As per case facts, the Petitioner and a foreign collaborator signed an MOJP, and subsequently, the Petitioner and Respondent entered into an MOU where the Respondent was appointed as an ...
O.M.P. (COMM) 149/2023 Page 1 of 17
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 20 January 2026
Judgment pronounced on: 2/2/26
+ O.M.P. (COMM) 149/2023 & I.A. 7531/2023
M/S JAY FE CYLINDERS LTD. .....Petitioner
Through: Mr. V.K. Garg, Senior Adv.
with Mr. Kaushal Gautam, Mr.
Rishi Jindal, Mr. Mrinal
Sharma, Ms. Snehpreet Kaur,
Ms. Hemant Dalal & Mr. K.S.
Rekhi, Advs.
versus
MANISH JAIN .....Respondent
Through: Mr. Sanjeev Mahajan, Adv.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. This petition under Section 34 of the Arbitration & Conciliation
Act, 1996 (for short „the Act‟) is filed aggrieved of the arbitral award
dated 14.12.2022.
2. The petitioner is a Company incorporated under the Companies
Act, 1956 and engaged in the business of manufacturing Compressed
Natural Gas (CNG), Liquefied Petroleum Gas (LPG) and Gas
Cylinders. The petitioner approached a foreign collaborator RT
Chemical Technologies and Composite Materials, a Joint Stock
Company for manufacturing Polymer Composite Gas
Balloons/Cylinders for storage and transportation of CNG & LPG. On
02.09.2016 Memorandum on Joint Participation in Investment Project
O.M.P. (COMM) 149/2023 Page 2 of 17
(for short „MOJP‟) was executed between the petitioner and the
foreign collaborator. The MOJP was valid for two years and could be
terminated earlier with mutual consent. A Memorandum of
Understanding (for brevity „MOU‟) dated 03.08.2017 was entered
between the respondent and the petitioner. The respondent was to be
instrumental in execution of the Joint Venture Agreement (JVA)
between the petitioner and the foreign collaborator; to arrange funds;
to provide consultancy for establishment of the plant in India pursuant
to the JVA and to assist in the successful implementation of the
project as well as in ensuring regulatory compliances. The
remuneration of the respondent was on commission basis as mutually
agreed between the parties under clause 3 of the MOU.
3. The first instalment of sixty lakhs plus taxes towards
commission was paid against Invoice no. 1 dated 06.09.2017. The
JVA was not signed and on 08.06.2018 the MOJP was terminated by
the petitioner. The arbitration proceedings were initiated at the
instance of the petitioner for seeking refund of first instalment along
with interest. The respondent filed a counter claim for release of
second and third instalments. The arbitrator framed following issues:-
(i) Whether the respondent is guilty of violating the
express terms and conditions of the MoU dated
03.08.2017 (SOC)? OPC
(ii) Whether the respondent is liable to refund the 1
st
instalment of commission paid to him on 03.08.2017
along-with the interest from the date of default till the
date of realization? If so, at what rate (SOC)? OPC.
(iii) Whether the payment of Rs. 60 lakhs along with
O.M.P. (COMM) 149/2023 Page 3 of 17
GST was made by the claimant to the respondent as
advance or towards DSS Fee? OPR.
(iv) Whether the respondent is entitled to pro rata
commission amount of progress of project? OPR.
(v) Whether the respondent is entitled to 2
nd
and 3
rd
instalment of commission under MoU dated
03.08.2017? OPR.
(vi) Whether the claimant can seek refund of GST
after having taken the benefit of the input credit in
pursuance thereto? OPR.
(vii) Whether the respondent is entitled to interest on
the counter claim? If so at what rate and for what
period? OPR.
(viii) Whether the claimant is liable to pay Arbitration
cost & other legal expenses to the respondent?
(ix) Relief.
4. The issue nos. 1 & 2 were considered together and the claim of
the petitioner for refund of sixty lakhs plus GST was rejected holding
that the payment of first instalment was an advance of commission
payable to the respondent. Issue nos. 4 & 5 pertaining to the counter
claims of the respondent were allowed. It was concluded that the
respondent had provided services including negotiating price of plant
and machinery for the project and there was no failure on part of the
respondent in rendering services as agreed under the MOU. The issue
with regard to refund of GST was decided against the petitioner. The
respondent was held entitled to interest at the rate of nine per cent per
annum and litigation cost of two lakhs was awarded.
5. Learned senior counsel for the petitioner relying on clauses
O.M.P. (COMM) 149/2023 Page 4 of 17
3.1(e) and 3.1(g) contends that the payment of the first instalment
made upon signing of the MOU was an advance refundable upon
termination of the MOJP or in the eventuality of non-signing of the
JVA. It is submitted that while deciding issue no. 3 in favour of the
respondent the arbitrator held that the amount paid was an advance
towards commission yet rejected the claim of the petitioner for refund
and thereby recorded contradictory findings.
5.1 Vis-a-viz the allowance of counter claim of the respondent,
contention is that the award is contrary to the express terms of the
MOU and no reasons for allowing the counter claim have been
recorded. The submission is that the counter claims were allowed in
the absence of evidence establishing entitlement of the respondent to
receive commission and the basis for quantification thereof.
6. Per contra the award is defended and it is argued that the scope
of interference under Section 34 of the Act is limited, there cannot be
re-appreciation of evidence and in case of two possible views the
award is not to be interfered with. Reliance is on the decisions of the
Supreme Court in “South East Asia Marine Engineering and
Constructions Limited v. Oil India Limited” (2020) 5 SCC 164 and
“Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.”(2019) 20
SCC 1.
6.1 The Supreme Court in “State of Rajasthan v. Ferro Concrete
Construction (P) Ltd.” (2009) 12 SCC 1 is relied upon to fortify the
argument that the quantum of evidence is within the exclusive domain
of the arbitrator and cannot be gone into under Section 34 of the Act.
O.M.P. (COMM) 149/2023 Page 5 of 17
The contention is that as per clauses 3.1(c), 3.1(e) & 3.1(g) of the
MOU the respondent was entitled to commission for the services
rendered and there was no occasion to refund the commission
received. It is argued that the pleadings before the arbitrator vis-a-viz
the services provided by the respondent remained uncontroverted. The
cross examination of CW-1 Mr. Sushil Kumar Pareek is relied upon
wherein the witness stated that it was not for the petitioner to judge
the failure of the respondent to render services and the witness had no
knowledge regarding the signing of the JVA.
6.2 It is submitted that the JVA was finalised but the petitioner
without any justifiable reason refused to sign it. Moreover, unilateral
termination of the MOJP by the petitioner was in violation of clause
5.2 thereof.
7. Heard learned counsel for the parties at length. No submission
other than those noted above was pressed.
8. Before proceeding further it would be relevant to quote the
clause 1 of the MOU dealing with the scope of the agreement and
clause 3 relating to payment of commission.
“1. SCOPE OF AGREEMENT
1.1 The Company hereby appoints the Consultant to be
its Exclusive Consultant/Advisor for providing advice/
Consultancy relating to the joint venture required to be
executed with the collaborator and arrangement of
Private Equity from the Fund saving the interest of the
party of the first part. The appointment of the second
party shall be subject to providing the consultancy on
all the issue put forth to him and safeguard the interest
of the part of first part in every manner whatsoever.
O.M.P. (COMM) 149/2023 Page 6 of 17
1.2 The Second Party to work and offer Service to the
First Party to finalize mutually beneficial terms of the
commercial and business arrangement for the aforesaid
project for successful implementation of project and
start commercial production of product which includes
but not limited to initiate, facilitate and ensure
meetings between parties, getting the mutually required
secretarial services such as recording of the discussion,
getting the arrangement's vetted, identifying and
introducing competent professionals to the First Party
and Collaborator (if such requirement is felt
necessary), to be available physically and on phone / e-
mail / fax to offer advisory and consultancy services if
and when the party of the First Part need or demand
such services. The Second party will provide all
documents / records / draft minutes exchanged with
Collaborators from time to time in English language.
3. COMMISSIONS/PAYMENTS
3.1 The Company agrees to pay Commission to the
Consultant for performing his duties subject to the
following conditions:
a. The First party has agreed to pay in phases the
commission as mutually agreed based on the project
cost to be determined upon signing of JV between
Company and Collaborator.
b. That the work assigned to the Consultant has been
completed in every manner and payment of
consultancy shall be paid strictly in terms of the
schedule of payment as agreed between the parties. It is
made clear by the party of first part that no interim
payment in the middle of work shall be paid to the
consultant.
b. The First Party has agreed to treat the Second Part as
an 'Advisor /Consultant' throughout the project from
inception till successful implementation of project and
start commercial production of Product; and to provide
O.M.P. (COMM) 149/2023 Page 7 of 17
every signed document / record / draft minutes
exchanged between the Company, Collaborator and
Fund and decision making meetings between/among
them if and when The Second Part's presence and
participation is solicited by the First Party. Also the
party of Second Part shall share investment proposals/
share calling communication, capital structure of the
JVC and likes with the Company from time to time till
commencement of production of product by the JVC.
c. That party of first part shall not be liable to pay any
commission or any payment if the consultant failed to
complete any of the duties assigned to the consultant. It
has been agreed by the consultant that all payments
received by the consultant shall be refunded to the
party of the first part, in case consultant failed to meet
any of the duties assigned to the consultant to meet the
requirement of the Joint Venture and to set up the
manufacturing of product.
d. The First Party shall pay the mutual agreed
Commission to the Second Party and Second Party will
raise Invoices for the same as per the following
payment schedule:
S.No. Particulars
1. 1
st
instalment of INR 60 Lacs
(INR Sixty Lacs) after signing
of this Memorandum of
Understanding.
2. 2
nd
instalment of 10% of
commission after signing of
Joint Venture Agreement with
collaborators.
3. 3
rd
instalment of 20% of
commission after
commissioning of plant and
machinery.
O.M.P. (COMM) 149/2023 Page 8 of 17
4. Balance upon commencement
of Commercial Production.
e. Any payment received by the consultant prior to
receiving the first capital instalment shall be treated as
Deposit and the same shall be payable by the party of
second part in the event of not concluding the joint
venture agreement with the foreign collaborator. If
there is delay or any non-performance by the first
party, the pro-rata commission amount based on the
progress of project will be payable to the second party.
f. The total commission due would be remitted by the
Company to the account of Consultant or any of its
Nominee intimated in writing on letterhead. The total
commission due would be remitted by the Company to
the account of Consultant in the Indian currency.
g. In case of termination of this agreement and/or not
successful commencement of commercial production
pursuant to joint venture agreement with the foreign
collaborator, the party of the second part shall not be
entitled for any commission and the party of the second
part shall be bound to return all payments received on
any account to the party of the first part. If first party
fails to comply by all the duties as per the JV
agreement, first party will be liable to pay pro-rata
commission based on progress of the project due to
second party.”
9. The undisputed facts are that the first instalment of commission
was paid. No JVA was signed between the petitioner and the foreign
collaborator, consequently neither any plant was set up in India nor
the commercial production started.
10. The MOU obligated the respondent to play an instrumental role
in execution of the JVA with the foreign collaborator and to make
arrangements for private equity. The respondent offered services to
O.M.P. (COMM) 149/2023 Page 9 of 17
finalise mutually beneficial terms and business arrangements for the
project; to assist in successful implementation of the project and
commencement of commercial production. The commission of the
respondent was to be paid in phases and was based on the project cost
to be determined upon signing of the JVA between the petitioner and
the foreign collaborator.
11. Clause 3.1(c), 3.1(e) and 3.1(g) are relevant with regard to the
commission payable and the manner in which the payment made was
to be treated.
11.1 Clause 3.1(c) provided that the petitioner was not liable to pay
commission in the event of failure of the consultant to complete the
duties assigned. The commission received by the respondent was to be
refunded upon failure to meet the duties assigned including meeting
the requirements of the JVA and setting up of the manufacturing
facility.
11.2 As per clause 3.1(e) the payment made to the consultant prior to
receipt of the first capital instalment was to be treated as a deposit and
was to be returned to the petitioner in the eventuality of non-
conclusion of the JVA with the foreign collaborator. In case of delay
or non-performance on part of the petitioner, the respondent was
entitled to pro-rata commission based upon the progress of the project.
11.3 Clause 3.1(g) comes into operation upon termination of the
agreement or unsuccessful commencement of commercial production
pursuant to the JVA. In these eventualities the respondent was not
entitled to the commission and had to return the payments received.
On failure of the petitioner to comply with the obligations under the
O.M.P. (COMM) 149/2023 Page 10 of 17
JVA, pro-rata commission based upon progress of the project was
payable to the respondent.
12. Clauses 3.1(c), 3.1(e), 3.1(g) covered three different
eventualities. Firstly failure of the respondent to complete the duties
assigned or failing to meet the requirements of the JVA and to set up
manufacturing facilities. Secondly in case no JVA was concluded
between the petitioner and the foreign collaborator and lastly on
termination of the agreement or unsuccessful commencement of
commercial production pursuant to the JVA. While deciding issue
nos. 1 & 2 the arbitrator considered clause 3.1(c) of the MOU but
failed to take into consideration clauses 3.1(e) and 3.1(g). Sub-Clause
(e) specifically dealt with a situation where the JVA was not
concluded between the petitioner and the foreign collaborator. In such
a scenario the payment received by the respondent was to be treated as
an advance and was to be refunded to the petitioner. At the cost of
repetition no JVA was concluded between the petitioner and the
foreign collaborator.
13. Under sub-clause (g) upon unsuccessful commencement of
commercial production pursuant to the JVA the respondent was not
entitled to commission and was bound to return all payments received.
It is an admitted fact that neither the JVA was concluded nor there was
successful commencement of commercial production.
14. The arbitrator while deciding issue nos. 1 & 2 against the
petitioner ignored the relevant clauses of the MOU and was swayed by
unilateral termination of the MOJP by the petitioner which was not the
subject matter of dispute in arbitration. The respondent was not a party
O.M.P. (COMM) 149/2023 Page 11 of 17
to the MOJP and cannot raise grievance with regard to its termination
more so, when the foreign collaborator accepted the termination and
had not challenged it. The arbitrator sat in appeal over the business
prudence of the petitioner in not signing the JVA whereas non-
conclusion of the JVA was an issue to be considered.
15. It was not considered as to whether under MOU the respondent
was entitled to retain the payment received rather the arbitrator
proceeded on the basis that service charges should be paid to the
respondent for the duties performed. Further that the commission
could not be denied on account of the failure of the petitioner to sign
the JVA. The arbitrator decided the matter contrary to the express
terms and conditions of the MOU.
16. The essence of the MOU was the conclusion of JVA between
the parties irrespective of which party was instrumental in non-signing
of the JVA. The condition was of „conclusion‟ of the JVA which
never happened in this case. The award passed ignoring the clauses of
the MOU and contrary to its terms is vitiated by patent illegality.
17. Issue no. 3 as to whether the payment of first instalment of
commission along with GST could be treated as an advance was
decided taking into consideration part of clause 3.1(e) and ignoring
clauses 3.1(c) and clause 3.1(g). Clause 3.1(e) was partially
considered to the extent that the payment received by the respondent
was to be treated as a deposit whereas the latter part providing that the
amount so received was refundable in the eventuality of non-
conclusion of the JVA was ignored.
18. No reasons are recorded for deciding issue no. 3 against the
O.M.P. (COMM) 149/2023 Page 12 of 17
petitioner. The conclusion on issue no. 3 is reproduced:
“38. Considering all facts and circumstances, this
Tribunal is of the view that the payment of Rs. 60 lacs
+ GST made by the Claimant is as advance on account
of fee/commission to be paid to the Respondent. This
issue thus is decided in favour of the Respondent and
against the Claimant.”
19. The counter claims filed by the respondent under issue nos. 4 &
5 were decided by recording:
“43. This Tribunal, upon perusal of the record and
consideration of arguments put forth by both the sides
finds weight in the submissions made by the
Respondent. If the journey is not complete and some
portion of it is left then the efforts and expenses made
till actual completion cannot be ignored.
44. These issues are thus decided in favour of the
Respondent and against the Claimant.”
20. The conclusion is bald of reasons. The claim for pro-rata
commission could have been made under clauses 3.1(e) and 3.1(g).
Neither evidence was adduced by the respondent in support of the
counter claim to establish delay or failure on the part of the petitioner
as stipulated clause 3.1(e) nor the arbitrator recorded reasons as to
under which clause the counter claim is allowed. For claiming pro-rata
commission under sub-clause (g) there should have been failure of the
petitioner to comply with duties under the JVA whereas in the case in
hand no JVA was executed between the parties.
21. From reading of clauses 3.1(a) and 3.1 (d) it emerges that the
second and third instalments were payable on a percentage based on
the project cost determined under the JVA. There was no basis for
O.M.P. (COMM) 149/2023 Page 13 of 17
quantifying the instalments in the absence of an agreed project cost
due to failure of the parties to enter into the JVA. The claim of the
respondent for payment of second & third instalments was allowed
against the clauses of MOU.
22. The issues of refund of GST and entitlement to interest are
consequent upon the decisions of issue nos. 1 to 4 and need not be
gone into.
23. The law is well-settled that an arbitral tribunal is obligated
under Section 31(3) of the Act to pass a speaking award. Reference in
this regard be made to decision of Supreme Court in Dyna
Technologies Private Limited v. Crompton Greaves Limited
(2019) 20 SCC 1:
“34. The mandate under Section 31(3) of the
Arbitration Act is to have reasoning which is
intelligible and adequate and, which can in appropriate
cases be even implied by the courts from a fair reading
of the award and documents referred to thereunder, if
the need be. The aforesaid provision does not require
an elaborate judgment to be passed by the arbitrators
having regard to the speedy resolution of dispute.
35. When we consider the requirement of a reasoned
order, three characteristics of a reasoned order can be
fathomed. They are: proper, intelligible and adequate.
If the reasonings in the order are improper, they reveal
a flaw in the decision-making process. If the challenge
to an award is based on impropriety or perversity in the
reasoning, then it can be challenged strictly on the
grounds provided under Section 34 of the Arbitration
Act. If the challenge to an award is based on the
ground that the same is unintelligible, the same would
be equivalent of providing no reasons at all. Coming to
the last aspect concerning the challenge on adequacy of
O.M.P. (COMM) 149/2023 Page 14 of 17
reasons, the Court while exercising jurisdiction under
Section 34 has to adjudicate the validity of such an
award based on the degree of particularity of reasoning
required having regard to the nature of issues falling
for consideration. The degree of particularity cannot be
stated in a precise manner as the same would depend
on the complexity of the issue. Even if the Court comes
to a conclusion that there were gaps in the reasoning
for the conclusions reached by the Tribunal, the Court
needs to have regard to the documents submitted by the
parties and the contentions raised before the Tribunal
so that awards with inadequate reasons are not set aside
in casual and cavalier manner. On the other hand,
ordinarily unintelligible awards are to be set aside,
subject to party autonomy to do away with the
reasoned award. Therefore, the courts are required to
be careful while distinguishing between inadequacy of
reasons in an award and unintelligible awards.”
24. In case of an award suffering from patent illegality, perversity
or being in conflict with the Public Policy of India the power under
Section 34 of the Act is to be exercised. The non-consideration of the
clauses of the MOU or rewriting of the contractual terms vitiates the
award on the ground of perversity. Reference in this regard be made to
following decisions of the Supreme Court:
24.1 In Delhi Metro Rail Corporation Ltd. V. Delhi Airport
Metro Express Pvt. Ltd. 2024 INSC 292 held as under:
“38. In Associate Builders vs. Delhi Development
Authority
22
, a two-judge Bench of this Court held that
although the interpretation of a contract is exclusively
within the domain of the arbitrator, construction of a
contract in a manner that no fair-minded or reasonable
person would take, is impermissible. A patent illegality
arises where the arbitrator adopts a view which is not a
O.M.P. (COMM) 149/2023 Page 15 of 17
possible view. A view can be regarded as not even a
possible view where no reasonable body of persons
could possibly have taken it. This Court held with
reference to Sections 28(1)(a) and 28(3), that the
arbitrator must take into account the terms of the
contract and the usages of trade applicable to the
transaction. The decision or award should not be
perverse or irrational. An award is rendered perverse or
irrational where the findings are (i) based on no
evidence; (ii) based on irrelevant material; or (iii)
ignores vital evidence. Patent illegality may also arise
where the award is in breach of the provisions of the
arbitration statute, as when for instance the award
contains no reasons at all, so as to be described as
unreasoned. A fundamental breach of the principles of
natural justice will result in a patent illegality, where
for instance the arbitrator has let in evidence behind the
back of a party. In the above decision, this Court
observed:
“31. The third juristic principle is that a
decision which is perverse or so irrational
that no reasonable person would have arrived
at the same is important and requires some
degree of explanation. It is settled law that
where:
(i) a finding is based on no evidence, or
(ii) an Arbitral Tribunal takes into account
something irrelevant to the decision which it
arrives at; or
(iii) ignores vital evidence in arriving at its
decision,
such decision would necessarily be perverse.
…
42.2. (b) A contravention of the Arbitration
Act itself would be regarded as a patent
illegality — for example if an arbitrator
gives no reasons for an award in
contravention of Section 31(3) of the Act,
O.M.P. (COMM) 149/2023 Page 16 of 17
such award will be liable to be set aside.”
40. In essence, the ground of patent illegality is
available for setting aside a domestic award, if the
decision of the arbitrator is found to be perverse, or so
irrational that no reasonable person would have arrived
at it; or the construction of the contract is such that no
fair or reasonable person would take; or, that the view
of the arbitrator is not even a possible view.
24
A
„finding‟ based on no evidence at all or an award which
ignores vital evidence in arriving at its decision would
be perverse and liable to be set aside under the head of
„patent illegality‟. An award without reasons would
suffer from patent illegality. The arbitrator commits a
patent illegality by deciding a matter not within his
jurisdiction or violating a fundamental principle of
natural justice.”
25.2 In Indian Oil Corpn. Ltd. v. Shree Ganesh Petroleum,
(2022) 4 SCC 463 held as under:
“43. An Arbitral Tribunal being a creature of contract,
is bound to act in terms of the contract under which it
is constituted. An award can be said to be patently
illegal where the Arbitral Tribunal has failed to act in
terms of the contract or has ignored the specific terms
of a contract.”
25.3 In State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022) 2
SCC 275 held as under:
“26. ………. We are, therefore, of the view that failure
on the part of the learned sole arbitrator to decide in
accordance with the terms of the contract governing the
parties, would certainly attract the “patent illegality
ground”, as the said oversight amounts to gross
contravention of Section 28(3) of the 1996 Act, that
enjoins the Arbitral Tribunal to take into account the
terms of the contract while making an award. The said
“patent illegality” is not only apparent on the face of
O.M.P. (COMM) 149/2023 Page 17 of 17
the award, it goes to the very root of the matter and
deserves interference……….”
25.4 In Bharat Coking Coal Ltd. v. Annapurna Construction,
(2003) 8 SCC 154 held as under:
“22. There lies a clear distinction between an error
within the jurisdiction and error in excess of
jurisdiction. Thus, the role of the arbitrator is to
arbitrate within the terms of the contract. He has no
power apart from what the parties have given him
under the contract. If he has travelled beyond the
contract, he would be acting without jurisdiction,
whereas if he has remained inside the parameters of the
contract, his award cannot be questioned on the ground
that it contains an error apparent on the face of the
record.”
(emphasis supplied)
25. For the reasons mentioned above, the impugned arbitral award
is set aside. Pending application is also disposed of.
AVNEESH JHINGAN , J.
FEBRUARY 02, 2026
‘JK’
Reportable:- Yes
Legal Notes
Add a Note....