(2024) 2 SCC 375

21

2012 SCC OnLine Del 1625

FAO(OS)(COMM) 210/2022 Page 18 of 57

14.3, (ii) the engineer issues an IPCs under Clause 14.6, and (iii) despite

such certification, payment is delayed beyond the stipulated period

under Clause 14.7. Reliance was placed on South East Asia Marine

Engg. & Constructions Ltd. (SEAMEC LTD.) v. Oil India Ltd.

22

, to

contend that contractual clauses must be construed in their entirety, and

no term may be applied divorced from its contractual context.

49. It was argued that the respondent produced neither applications

for IPCs under clause 14.3 nor any payment certificates under clause

14.6. The claims rested solely on self-generated annexures reflecting

hypothetical calculations. It was contended that the learned Arbitrator

ignored the absence of these foundational documents, thereby

overlooking essential contractual requirements and granted financing

charges as if they were interest on disputed claims. Learned Senior

Counsel relied on Delhi Metro Rail Corporation Ltd. v. Delhi Airport

Metro Express Pvt. Ltd

23

, to submit that an award ignoring vital

evidence or contractual stipulations amounts to perversity.

50. He further emphasized that the cascading effect of such

erroneous computation is manifest as financing charges alone constitute

to Rs.22,60,34,141/- out of a total arbitral award of Rs.38,00,97,929/-,

far exceeding the principal sum of Rs.15,40,63,788/-, thereby

demonstrating gross arbitrariness.

51. It was further argued that though the learned Single Judge

recorded that financing charges were confined to admitted or certified

22

(2020) 5 SCC 164.

23

2024 SCC OnLine SC 522

FAO(OS)(COMM) 210/2022 Page 19 of 57

dues, the award was nevertheless upheld. This, it was argued, amounted

to re-writing the contract by converting financing charges into interest,

despite lack of contractual sanction, which is impermissible.

52. Reliance was placed on Union of India and Others v. Bharat

Enterprise

24

, Union of India v. Manraj Enterprises

25

, State of

Chhattisgarh and another v. SAL Udyog (P) Ltd.,

26

, Indian Oil

Corporation. Limited v. Shree Ganesh Petroleum Rajgurunagar

27

,

and Bharat Coking Coal Ltd. v. Annapurna Construction

28

, to assert

that where the contract expressly regulates financial liability, deviation

from its terms renders the award unsustainable.

53. Learned Senior Counsel further contended that all claims were ex

facie time-barred. The cause of action arose on 28.01.2009 and expired

on 27.01.2012. Therefore, the learned Single Judge erred in treating the

disputes as live until 08.02.2013.

54. Relying on Geo Miller & Co. (P) Ltd. v. Chairman, Rajasthan

Vidyut Utpadan Nigam Ltd.

29

, it was argued that negotiations or

settlement discussions cannot continue indefinitely and that a “breaking

point” occurred when execution of the DAA was deferred at

respondent’s request vide letter dated 28.01.2009, thereby triggering the

commencement of limitation.

55. It was further submitted that the subsequent letters dated

24

2023 SCC OnLine SC 369.

25

(2022) 2 SCC 311.

26

(2022) 2 SCC 275

27

(2022) 4 SCC 463.

28

(2003) 8 SCC 154.

29

(2020) 14 SCC 643.

FAO(OS)(COMM) 210/2022 Page 20 of 57

01.09.2011, 20.06.2012 and 08.10.2013, were unrelated to the

contractual disputes and pertained to O&M, thus incapable of reviving

limitation. Once limitation expired on 27.01.2012, it could not be

revived by subsequent consent, as held in Extramarks Education India

Private Limited v. Shri Ram School and Another

30

that the consent of

parties cannot revive an already time barred claim.

56. Learned Senior Counsel further assailed the impugned award in

respect of claims 4C, 9A, 9B and 9C, contending that the claims were

allowed without due application of mind and are therefore perverse and

irrational. It was contended that, with respect to claim 4C, Annexure E

itself records that the entire mobilisation advance stood fully adjusted

by the 23

rd

RA Bill. Despite this admitted position, financing charges

continued to be awarded, which is contrary both to the factual record

and the express terms of the contract.

57. As regards claim 9C, it was also submitted that, even assuming

there was a delay in the release of the mobilisation advance, such delay

was limited to a period of one month. Nonetheless, financing charges

were awarded up to 05.03.2018, i.e., up to the date of the Award, and

thereafter until payment, which is contrary to the contractual framework

and wholly unjustified.

58. Per contra, Mr. Amit Sibal, learned Senior Counsel for the

respondent, at the very threshold, objected to the appellant raising fresh

challenge to the claims 12A and 12B, contending that no specific

grounds in respect thereof were pleaded under Section 34 of the A&C

30

2022 SCC Online Del 3123.

FAO(OS)(COMM) 210/2022 Page 21 of 57

Act, and therefore such a challenge cannot be permitted to be raised for

the first time in appellate proceedings. It was submitted that

proceedings under Section 34, being summary in nature, permit

examination only of grounds specifically pleaded therein. Reliance was

placed on Sidhi Industries and Ors. v. Religare Finvest Limited and

Ors.

31

and Media Asia (P) Ltd. v. Prasar Bharti

32

, where as per the

learned Senior Counsel, the Co-ordinate benches of this Court have held

that the limited scope of Section 37 does not permit re-agitation of

unpleaded challenges. Thus, having failed to raise these grounds at the

appropriate stage, the appellant cannot now be allowed to raise them for

the first time in an appeal under Section 37. Such an attempt would

amount to permitting a party to improve its case at the appellate stage,

which is contrary to settled principles governing proceedings under

Section 37.

59. Reliance was further placed on OPG Power Generation Private

Limited v. Enexio Power Cooling Solutions India Private Limited and

Another

33

and Punjab State Civil Supplies Corporation Limited and

Another v. Sanman Rice Mills and Others

34

, to submit that the scope

under Section 37 is even narrower than Section 34, and is akin to

supervisory or revisionary jurisdiction, limited to examining whether

the Court below exceeded or failed to exercise jurisdiction. Therefore,

it was submitted that re-appreciation of facts or substitution of

conclusions is impermissible at this stage.

31

2017 SCC OnLine Del 12685

32

2012 SCC OnLine Del 2739

33

(2025) 2 SCC 417

34

2024 SCC OnLine SC 2632

FAO(OS)(COMM) 210/2022 Page 22 of 57

60. On merits, learned Senior Counsel submitted that claim 12A was

duly supported by Annexure 12A, which comprised extracts from

audited accounts, duly certified by a Chartered Accountant, and drawn

from, as well as reconcilable with, the audited books of account, which

were never disputed by the appellant. The learned Arbitrator, in

paragraph 39.4.2, expressly noted this aspect. It was further submitted

that the appellant never challenged the authenticity of these documents

in its Statement of Defence and is, therefore, estopped from doing so at

this stage.

61. It was further submitted that Annexure 12A constitutes

admissible secondary evidence under Section 65(g) of the Indian

Evidence Act, 1872

35

(now Section 60(g) of Bharatiya Sakshya

Adhiniyam, 2023). It was premised on the fact that the said annexure

consolidates voluminous data such as manpower deployment,

machinery utilization, and monthly expenditure incurred during the

overrun period, and has consistently been recognized in construction

arbitrations as a valid evidentiary method. Reliance was placed on

NHAI v. CEC-HCC Joint Venture

36

and NHAI v. Hindustan

Construction Company Ltd.

37

, where the claims were ultimately

allowed by the learned Arbitral Tribunal by relying inter alia, on the

Chartered Accountant's certificate produced by the contractor.

62. It was further emphasised that the learned Arbitrator did not

mechanically accept the figures, but applied contractual and statutory

35

“IE Act”, hereinafter

36

2017 SCC OnLine Del 7593

37

2016 SCC OnLine Del 1144

FAO(OS)(COMM) 210/2022 Page 23 of 57

filters, restricting manpower costs to one Graduate Engineer and three

Watchmen under Clauses 4.3 and 4.22, restricting machinery costs to

the batching plant under Clause 2.3, applying the relevant DSR rates,

and finally reducing the entire assessed amount by 50% towards idling.

Thus, against a claim exceeding Rs. 10.56 crores, only Rs. 3.68 crores

stood awarded, thereby demonstrating a reasoned and conservative

assessment

63. As regards claim 12B, it was submitted that the award relates not

to loss of profits but to overhead and head-office expenses attributable

to delays caused by the appellant. The learned Arbitrator expressly

declined to adopt the Emden Formula and instead awarded only 5% of

the work value executed beyond stipulated completion, consistent with

Central Public Works Department

38

circulars under clause 12.3.

Reliance was placed on National Highways Authority of India v. M/s

Prakash Atlanta (JV)

39

; and Union of India v. Rama Construction

Company

40

, and OPG Power (supra), to submit that once the arbitrator

adopts a plausible view grounded in contractual terms, interference is

unwarranted.

64. On Financing charges, learned Senior Counsel submitted that the

award has been passed strictly within the contractual framework, and

such charges are not interest on unliquidated damages, but contractual

compensation for delayed payment. Clauses 14.3, 14.6, 14.7 and 14.8

constitute mechanism for valuation, certification and timing of

payments. Clause 14.8 operates when payments falling under Clause

38

“CPWD”, hereinafter

39

2018 SCC OnLine Del 8327

40

2022 SCC OnLine Del 1016

FAO(OS)(COMM) 210/2022 Page 24 of 57

14.3 remain unpaid beyond stipulated time. Financing charges accrue

even if IPCs are not issued by the appellant, and the appellant cannot

benefit from its failure to certify when the learned Arbitrator awarded

such claim exercising its power under clause 20 of the contract.

65. Reliance was placed on Nabha Power Limited v. Punjab State

Power Corporation Limited and Another

41

and Adani Power

(Mundra) Limited v. Gujarat Electricity Regulatory Commission and

Others

42

and Municipal Committee Katra and Others v. Ashwani

Kumar

43

to reinforce the principle that contracts must be enforced as

written and no party may take advantage of its own wrong. Therefore,

both the learned Arbitrator and the learned Single Judge, rightly upheld

the award of financing charges in terms of the contract.

66. On limitation, it was urged that the cause of action for invoking

arbitration does not accrue until pre-arbitral procedures under Clause

20 of the contract stand exhausted. It was contended that the DAB

process could not be unilaterally terminated and came to an end only on

05.03.2018 by mutual closure, whereafter the period of limitation

commenced. In this regard, reliance was placed on a judgment of this

Court in Welspun Enterprises Ltd. v. NCC Ltd.

44

and B and T AG v.

Ministry of Defence

45

.

67. Learned Senior Counsel further submitted that no “breaking

point” arose in 2009. The parties continued sincere negotiations,

41

(2018) 11 SCC 508

42

(2019) 19 SCC 9

43

2024 SCC OnLine SC 840

44

2022 SCC OnLine Del 3296

45

(2024) 5 SCC 358

FAO(OS)(COMM) 210/2022 Page 25 of 57

reflected in letters dated 01.09.2011 and 20.06.2012 repeatedly urging

execution of the DAA. Reliance was placed on Geo Miller (supra),

which recognizes exclusion of time spent in bona fide negotiations.

68. The appellant’s contention that the aforesaid letters relate only to

O&M was specifically denied, it being pointed out that the work order

was on a turnkey basis, encompassing civil works, E&M and O&M,

and that there was no separate or independent O&M contract.

69. Learned Senior Counsel further argued that challenges to claims

4C, 9A, 9B, and 9C cannot now be entertained, as such objections were

neither pleaded nor urged before the Court under the Section 34

petition. It was submitted that, having elected not to contest these claims

at the earlier stage, the appellant is barred from reopening such issues

at the appellate stage.

70. With respect to claim 4C, learned Senior Counsel contended that

the mobilization advance was contractually required to be recovered at

the rate of 10% on a pro-rata basis, whereas the appellant made excess

and premature deductions. Accordingly, the award of financing charges

was confined only to amounts prematurely withheld and was strictly in

accordance with the contractual stipulations.

71. It was further submitted that in respect of claims 9A, 9B and 9C,

the learned Arbitrator, upon appreciation of evidence, rightly awarded

the unpaid contractual dues and the corresponding financing charges

under Clause 14.8, and such findings, being factual and plausible,

warrant no interference.

FAO(OS)(COMM) 210/2022 Page 26 of 57

72. In rebuttal, learned Senior Counsel for the appellant submitted

that the objection regarding the absence of any challenge to claims 12A

and 12B is misconceived. It was contended that specific challenges

were, in fact, raised in Grounds H and FF of the Section 34 petition,

alleging lack of evidence and arbitrary assessment. The appellant,

therefore, cannot be faulted on this count.

73. Without prejudice, learned Senior Counsel submitted that

Section 34(2) of the A&C Act confers statutory power upon the Court

to set aside an arbitral award where it suffers from patent illegality and

violates fundamental policy of Indian law, irrespective of the manner in

which such grounds are pleaded. It was further submitted that the Court

is duty-bound to strike down awards that are ex facie contrary to law.

Reliance was placed on Sal Udyog (supra).

74. It was further submitted that the Chartered Accountant

certificates relied upon by the respondent do not establish actual

expenditure, as they merely certify tax computations without verifying

supporting vouchers, invoices, wage registers or deployment records.

The respondent’s reliance on CEC-HCC Joint Venture (supra) and

Hindustan Construction Co. Ltd (supra) was distinguished, on the

ground that in those cases the certifications were tied to

contemporaneous account records and jointly verified site registers,

which are conspicuously absent in the present case.

75. Learned Senior Counsel argued that alleged compliance with

clause 14 was shown, if at all, only in relation to claim 9A and 9B. For

FAO(OS)(COMM) 210/2022 Page 27 of 57

all other claims where financing charges were awarded, there was no

demonstration of compliance of Clause 14 of the contract. Further, it

was submitted that learned Single Judge had re-written the contract by

upholding financing charges as “interest”, which was alleged to be alien

to the contract and hence it was contended that Clause 14.8 could not

be invoked to grant the Financing charges. The above position was

argued even for claim 9A and 9B.

76. Learned Senior Counsel submitted that the letters dated

01.09.2011 and 20.06.2012 primarily concern non-payment of O&M

dues and contain unilateral request for execution of the DAA, with no

response. Even the respondent, while invoking DAB, referred back to

the letter dated 28.01.2009, thereby acknowledging that subsequent

correspondence was unrelated and incapable of extending limitation.

77. Finally, it was submitted that Clause 20 does not envisage

perpetual continuation of the DAB process. By seeking deferment on

28.01.2009, the respondent effectively abandoned the contractual

mechanism, bringing it to an end and triggering limitation. Permitting

otherwise would defeat settled law governing limitation and finality in

commercial transactions.

ANALYSIS AND CONCLUSION

78. We have carefully considered the submissions advanced by

learned Senior counsel for parties and have meticulously examined the

material placed on record.

FAO(OS)(COMM) 210/2022 Page 28 of 57

79. Before entering into the merits of the controversy, it is necessary

to first delineate the scope and contours of judicial interference in

proceedings arising under Section 34 and 37 of the A&C Act:

“34. Application for setting aside arbitral award. -(1) Recourse to

a Court against an arbitral award may be made only by an

application for setting aside such award in accordance with

subsection (2) and sub-section (3).

(2) An arbitral award may be set aside by the Court only if-

(a) the party making the application establishes on the basis

of the record of the arbitral tribunal that-

(i) a party was under some incapacity; or

(ii) the arbitration agreement is not valid under the

law to which the parties have subjected it or, failing

any indication thereon, under the law for the time

being in force; or

(iii) the party making the application was not given

proper notice of the appointment of an arbitrator or

of the arbitral proceedings or was otherwise unable

to present his case; or

(iv) the arbitral award deals with a dispute not

contemplated by or not falling within the terms of the

submission to arbitration, or it contains decisions on

matters beyond the scope of the submission to

arbitration:

Provided that, if the decisions on matters submitted

to arbitration can be separated from those not so

submitted, only that part of the arbitral award which

contains decisions on matters not submitted to

arbitration may be set aside; or

(v.) the composition of the arbitral tribunal or the

arbitral procedure was not in accordance with the

agreement of the parties, unless such agreement was

in conflict with a provision of this Part from which

the parties cannot derogate, or, failing such

agreement, was not in accordance with this Part; or

(b) the Court finds that—

(i) the subject-matter of the dispute is not capable of

settlement by arbitration under the law for the time

being in force, or

(ii) the arbitral award is in conflict with the public

policy of India.

37. Appealable orders.—(1) (Notwithstanding anything contained in

any other law for the time being in force, an appeal) shall lie from

the following orders (and from no others) to the court authorised by

FAO(OS)(COMM) 210/2022 Page 29 of 57

law to hear appeals from original decrees of the Court passing the

order, namely:

(a) refusing to refer the parties to arbitration under Section

8;

(b) granting or refusing to grant any measure under Section

9;

(c) setting aside or refusing to set aside an arbitral award

under Section 34.)

(2) An appeal shall also lie to a court from an order of the arbitral

tribunal—

(a) accepting the plea referred to in sub-section (2) or sub

section (3) of Section 16; or

(b) granting or refusing to grant an interim measure under

Section 17.

(3) No second appeal shall lie from an order passed in appeal under

this section, but nothing in this section shall affect or take away any

right to appeal to the Supreme Court.”

80. A plain reading of Section 34 of the A&C Act makes it evident

that the power of the Court to interfere with an arbitral award is

extremely limited. Section 34 does not permit the Court to sit in appeal

over the findings of the Arbitral Tribunal. The Court is not expected to

re-appreciate evidence, reassess factual findings, or substitute its own

view merely because an alternative view is possible. Even if the award

appears unreasoned or partially non-speaking, that by itself, does not

furnish a ground for interference unless the award is shown to fall

within one of the narrowly defined statutory grounds. Thus, the

correctness or reasonableness of the conclusions reached by the

Arbitrator is ordinarily beyond the scope of judicial scrutiny under

Section 34.

81. It is now well-settled that the jurisdiction exercised under Section

34 of the A&C Act is neither appellate nor revisional in nature. The

arbitral award may be challenged only within the narrow confines

expressly stipulated in sub-sections (2), (2A) and (3) of Section 34,

FAO(OS)(COMM) 210/2022 Page 30 of 57

including grounds such as incapacity of parties, lack of jurisdiction,

conflict with public policy, or patent illegality appearing on the face of

the award (in a domestic arbitration). The merits of the dispute are,

therefore, insulated from judicial review. Correspondingly, the

appellate jurisdiction under Section 37 is even more restricted, being

confined only to examining whether the Court deciding the Section 34

petition acted within the limits prescribed by law. The Appellate Court,

while exercising powers under Section 37, cannot re-evaluate evidence,

revisit factual determinations, or decide whether the Arbitral Tribunal’s

conclusions were right or wrong, as permissible in a regular appeal.

82. In Haryana Tourism Limited v. M/s. Kandhari Beverages Ltd

46

,

the Hon’ble Supreme Court reaffirmed that a Court exercising power

under Section 37 cannot travel into the merits of the dispute. An arbitral

award can be interfered with only if it is shown to be contrary to the

fundamental policy of Indian law, the interests of India, justice or

morality, or if it suffers from patent illegality going to the root of the

matter. Mere errors of fact or appreciation of evidence do not justify

judicial intervention.

83. In light of the settled legal position, this Court is of the considered

view that the scope of review under Section 37(1)(c) of the A&C Act,

while examining an order passed under Section 34, is extremely

circumscribed. The appellant, therefore, carries a very heavy burden

and must demonstrate a clear case of jurisdictional error, violation of

statutory mandate, or patent illegality apparent on the face of the record,

46

(2022) 3 SCC 237

FAO(OS)(COMM) 210/2022 Page 31 of 57

in order to justify interference. Within this narrowly confined

framework, the present appeal calls for consideration of the following

issues-

i. Whether claims 12A and 12B were awarded in the impugned

award without any supporting evidence, and if so, whether

such findings constitute patent illegality warranting

interference by this Court.

ii. Whether the award of ‘Financing Charges’ in respect of

claims 1, 2, 4A, 4B, 4C, 5, 6B, 9B, 9C, 10 and 13 is patently

illegal, contrary to contractual provisions, or inconsistent with

the fundamental policy of Indian law.

iii. Whether the claims allowed by the arbitral tribunal were ex-

facie barred by limitation and, if so, whether the learned

Arbitral Tribunal committed a manifest error in law in

entertaining and awarding such time-barred claims?

Issue 1- CLAIM 12A AND 12B

84. Claim 12A pertains to the alleged additional expenditure incurred

during the period of overrun/prolongation of the contract, consisting of

(i) manpower expenses at site and (ii) hire/idling charges of plant and

machinery. In substance, the claim represents compensation for site

overheads and idling costs allegedly suffered on account of

prolongation of works beyond the stipulated completion period.

85. Claim 12B, on the other hand, pertains to the alleged loss of off-

site/Head Office overheads and profit during the prolongation period.

The claim proceeds on the premise that the project delay resulted in

FAO(OS)(COMM) 210/2022 Page 32 of 57

continued deployment of head office establishment and blocking of the

contractor’s profit element, thereby giving rise to an entitlement for

compensation under this head.

86. The learned arbitrator allowed claim 12A primarily on the basis

of Annexure 12A appended to the Statement of Claims. It was asserted

that the said Annexure had been authenticated by a Chartered

Accountant, and proceeding on that premise, the learned sole Arbitrator

accepted it as reliable evidence and accordingly granted the claim 12A

in favour of the respondent.

87. Learned Senior Counsel for the appellant argued that the Court

exercising jurisdiction under Section 34, while upholding the impugned

Award on claims 12A and 12B, failed to assign any reasons or to

examine the specific challenges raised by the appellant,

notwithstanding the fact that the impugned award itself contains a

detailed and reasoned analysis. According to the appellant, such an

approach amounts to failure on the part of the Section 34 Court to

exercise the jurisdiction, thereby rendering the order vulnerable on the

ground of patent illegality.

88. It was further contended that both claim 12A and 12B were

allowed in the absence of any substantive evidence and therefore suffer

from patent illegality.

89. Before examining whether the impugned award is vitiated, it is

apposite to recapitulate and delineate the scope of “patent illegality”

under Section 37 read with Section 34 of the A&C Act.

FAO(OS)(COMM) 210/2022 Page 33 of 57

90. It is now settled that patent illegality constitutes a ground for

setting aside an award under Section 34(2A) of the A&C Act. However,

such illegality must be apparent on the face of the award, and not one

that requires reappreciation of evidence or a merit based review.

91. In Delhi Airport Metro Express (P) Ltd. (supra), the Hon’ble

Supreme court made the following observations. The same reads as

follows:

“39. In essence, the ground of patent illegality is available for

setting aside a domestic award, if the decision of the arbitrator is

found to be perverse, or so irrational that no reasonable person

would have arrived at it; or the construction of the contract is such

that no fair or reasonable person would take; or, that the view of the

arbitrator is not even a possible view. A “finding” based on no

evidence at all or an award which ignores vital evidence in arriving

at its decision would be perverse and liable to be set aside under the

head of “patent illegality”. An Award without reasons would suffer

from patent illegality. The arbitrator commits a patent illegality by

deciding a matter not within his jurisdiction or violating a

fundamental principle of natural justice.”

(Emphasis supplied)

92. Thus, it could be understood that patent illegality refers to such

an error that is obvious, self-evident and goes to the root of the matter,

offending substantive provisions of law, principles of natural justice, or

reflecting a decision based on “no evidence”, thereby warranting

judicial interference.

93. In Ssangyong Engineering & Construction Co. Ltd. v. NHAI

47

,

it was held that “Thus, a finding based on no evidence at all or an award

47

(2019) 15 SCC 131

FAO(OS)(COMM) 210/2022 Page 34 of 57

which ignores vital evidence in arriving at its decision would be

perverse and liable to be set aside on the ground of patent illegality”.

94. Further, on perversity of an arbitral award, the Hon’ble Supreme

Court in its decision in Associate Builders v. Delhi Development

Authority

48

held as follows:

“31. The third juristic principle is that a decision which is perverse

or so irrational that no reasonable person would have arrived at the

same is important and requires some degree of explanation. It is

settled law that where:

(i) a finding is based on no evidence, or

(ii) an Arbitral Tribunal takes into account something

irrelevant to the decision which it arrives at; or

(iii) ignores vital evidence in arriving at its decision, such

decision would necessarily be perverse.”

95. The Hon’ble Supreme Court has consistently held that where an

arbitral award is based on no evidence or ignores vital evidence, such

illegality goes to the foundation of the Award and amounts to patent

illegality. However, a mere erroneous application of law or re-

appreciation of evidence is impermissible within the limited scope of

interference under Section 34 or Section 37 of the A&C Act.

96. The primary grievance of the appellant, therefore, is that claim

12A was awarded merely on the basis of a “put up calculation”, without

any supporting evidence.

48

(2015) 3 SCC 49

FAO(OS)(COMM) 210/2022 Page 35 of 57

97. The learned Arbitral Tribunal attached significant weight to the

Chartered Accountant’s certificate. Hence, we deem it relevant to

reproduce the Chartered Accountant certificates relied on by the learned

arbitrator:

“TO WHOMSOEVER IT MAY CONCERN

This is to certify that M/s Mohini Electricals Ltd., WZ-263, Railway

Road, Srinagar, Delhi-110034 discharged their tax liability with

respect to DVAT as well as Service Tax as per its applicability

during the Financial Year period 2004-05 to 2012-13 víz. 12.5%

under DVAT for the entire corresponding period & Service Tax

12.24% w.e.f. 18/04/2006 to 10/05/2007, 12.36% w.e.f. 11/05/2007

to 23/02/2009 and 10.3% w.e.f. 24/02/2009 to 31/03/2012 including

the payments pertaining to Delhi Jal Board works of Contract of

UGR & BPS at various location in Trans-Yamuna Area. It is further

confirmed that M/s Mohini Electricals Ltd. has declared the entire

receipts of payments for the Project.

For V.D. BISHAMBHU & CO.

CHARTERED ACCOUNTANTS

(F.C.A. V.D. BISHAMBHU)

(PROP.)

M.No. F-004303

Place: New Delhi

Date: 31.03.2016”

98. Upon scrutiny, it is evident that the certificates attached in

Annexure 1D and 2B only certify payment of taxes and receipts of

amounts. They neither certify, authenticate, audit, nor verify the

expenditure allegedly incurred during the period of prolongation, which

forms the very basis of claim 12A.

99. It is thus evident that there is no material before the learned

Arbitrator to show that the Chartered Accountant even certified or

examined the underlying books of accounts, vouchers, muster rolls,

utilization statements or any contemporaneous documents in support of

FAO(OS)(COMM) 210/2022 Page 36 of 57

Annexure 12A. Annexure 12A appears to be nothing more than a self-

prepared statement of the contractor, unsupported by any independent

verification. Self-serving documents, unsupported by corroborative

proof, cannot be treated as evidence of actual expenditure. Reliance on

such material renders the impugned award unsupported by evidence and

squarely places it within the category of a finding based on “no

evidence”.

100. The learned Senior Counsel for the respondent sought to justify

reliance on Annexure 12A by invoking Section 65(g) of the IEA,

contending that secondary evidence is admissible where original

records are voluminous. They also relied on precedents such as CEC-

HCC Joint Venture (supra) and Hindustan Construction Co. Ltd

(supra).

101. However, the said judgments are clearly distinguishable on facts.

In those cases, the Chartered Accountant’s certificates were accepted

only after it was demonstrated that the Chartered Accountant had

conducted an independent examination of account books, stock

registers, and jointly verified site records. No such verification exists or

foundational exercise is evident in the present case, nor is there any

material to indicate that certificates relied upon were based on an

examination of primary records.

102. Accordingly, the learned Arbitrator’s approach of treating

Annexure 12A as conclusive proof of expenditure, without examining

its foundation on which it rested, is legally unsustainable. The grant of

compensation in the absence of proof of actual expenditure amounts to

FAO(OS)(COMM) 210/2022 Page 37 of 57

reliance on “no evidence”, and therefore, squarely attracts the ground

of patent illegality.

103. Therefore, the Award granting claim 12A is liable to be set aside.

104. With respect to claim 12B, learned Senior Counsel for the

appellant argued that the claim was purportedly founded on the Emden

Formula and was supported only by unsubstantiated statements of Head

Office Overheads and Profit contained in Annexures 12B and 12C.

105. However, a reading of paragraph 39.4.16 of the impugned award,

reproduced below, clearly establishes that the learned Arbitrator did

not, in fact, apply any formula. Instead, claim 12B was awarded on the

basis of 5% of the value of work remaining beyond the stipulate date of

completion, quantified viz. Rs. 21,20,63,711/-.

“In view of the aforesaid discussions and findings including the

issue or delays I hold that the Claimant is entitled for this claim.

However. the use of overhead %age as 10% in Emden formulae

results in hugely exaggerated amounts. In my opinion this has

resulted due to hugely disproportionate period of prolongation of

work beyond the stipulated completion date. Thus, to be realistic,

under this claim I award 5% of the amount of work remaining

beyond the stipulate date of completion viz. Rs. 21.20,63, 711.”

106. Although the respondent referred to circulars issued by the

CPWD, which prescribe a range of 10-15%, the learned Arbitrator did

not expressly place reliance upon such circulars. Nonetheless, having

determined that delay was attributable to the appellant, and that the

respondent was required to remain mobilized during the extended

period, the learned Arbitrator considered 5% to be a reasonable measure

FAO(OS)(COMM) 210/2022 Page 38 of 57

of compensation in the facts of the case.

107. At this juncture, we deem it relevant to refer to the decision of

division bench of this court in National Highways Authority of India

v. M/s Prakash Atlanta (JV) (supra), where the application of a

standard percentage towards overhead was upheld, recognizing the

technical expertise of arbitral tribunals in adjudicating construction-

related disputes.

108. Further, the Apex court in its decision of McDermott

international INC. v. Burn Standard Co. Ltd and others

49

, held that

selection of a formula or method for calculating damages lies within the

discretion of the Arbitral Tribunal, so long as such discretion is not

exercised arbitrarily. The relevant observation reads as follows:

“106. We do not intend to delve deep into the matter as it is an

accepted position that different formulae can be applied in different

circumstances and the question as to whether damages should be

computed by taking recourse to one of the other formula, having

regard to the facts and circumstances of a particular case, would

eminently fall within the domain of the arbitrator”.

109. In the present case, the learned Arbitrator’s reasoning does not

appear perverse or irrational in our opinion. The impugned award

reflects due consideration of the factual matrix, the nature of delay, and

the entitlement to overheads during the period of prolongation. Thus,

claim 12B does not warrant interference.

110. Learned Senior Counsel for the respondent argued that claims

49

(2006) 11 SCC 181

FAO(OS)(COMM) 210/2022 Page 39 of 57

12A and 12B cannot be assailed, as no specific challenge in respect

thereof was raised before the Court exercising jurisdiction under

Section 34 of the A&C Act.

111. Per contra, the learned Senior Counsel for the appellant pointed

out that they had challenged the finding on claims 12A and 12B in

ground H and FF of the Section 34 petition, which are reproduced

below-

“H. For that the Ld. Arbitrator ignored the relevant terms of the

Contract and went beyond the same while awarding various claims.

Likewise, the assessment of evidence was wholly perverse such that

no reasonable adjudicator exercising a judicial function would have

reached.

FF. For that the primary onus to prove the claims was that of the

Respondent. The Respondent miserably failed to produce any single

document in support of their claim and therefore the impugned

award is bad in the eyes of law and is liable to be set aside.”

112. In this context, it is apposite to refer to the decision of the Apex

Court in Sal Udyog (supra), wherein the following was held-

24. We are afraid, the plea of waiver taken against the appellant-

State on the ground that it did not raise such an objection in the

grounds spelt out in the Section 34 petition and is, therefore,

estopped from taking the same in the appeal preferred under Section

37 or before this Court, would also not be available to the

respondent-Company having regard to the language used in Section

34(2A) of the 1996 Act that empowers the Court to set aside an

award if it finds that the same is vitiated by patent illegality

appearing on the face of the same. Once the appellant-State had

taken such a ground in the Section 37 petition and it was duly noted

in the impugned judgment, the High Court ought to have interfered

by resorting to Section 34(2A) of the 1996 Act, a provision which

would be equally available for application to an appealable order

under Section 37 as it is to a petition filed under Section 34 of the

1996 Act. In other words, the respondent-Company cannot be heard

to state that the grounds available for setting aside an award under

sub-section (2A) of Section 34 of the 1996 Act could not have been

invoked by the Court on its own, in exercise of the jurisdiction vested

FAO(OS)(COMM) 210/2022 Page 40 of 57

in it under Section 37 of the 1996 Act. Notably, the expression used

in the sub-rule is “the Court finds that”. Therefore, it does not stand

to reason that a provision that enables a Court acting on its own in

deciding a petition under Section 34 for setting aside an Award,

would not be available in an appeal preferred under Section 37 of

the 1996 Act.

25. Reliance placed by learned counsel for the respondent-

Company on the ruling in the case of Hindustan Construction

Company Limited(Supra) is found to be misplaced. In the aforesaid

case, the Court was required to examine whether in an appeal

preferred under Section 37 of the 1996 Act against an order refusing

to set aside an Award, permission could be granted to amend the

Memo of Appeal to raise additional/new grounds. Answering the

said question, it was held that though an application for setting aside

the Arbitral Award under Section 34 of the 1996 Act had to be moved

within the time prescribed in the Statute, it cannot be held that

incorporation of additional grounds by way of amendment in the

Section 34 petition would amount to filing a fresh application in all

situations and circumstances, thereby barring any amendment,

however material or relevant it may be for the consideration of a

Court, after expiry of the prescribed period of limitation. In fact,

laying emphasis on the very expression “the Courts find that”

applied in Section 34(2)(b) of the 1996 Act, it has been held that the

said provision empowers the Court to grant leave to amend the

Section 34 application if the circumstances of the case so warrant

and it is required in the interest of justice. This is what has been

observed in the preceding paragraph with reference to Section

34(2A) of the 1996 Act.

(Emphasis supplied)

113. Thus, although the pleadings were general, the settled legal

position remains that patent illegality, when apparent on the face of the

award, can be examined even if not specifically pleaded. Section

34(2A) confers power upon the Court to suo moto consider such

illegality, and this jurisdiction extends equally to proceedings under

Section 37, as authoritatively held in Sal Udyog (supra). Therefore, the

absence of a specific plea cannot defeat the Court’s duty to intervene

where the Award is ex facie vitiated by patent illegality.

FAO(OS)(COMM) 210/2022 Page 41 of 57

114. In light of the above discussion, in our considered view, claim

12A has been awarded without any cogent evidence and, therefore,

suffers from patent illegality. The Award, to that extent, is liable to be

set aside.

115. However, the reasoning adopted by the learned Arbitrator in

relation to claim No. 12B does not disclose any perversity, arbitrariness,

or illegality warranting interference. The challenge to claim 12B is,

therefore, rejected.

LIMITATION

116. The next contention urged by the learned Senior Counsel for the

appellant relates to limitation. It was submitted that the impugned award

is ex-facie time barred and therefore, liable to be set aside. According

to the appellant, negotiations between the parties cannot be permitted

to continue indefinitely and there must necessarily be a “breaking

point”, after which the aggrieved party is required to invoke arbitration.

It was argued that, in the present case, such breaking point arose

immediately after 28.01.2009, when the signing of DAA/DAB was

deferred, and that there is no material to show that negotiations

continued, thereafter, until 10.10.2013.

117. In support of this submission, reliance was placed on the

judgment of the Hon’ble Supreme Court in Geo Miller (supra). The

Hon’ble Supreme Court held that, while computing limitation for

invoking arbitration under the A&C Act, the period spent by parties in

bona fide negotiations may be excluded, provided that such

FAO(OS)(COMM) 210/2022 Page 42 of 57

negotiations are real and demonstrable. Importantly, the Court

emphasized that the adjudicating forum may identify the “breaking

point” i.e., the stage at which any reasonable party would conclude that

amicable settlement is no longer possible and would instead proceed to

arbitration. Thus, such breaking point constitutes the date from which

limitation commences.

118. Proceeding on this basis, the appellant contended that after the

DAA/DAB signing was deferred vide letter dated 28.01.2009, there was

no substantive correspondence concerning adjudication of disputes

until the respondent’s letter dated 10.10.2013, whereby execution of the

DAB/DAA was requested. It was, therefore, urged that the limitation

period commenced on 28.01.2009 and expires three years thereafter.

According to the appellant, the respondent, by its conduct, permitted

the claims to become time-barred, remained in prolonged inaction, and

could not thereafter revive limitation by issuing subsequent

correspondence dated 10.10.2013.

119. The learned Senior Counsel for the respondent, however,

controverted this submission and drew our attention to several

communications exchanged between the parties, namely, (i) letter dated

01.09.2011, whereby a formal notice for payment was issued and the

request to proceed with the DAA was reiterated; (ii) letter dated

20.06.2012, intimating a change in staff and operational deployment,

while once again referring to the execution of the DAA; and (iii) the

earlier letter dated 28.01.2009, deferring signing of the DAA. It was

submitted that these communications clearly demonstrate that

negotiations and engagement between the parties were ongoing, and

FAO(OS)(COMM) 210/2022 Page 43 of 57

that there was no definitive “breaking point” as alleged by the appellant.

120. The learned Senior Counsel for the appellant contended that the

aforesaid communications were unrelated to the present dispute and

pertained instead to a separate O&M contract. This submission was,

however, controverted by the learned Senior Counsel for the

respondent, who pointed out that each of the said letters expressly

referred to the same turnkey project and repeatedly requested execution

of the DAA/DAB under that very contract.

121. Upon a careful perusal of the above letters, we find merit in the

respondent’s submission. The letter dated 01.09.2011 specifically urges

the appellant to “At least proceed with signing of DAA”, and is

addressed to the CEO, DJB, with a clear reference to the work order

governing the turnkey project. The scope of the said project itself

encompassed O&M obligations. Hence, said communication cannot be

dissociated or segregated from the disputes forming the subject matter

of the present arbitration.

122. Thus, it is not possible to accept the argument that the letter dated

01.09.2011 pertains to an entirely different contractual arrangement. On

the contrary, it appears to constitute a continuing part of the

negotiations and efforts undertaken by the respondent either to secure

payment or to advance adjudication of disputes through the

contractually agreed DAA/DAB mechanism.

123. Further, the letter dated 28.01.2009 indicates that both parties

remained inclined to resolve the disputes amicably. It records detailed

FAO(OS)(COMM) 210/2022 Page 44 of 57

discussions and a mutual decision to defer execution of the DAA, so as

to enable the issues to be reviewed at an appropriate level. This

communication clearly reflects a continuation of dialogue between the

parties, rather than cessation or termination of negotiations.

124. The subsequent letters dated 01.09.2011 and 20.06.2012 further

reinforce this narrative. Both make reference to the same work order

dated 30.09.2003 and repeatedly call upon the appellant to proceed with

DAA execution. These communications, taken together, demonstrate a

sustained and consistent effort on the part of the respondent to invoke

and operationalise the contractual dispute resolution mechanism, and

cannot be characterised either as isolated demands or as relating to a

distinct or independent contractual arrangement.

125. Equally significantly is the absence of any categorical rejection

by the appellant. There is no material indicating that the appellant

refused to sign the DAA or conclusively denied its liability in respect

of the disputes raised. In the absence of such an unequivocal

repudiation, the correspondence demonstrates that the parties continued

negotiations and remained engaged in addressing disputes.

Consequently, no clear or identifiable “breaking point” emerges from

the record so as to trigger the commencement of limitation.

126. Moreover, under the contractual framework, the parties had

expressly agreed that disputes would first be addressed through the

DAB mechanism before arbitration could be invoked. Where parties

consciously adopt such a tiered or staged dispute resolution, the cause

of action to invoke arbitration ordinarily arises only upon exhaustion,

FAO(OS)(COMM) 210/2022 Page 45 of 57

or failure of the stipulated pre-conditions. The contractual intent,

therefore, was that limitation would commence only upon the

breakdown, dissolution, or failure of the DAB process, and not prior

thereto.

127. The learned Single Judge has rightly observed that the award is

not vitiated by patent illegality on the question of limitation. The

respondent was consistently pursuing the agreed dispute resolution

process, and the right to seek arbitration arose only upon fulfilment of

contractual pre-conditions.

128. In light of the above discussion, and applying the principles

enunciated by the Hon’ble Supreme Court in Geo Miller (supra) and

other binding precedents, we find no perversity or illegality in the view

taken by the learned Single Judge. Accordingly, no ground is made out

to interfere with the finding on limitation.

FINANCING CHARGES

129. The learned Senior Counsel for the appellant contended that the

Contract envisages “Financing Charges” strictly within the limited

contingency contemplated under Clause 14.8, namely delayed payment

of amounts duly certified under the contractual mechanism. It was

urged that clause 14.8 cannot be read in isolation, but must necessarily

be construed in conjunction with Clauses 14.3, 14.6 and 14.7, which

together prescribe a mandatory sequence for submission of monthly

Statements by the Contractor, examination by the Engineer, and

FAO(OS)(COMM) 210/2022 Page 46 of 57

issuance of IPCs. In the absence of this contractual process, no

crystallised liability can be said to arise, and therefore, no financing

charges can be fastened upon the Employer.

130. It was further argued that, in the present case, the respondent

neither pleaded nor proved compliance with Clause 14.3, nor produced

any Applications for IPCs or the IPCs themselves as contemplated

under Clause 14.6. Instead reliance was placed on self-generated charts

and unilateral computations. In the absence of proof of certification, it

was urged that the learned Arbitral Tribunal erred in awarding financing

charges across multiple claims, thereby travelling beyond the four

corners of the Contract and granting amounts unsupported by evidence,

resulting in a manifest miscarriage of justice.

131. Before considering this contention, reference may be made to the

judgment of the Hon’ble Supreme Court in M/s. Hindustan

Construction Company Ltd. v. M/s NHAI

50

, which underscores the

settled principles that courts ordinarily refrain from re-examining

contractual interpretation by an arbitrator. While reiterating this

position, the Hon’ble Supreme Court referred to the judgment of

Associate Builders (supra), wherein it was held that the construction of

contractual terms is primarily for the arbitral tribunal, and that if the

arbitrator adopts a reasonable interpretation of the contract, the award

cannot be set aside merely because another view is possible. It was

further observed that interference is warranted where the interpretation

is so irrational or implausible that no fair-minded or reasonable person

50

(2024) 2 SCC 613

FAO(OS)(COMM) 210/2022 Page 47 of 57

could have arrived at such a conclusion.

132. Further, in PSA SICAL Terminals Pvt. Ltd. v. Board of Trustees

of V.O. Chidambranar Port Trust

51

, the Hon’ble Supreme Court

emphasised that an arbitral tribunal is bound by the contractual

framework agreed upon by the parties. The Court held that where an

award proceeds on a basis that effectively alters or rewrites the contract,

such an exercise violates fundamental principles of justice. Interference

by the Court is warranted in such cases, as the award would fall within

the exceptional category of decisions that shock the judicial conscience

and thereby attract scrutiny under the limited grounds available for

setting aside an arbitral award.

133. Bearing this position in mind, the relevant contractual provisions

regarding financing charges merit close scrutiny, and are accordingly

reproduced hereinafter:

"14.3 Application for Interim Payment Certificate:

The Contractor shall submit a statement in six copies to the

Engineer after the end of each month, in a form approved by the

Engineer, showing in detail the amounts to which the Contractor

considers himself to be entitled, together with supporting

documents which shall include the report on the progress during

this month in accordance with Sub- Clause 4.21 [Progress

Reports].

The statement shall include the following items, as applicable,

which shall be expressed in the various currencies in which the

Contract Price is payable, in the sequence listed:

a) the estimated contract value of the works executed and the

Contractor's documents produced up to the end of the month

(including variations but excluding items described in

subparagraphs (b) to (g) below);

51

(2023) 15 SCC 781

FAO(OS)(COMM) 210/2022 Page 48 of 57

b) any amounts to be added and deducted for changes in legislation

and changes in cost, in accordance with Sub- Clause 13.7

[Adjustments for changes in Legislation] and Sub-Clause 13.8

[Adjustments for changes in Cost];

c) any amount to be deducted for retention, calculated by applying

the percentage of retention stated in the Appendix to Tender to the

total of the above amounts, until the amount so retained by the

Employer reaches the limit of Retention Money (if any) stated in the

Appendix to Tender;

d) any amounts to be added and deducted for the advance payment

and repayments in accordance with Sub-Clause 14.2 [Advance

Payment];

e) any amounts to be added and deducted for Plant and Materials

in accordance with Sub-Clause 14.5 [Plant and Materials intended

for the Works];

f) any other additions or deductions which may have become due

under the Contract or otherwise, including those under Clause 20

[Claims, Disputes and Arbitration];

Sub-Clause 14.6:Issue of Interim Payment Certificates: …..The

Engineer may in any Payment certificate make any correction or

modification that should properly be made to any previous Payment

Certificate....

"14.7 Payment:

The Employer shall pay to the Contractor:

a) the first instalment of the advance payment within 42 days after

issuing the Letter of Acceptance or within 21 days after receiving

the documents in accordance with Sub- Clause 4.2 [Performance

Security] and Sub-Clause 14.2 [Advance Payment], whichever is

later;

b) the amount certified in each interim Payment Certificate within

56 days after the Engineer receives the Statement and supporting

documents; and

FAO(OS)(COMM) 210/2022 Page 49 of 57

c) the amount certified in the Final payment Certificate within 56

days after the Employer receives this Payment Certificate.

Payment of the amount due in each currency shall be made

into the bank account, nominated by the Contractor, in the

payment country (for this currency) specified in the Contract. "

"14.8: Delayed Payment:

If the Contractor does not receive payment in accordance with Sub-

Clause 14.7 [Payment], the Contractor shall be entitled to receive

financing charges compounded monthly on the amount unpaid

during the period of delay. This period shall be deemed to commence

on the date for specified in Sub-Clause 14.7 [Payment], irrespective

(in the case of its sub-paragraph (b)) of the date on which any

Interim Payment Certificate is issued.

Unless otherwise stated in the Particular Conditions, these

financing charges shall be calculated at the annual rate of three

percentage points above the discount rate of the central bank in the

country of the currency of payment, and shall be paid in such

currency.

The Contractor shall be entitled to this payment without formal

notice or certification and without prejudice to any other right or

remedy. "

134. The learned Arbitral Tribunal proceeded on the premise that

entitlement to financing charges under clause 14.8 extends beyond

admitted or certified amounts and may include all sums that could

notionally fall within clause 14.3(a) to (g). On this basis, it held that

once an amount is said to fall within clauses 14.3, any delay in payment

beyond the period stipulated under clause 14.7 would automatically

attracts financing charges.

135. Such an approach, however, overlooks the plain structure and

scheme of the contract. Clauses 14.3, 14.6 and 14.7, when read together,

establish a clear and sequential framework: (i) submission of a

FAO(OS)(COMM) 210/2022 Page 50 of 57

Statement by the Contractor, (ii) examination and determination by the

Engineer, and (iii) certification of the determined amount through an

IPCs. It is only upon such certification that the Employer’s obligation

to make payment crystallises, and clause 14.7 merely governs the time

frame for discharge of this crystallised obligation.

136. Clause 14.3, properly construed, serves only to identify the

categories or heads of claims that may be included in a Statement

submitted for scrutiny; it does not, by itself, render any amount due or

payable. To construe clause 14.3 as creating an automatic entitlement

to payment would convert tentative and unverified claims into

enforceable liabilities, thereby undermining the very purpose of

examination and certification by the appellant mandated under clause

14.6.

137. Even in respect to the release of advance payment, there is a

contractual pre-condition for compliance under clause 14.2 which

mandates the submission of a statement and the issuance of an IPCs.

The clause provides that only after the contractor submits a statement

under clause 14.3 and after the employer receives both the performance

security and the advance payment guarantee, the Engineer “shall issue

an interim payment certificate for the first instalment” after which such

amount becomes due.

138. Further, the concluding words of clause 14.8, referring to the levy

of financing charges “without formal notice or certification”, cannot be

read as dispensing with the requirement of certification altogether. The

said phrase operates only after the underlying sum has already attained

FAO(OS)(COMM) 210/2022 Page 51 of 57

the status of an amount lawfully payable under the contract. It merely

obviates the need of issuing further procedural notices once liability has

stood crystallised. To construe this phrase as creating an independent

or substantive entitlement to financing charges would amount to a re-

writing of the Contract, which is impermissible at this stage.

139. Consequently, in the absence of certification or determination by

the Engineer, there can be no concluded or crystallised liability, and

therefore, no legal basis for imposition of financing charges in the

impugned award. The expression “irrespective of the date on which any

Interim Payment Certificate is issued”, cannot be construed as

legitimising claims that were never subjected to the certification

process. Its true purpose is only to guard against deliberate or undue

administrative delay in issuing certificates after the entitlement has

otherwise been determined.

140. Therefore, award of financing charges provided under clauses

14.7 and 14.8 apply only to amounts actually admitted or certified in

accordance with the Contract by the appellant and not to the disputed/

revised claims on which liability was affixed on the appellant at the later

stage by the learned Arbitrator in exercise of its power provided under

clause 20.6. The absence of certification is fatal to any claim for

financing charges. Any broader interpretation would expose the

Employer to financing charges revised, unverified or disputed claims

later affixed on the appellant, a consequence clearly not contemplated

by the parties at the time of contract.

141. Having accepted the principle that financing charges under

FAO(OS)(COMM) 210/2022 Page 52 of 57

clause 14.8 are payable only in respect of admitted or certified amounts,

the learned Single Judge could not have upheld the award of financing

charges on amounts which admittedly stood not certified under the

contractual mechanism. As per the contract, financing charges are

triggered by delay in payment of certified dues, not by delay in

processing of the claims that were never certified.

142. The learned Single Judge permits the levy of financing charges

in circumstances not contemplated by clause 14, and thereby extends

the contractual obligation of the employer on the payments that ought

to be paid. Such an approach is not protected by the principle of judicial

restraint under Section 34, as it results in enforcement of a liability

outside the four corners of the contract.

143. Viewed in this backdrop, the interpretation adopted by the

learned Arbitral Tribunal disregards the mandatory certification

requirement, impermissibly expands clause 14.8 beyond its legitimate

scope, and results in awarding financing charges on amounts that never

crystallised into payable sums. Such an interpretation runs contrary to

the plain contractual text and offends the settled principle that an

arbitrator cannot rewrite the commercial bargain between the parties.

144. The impugned award, therefore, suffers from patent illegality

going to the root of the matter. By granting financing charges without

proof of certification or crystallised liability, the learned Arbitral

Tribunal has effectively dispensed with a mandatory contractual pre-

conditions of submission of application and certification provided in the

contract for the purpose of financing charges. Such an approach does

FAO(OS)(COMM) 210/2022 Page 53 of 57

not amount to a mere erroneous interpretation but adopting an

interpretation that specifically disregards the mandatory pre-conditions

provided in the contract. The impugned award, to that extent, warrants

interference of this Court, and the financing charges so awarded are

liable to be set aside.

145. Claim 9B pertains to financing charges on delayed payments.

The requisite bills were shown to be submitted, and the appellant raised

objections only with respect to the dates of submission of the bills. The

learned Arbitrator examined both the dates of submission of the bills

and the dates on which payments were released and found that

payments were not made within the timelines stipulated under the

contract, which timelines were not themselves in dispute. Since the

amounts were admittedly paid, the underline liability stood accepted,

leaving only a factual dispute regarding the relevant dates of procedural

compliance. In these circumstances, the learned Arbitrator rightly

awarded financing charges in accordance with the contract after

verifying the relevant dates, which warrants no interference by this

Court.

CONCLUSION

146. Insofar as claim 12A is concerned, this Court finds that the

conclusions returned by the learned Arbitral Tribunal are not founded

on any reliable or cogent evidence. The respondent has rested its claim

entirely on certain certificates purportedly issued by a Chartered

Accountant. A bare perusal of these certificates reveals that they merely

acknowledge the discharge of tax liabilities by the respondent and

record receipt of payments. They neither disclose the factual substratum

FAO(OS)(COMM) 210/2022 Page 54 of 57

of the claim nor explain the methodology adopted for computing the

amounts so certified.

147. The said certificates do not reveal the source data, underlying

books of accounts, ledgers, vouchers or any contemporaneous records

from which the figures were derived. Significantly, the Chartered

Accountant who issued the certificates was also not examined as a

witness, thereby depriving the appellant of an opportunity to test the

veracity and correctness of the contents through cross-examination. In

the absence of production of primary documentary material, the learned

Arbitral Tribunal’s implicit presumption that such certificates

constituted reliable proof of expenditure amounts, in law, to treating

“no evidence” as evidence.

148. In these circumstances, the learned Arbitral Tribunal’s

acceptance of such untested, unreasoned and unsupported certificates is

clearly unsustainable. The finding rendered in respect of Claim 12A,

therefore, stands vitiated as perverse, being based on no admissible or

legally acceptable evidence, and falls foul of the test of patent illegality

as elucidated by the Hon’ble Supreme Court in a catena of decisions.

Accordingly, the award, to that extent, warrants interference and is

liable to be set aside.

149. Turning to claim 12B, this Court finds no infirmity warranting

interference. The learned Arbitral Tribunal has recorded a clear finding,

based on the material on record, that the contract period stood extended

and that the respondent suffered consequential prolongation costs,

including extended overheads. The learned sole Arbitrator adopted a

FAO(OS)(COMM) 210/2022 Page 55 of 57

pragmatic approach by granting compensation calculated at 5% of the

value of work remaining beyond the stipulated date of completion,

which constitutes a rational and permissible method of quantification in

the facts of the case.

150. It is settled law that the arbitral forum is the final judge of the

quality and quantity of evidence, as well as the methodology adopted

for computation, and that courts exercising jurisdiction under Section

37 do not sit in appeal so as to substitute their own assessment merely

because another view is possible. Unless the quantification adopted is

demonstrated to be patently arbitrary, irrational or shocking to judicial

conscience, interference is impermissible. The impugned award insofar

as claim no. 12B is concerned is reasoned, proportionate, and firmly

anchored in the material placed before the learned Arbitral Tribunal,

and therefore merits affirmation.

151. The objection based on limitation is equally devoid of merit. The

record reveals continuous correspondence and ongoing engagement

between the parties, evidencing a clear intent to resolve the outstanding

issues, rather than to treat them as finally repudiated. In particular, the

letters dated 01.09.2011 and 20.06.2012 demonstrate that the disputes

remained alive and under active consideration. In the absence of a clear

and unequivocal repudiation, the limitation period cannot be said to

have commenced in the manner urged by the appellant. The plea of

limitation is, accordingly, rejected.

152. Lastly, with respect to financing charges, this Court finds that the

learned Arbitral Tribunal has failed to appreciate the contractual

FAO(OS)(COMM) 210/2022 Page 56 of 57

framework and the evidence on record in its proper perspective. The

award proceeds on an erroneous assumption that financing charges

were recoverable as matter of course, despite the absence of any express

contractual provision permitting such recovery in the circumstances

obtaining in the present case. By treating such charges as a natural or

consequential component of compensation, the learned Arbitral

Tribunal has, in effect, re-written the commercial bargain between the

parties, which is impermissible in law. Further, the learned Single

Judge, despite recording that financing charges were payable only in

respect of admitted or certified amounts, erred in upholding the award

of such charges.

153. Under Section 37, although the jurisdiction of this Court is

supervisory, interference is warranted where the award suffers from

perversity or patent illegality apparent on the face of the record. In the

present case, the learned Arbitral Tribunal’s conclusion on financing

charges is contrary to the express terms of the Contract and is

unsupported by any evidence demonstrating an agreed entitlement to

such charges. Where the learned Arbitral Tribunal travels outside the

four corners of the contract and awards sums not legally due, the error

amounts to patent illegality and a jurisdictional transgression. In such

circumstances, the limited supervisory jurisdiction of this Court stands

squarely attracted.

154. The grant of financing charges, therefore, cannot be sustained

and is liable to be set aside.

155. In view of the foregoing discussion, the portion of the award

FAO(OS)(COMM) 210/2022 Page 57 of 57

insofar as it relates to claim 12A and financing charges is held to be

unsustainable and is accordingly set aside.

156. Save and except the above interference, the remaining findings

and directions contained in the award are found to be lawful, reasoned

and within the jurisdiction of the learned Arbitral Tribunal, and

therefore call for no interference.

157. The appeal is, therefore, partly allowed in the aforesaid terms. No

order as to costs.

OM PRAKASH SHUKLA, J .

C. HARI SHANKAR, J.

JANUARY 12, 2026/rjd/gunn/pa

Description

Legal Notes

Add a Note....