energy law, contract law
 30 Jan, 2026
Listen in 02:00 mins | Read in 34:00 mins
EN
HI

M/S Saisudhir Energy Ltd. Vs. M/S Ntpc Vidyut Vyapar Nigam Ltd.

  Supreme Court Of India CIVIL APPEAL NOS.12892-12893 OF 2024 & CIVIL APPEAL
Link copied!

Case Background

As per case facts, an Arbitral Tribunal awarded damages for delayed commissioning of a solar power plant. A Single Judge, under Section 34 of the Arbitration Act, 1996, increased the ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

2026 INSC 103 C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 1 of 23

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOS.12892-12893 OF 2024

M/S SAISUDHIR ENERGY LTD . APPELLANT(S)

VERSUS

M/S NTPC VIDYUT VYAPAR NIGA M LTD. RESPONDENT(S)

WITH

CIVIL APPEAL NOS.12894-12895 OF 2024

M/S NTPC VIDYUT VYAPAR NIGA M LTD. APPELLANT(S)

VERSUS

M/S SAISUDHIR ENERGY LTD . RESPONDENT(S)

J U D G M E N T

ATUL S. CHANDURKAR, J.

1. These cross appeals arise out of the common judgment

passed by the Division Bench of the Delhi High Court dated

18.01.2018 in proceedings filed under Section 37 of the Arbitration

and Conciliation Act, 1996 (for short, “the Act of 1996”). Broadly,

the dispute between the parties relates to the claim for liquidated

damages raised by the employer against the Solar Power Developer

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 2 of 23

on account of delay caused in commissioning a power plant. A

three-member Arbitral Tribunal while holding that there was a

delay in commissioning the power plant, by majority, awarded an

amount of ₹1.2 crores towards the claim made by the employer.

Both parties raised objections under Section 34 of the Act of 1996.

A learned Single Judge of the Delhi High Court proceeded to grant

an amount of ₹ 27.06 crores to the employer on account of delay

on the part of the Solar Power Developer in commissioning the

power plant. Both parties further took recourse to Section 37 of

the Act of 1996. By the impugned judgment, the Division Bench

modified the order passed under Section 34 of the Act of 1996 in

the matter of grant of liquidated damages and reduced the amount

to ₹ 20.70 crores.

2. The facts relevant for considering the challenge as raised by

the parties to the aforesaid common judgment are that, in 2010

the Ministry of Power, Government of India, launched the

Jawaharlal Nehru National Solar Mission (for short, “the JNNSM”)

with the objective of deploying 20000 Mega Watt (MW) of grid

connected solar power in three phases by 2022 at a reasonable

cost. The JNNSM postulated bundling of solar power alongwith

cheaper power from and out of the unallocated quota of central

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 3 of 23

stations and thereafter selling the said bundled power to the State

distribution utilities at a regulated price.

3. The Ministry of Power designated NTPC Vidyut Vyapar Nigam

Limited (for short, “NVVNL”) as the nodal agency. NVVNL was

required to enter into Power Purchase agreements with Solar

Power Developers at a fixed rate for twenty-five years. The bundled-

up power was to be sold by NVVNL to various distribution utilities

at prices determined by the Regulatory Commission. Accordingly,

on 24.01.2012, a Power Purchase Agreement (for short, “PPA”) was

entered into between M/s Saisudhir Energy Limited (for short,

“SEL”) and NVVNL. Under the said agreement, SEL agreed to set

up and thereafter supply 20 MW solar power at the rate of ₹ 8.22

per unit, which was a discounted price from the tariff approved by

the Regulatory Commission of ₹ 15.39 per unit. Under the said

agreement, the date of commissioning supply of 20 MW solar

power was 26.02.2013. Clause 4.6 of the PPA provided for

liquidated damages in case there was a delay in commencement of

supply of solar power to NVVNL. On 30.01.2013 , SEL sought

extension of time by two months from NVVNL citing various

exigencies and invoked the force majeure clause. This request was,

however, rejected by NVVNL on 31.01.2013 as notice of seven days

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 4 of 23

as required under Clause 11.5.1 of the PPA was not given. SEL

failed to commission its project by 26.02.2013. It commissioned

supply of 10 MW power from 26.04.2013, which was after a delay

of two months. Thereafter, it commissioned supply for the balance

10 MW power from 24.07.2013, which was after a delay of about

five months. SEL, thereafter, moved an application under Section

9 of the Act of 1996 before the Delhi High Court seeking to restrain

NVVNL from encashing the bank guarantees furnished by it. The

High Court granted interim relief in favour of SEL till the

consideration of its prayer for interim relief by the Arbitral Tribunal

under Section 17 of the Act of 1996.

4. On invocation of the arbitration clause, a three-member

Arbitral Tribunal was constituted. SEL as claimant submitted its

claim and sought to restrain NVVNL from encashing the bank

guarantees. It also claimed charges for maintenance of the bank

guarantees. On the other hand, NVVNL claimed encashment of the

bank guarantees as per Clause 4.6 of the PPA. On 21.07.2015, the

three-member Arbitral Tribunal passed a split award. As per the

majority award, SEL was directed to pay NVVNL ₹ 1.2 crores being

20% of the original performance guarantee at the rate of ₹ 30 lakhs

per MW. The claim made by SEL for reimbursement of expenditure

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 5 of 23

was, however, rejected. The minority award on the other hand held

that it was not possible to work out the actual loss suffered by

NVVNL on account of delay in commissioning the project. The

liquidated damages as mentioned in Clause 4.6 of the PPA were

held to be a genuine pre-estimate of loss suffered and SEL was

directed to pay the same. NVVNL was held entitled to encash the

bank guarantees amounting ₹ 49.92 crores excluding the bank

guarantees furnished towards earnest money deposit.

5. Both the parties were aggrieved by the aforesaid awards and

they took recourse to the provisions of Section 34 of the Act of

1996. By the judgment dated 08.09.2016, a learned Judge of the

Delhi High Court held that there was delay on the part of SEL in

commencing the supply of power in terms of the PPA. He held that

NVVNL had not invested any amount in the said project nor did it

prove any actual damage suffered by it. The project was for a

duration of twenty-five years while the delay caused was of only a

few months. He, therefore, modified the award and granted 50% of

the amount awardable towards damages under Clause 4.6. This

amount was to be recovered by adjusting a sum of ₹ 25 lakhs per

month from 01.10.2016 that was payable to SEL. The majority

award was set aside by the learned Single Judge.

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 6 of 23

6. Both the parties were further aggrieved by the judgment

passed under Section 34 of the Act of 1996 and they preferred

appeals under Section 37 of the Act of 1996. The Division Bench

by its common judgment did not agree with the findings recorded

in the majority award on the aspect of liquidated damages as well

as on the question of public utility. It held that the PPA had been

entered into with a social object and purpose. It was difficult to

prove the quantum of damages that could be awarded and paid in

case of breach on account of delay on the part of SEL. After

considering various aspects such as total cost of the project

incurred by SEL, the monthly income received by SEL from NVVNL

and the fact that duration of the project was about twenty-five

years while the period of delay was not very long, SEL was directed

to pay damages at the rate of ₹ 1,00,000/- per MW for the entire

period of delay which amounted to ₹ 20.70 crores. SEL was also

directed to pay bank guarantee renewal charges within a period of

six weeks from the date of the judgment. It is this judgment that

is the subject matter of challenge at the instance of both the parties

in these cross appeals.

7. Mr. Nakul Dewan, learned Senior Advocate on behalf of SEL

submitted that NVVNL having failed to prove the actual loss

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 7 of 23

suffered by it, it was not entitled to receive any liquidated damages

under Clause 4.6.2 of the PPA. The PPA was a purely commercial

contract entered into for the purchase and sale of solar power.

Merely because the PPA was executed under the JNNSM, it could

not be stated that it was a project of public utility and, hence, there

was no obligation on the part of the NVVNL to prove its actual loss

for claiming liquidated damages. Relying upon the decision of this

Court in Kailash Nath Associates vs. D. D. A.

1, it was submitted

that in terms of Section 74 of the Indian Contract Act, 1872 (for

short, “the Act of 1872”) proof of damage caused or loss suffered

was a sine qua non for claiming compensation on account of such

breach. In absence of any such loss being proved by NVVNL before

the Arbitral Tribunal, it was not entitled to receive any liquidated

damages under Clause 4.6.2 of the PPA. Both the Courts erred in

relying upon the decision in M/s Construction and Design

Services vs. D.D.A.

2 inasmuch as the employer therein had made

various investments in the concerned project and had suffered loss

due to delay. It was urged that in the present case, NVVNL had not

made any investment whatsoever and that all investments were in

fact made by SEL. While the contractor in the said case had

1

2015 INSC 22

2

2015 INSC 92

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 8 of 23

abandoned the project, SEL had successfully commissioned the

Solar Power Project and it was running smoothly. A delay of few

months, therefore, ought not to be the reason to impose liquidated

damages on SEL.

It was further submitted that ignoring the limited power

available under Sections 34 and 37 of the Act of 1996, the Courts

proceeded to modify the arbitral award while granting liquidated

damages. A merit based evaluation under Sections 34 and 37 of

the Act of 1996 was impermissible and a review of the arbitral

award in such a manner could not have been undertaken. Both

the Courts erred in travelling beyond the arbitral award and

modifying the same. The exercise of undertaking the calculation of

liquidated damages was also an exercise on merits of the dispute,

which was impermissible under the limited jurisdiction available.

In this regard, reliance was placed on the decision in Gayatri

Balasamy vs. ISG Novasoft Technologies Limited

3. It was, thus,

submitted that interference by both the Courts being

unwarranted, the said orders were liable to be set aside. The

appeal filed by SEL, thus, ought to be allowed.

3

2025 INSC 605

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 9 of 23

8. On the other hand, Mr. Gopal Jain, learned Senior Advocate

appearing on behalf of NVVNL submitted that in the case of a

public utility project or a work involving public interest, it was not

necessary to prove the actual loss suffered. The supply of solar

energy under the JNNSM was in fact a public utility project and it

was necessary for SEL to have complied with the time schedules

agreed. The fact that delay was caused in the initiation of the

project was itself sufficient to indicate that NVVNL had in fact

suffered loss and that there was no need of any specific evidence

in that regard. It was submitted that the ratio of the decision in

M/s Construction and Design Services (supra) was squarely

applicable to the case in hand. In fact, NVVNL was entitled to

higher amount of liquidated damages and that the Division Bench

was not justified in reducing the same. Referring to the pleadings

of the parties, it was submitted that the delay caused by NVVNL

being an admitted fact, the entire claim for liquidated damages in

accordance with Clause 4.6.2 of the PPA ought to have been

allowed. There was no question of importing the notions of equity

in such matters and that the rights of the parties were governed

by the PPA entered into by them. The reduction in the amount of

liquidated damages from ₹ 27.06 crores to ₹ 20.70 crores by the

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 10 of 23

Division Bench was uncalled for. To substantiate the aforesaid

contentions, reliance was placed on the decision in

Chamundeshwari Electricity Supply Company Limited vs.

Sai-Sudhir Energy (Chitradurga) Private Limited and

another

4. While the entitlement of NVVNL to liquidated damages

under Clause 4.6.2 of the PPA was ₹ 54.12 crores, the Division

Bench despite being satisfied with the claim made on behalf of

NVVNL was not justified in reducing that amount to ₹ 20.70 crores.

Finally, it was submitted that the dispute between the parties was

of the year 2013 and relegating the parties to any fresh proceedings

was totally unwarranted. It was prayed that the appeal preferred

by NVVNL be allowed.

9. We have heard the learned Senior Advocates for the parties

at length and we have also perused the documentary material on

record. Having given our due consideration to the entire matter,

we find that the Division Bench in exercise of jurisdiction under

Section 37 of the Act of 1996 was not justified in modifying the

amount of compensation awarded by the Court under Section 34.

10. The PPA entered into by NVVNL with SEL on 24.01.2012 was

in its capacity as the Nodal Agency for carrying out the objectives

4

2025 INSC 1034

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 11 of 23

under the JNNSM. This was to enable the sale of bundled up power

by NVVNL to various distribution utilities at prices determined by

the regulatory commission. A total of 20 MW solar power was to be

commissioned under the PPA. It is an admitted position under the

terms of the PPA that the date of commissioning was fixed as

26.02.2013. SEL, however, failed to meet this deadline. It

commissioned supply of 10 MW power from 26.04.201 3, which

was after a delay of two months. The balance of 10 MW power was

commissioned from 24.07.2013, which was after a delay of about

five months. Clause 4.6 of the PPA is the subject matter of dispute

between the parties and same reads as under: -

“4.6 Liquidated Damages for delay in commencement

of supply of power to NVVN

4.6.1 If the SPD is unable to commence supply of power

to NVVN by the Scheduled Commissioning Date other than

for the reasons specified in Article 4.5.1, the SPD shall pay

to NVVN, Liquidated Damages for the delay in such

commencement of supply of power and maki ng the

Contracted Capacity available for dispatch by the Scheduled

Commissioning Date as per the following:

a. Delay upto one (1) month - NVVN will encash 20%

of total Performance Bank Guarantee proportionate to the

Capacity not commissioned.

b. Delay of more than one (1) month and upto two

months - NVVN will encash 40% of the total Performance

Bank Guarantee proportionate to the Capacity not

commissioned.

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 12 of 23

c. Delay of more than two and upto three months -

NVVN will encash the remaining Performance Bank

Guarantee proportionate to the Capacity not commissioned.

4.6.2 In case the commissioning of Power Project is

delayed beyond three (3) months, the SPD shall pay to NVVN,

the Liquidated Damages at rate of Rs. 1,00,000/- per MW per

day of delay for the delay in such remaining Capacity which

is not commissioned. The amount of liquidated damages

would be recovered from the SPD from the payments due on

account of sale of solar power to NVVN.

4.6.3 The maximum time period allowed for

commissioning of the full Project Capacity with encashment

of Performance Bank Guarantee and payment of Liquidated

Damages shall be limited to eighteen (18) months from the

date of signing of this Agreement. In case, the commissioning

of the Power Project is delayed beyond eighteen (18) months

from the date of signing of this Agreement, it shall be

considered as an SPD Event of Default and provisions of

Article 13 shall apply and the Contracted Capacity shall

stand reduced/amended to the Project Capacity

Commissioned within 18 months of signing of PPA and the

PPA for the balance Capacity will stand terminated.

4.6.4 However, if as a consequence of delay in

commissioning, the applicable tariff changes, that part of the

capacity of the Project for which the commissioning has been

delayed shall be paid at the tariff as per Article 9.2 of this

Agreement.”

11. As regards failure on the part of SEL to meet the deadline for

commissioning solar power is concerned, there is no dispute that

SEL failed to meet the agreed deadline as the supply of 10 MW

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 13 of 23

power was undertaken with a delay of two months and the supply

of balance 10 MW power was undertaken after a delay of about five

months. The majority award in paragraph 97 records this aspect,

including the admission on the part of SEL that such delay in fact

had been occasioned. The learned Single Judge while dealing with

the proceedings under Section 34 of the Act of 1996 has in

paragraphs 57, 76 and 77 recorded in clear terms that the breach

of contract was admitted by SEL and that there was in fact delay

on its part in supplying power. The Division Bench in the appeals

filed under Section 37 of the Act of 1996 affirmed this position.

The aforesaid would indicate that insofar as the grievance

raised by NVVNL that SEL failed to commission 20 MW power

within the time stipulated under the PPA is concerned, the said

position does not admit of any doubt. In fairness to the learned

Senior Advocate for SEL, it may be stated that this finding was not

seriously challenged in its appeal.

12. Thus, having found that the timelines agreed to by the parties

to the PPA not having been followed by SEL, it is evident that

Clause 4.6 of the PPA that provides for liquidated damages for

delay in commencement of supply of power gets attracted. Clause

4.6 provides the consequence of delay in not commissioning the

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 14 of 23

agreed capacity within the prescribed period. The period of delay

is material in determining the amount of liquidated damages. It is

in this context that the provisions of Section 74 of the Act of 1872

gets attracted. Section 74 reads as under:-

“74. Compensation for breach of contract where penalty

stipulated for:- [When a contract has been broken, if a sum is

named in the contract as the amount to be paid in case of such

breach, or if the contract contains any other stipulation by way of

penalty, the party complaining of the breach is entitled, whether

or not actual damage or loss is proved to have been caused

thereby, to receive from the party who has broken the contract

reasonable compensation not exceeding the amount so named or,

as the case may be, the penalty stipulated for.

Explanation.-- A stipulation for increased interest from the date of

default may be a stipulation by way of penalty.]

Exception.-- When any person enters into any bail -bond,

recognizance or other instrument of the same nature, or, under

the provisions of any law, or under the orders of the [Central

Government] or of any [State Government], gives any bond for the

performance of any public duty or act in which the public are

interested, he shall be liable, upon breach of the condition of any

such instrument, to pay the whole sum mentioned therein.

Explanation.-- A person who enters into a contract with

Government does not necessarily thereby undertake any public

duty, or promise to do an act in which the public are

interested…………”

Section 74 of the Act of 1872 stipulates that in the case

of breach of contract, the party complaining of the breach is

entitled, whether or not actual damage or loss is proved to have

been caused, to receive from the party who has broken the contract

reasonable compensation not exceeding the amount named or the

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 15 of 23

penalty stipulated. The provisions of Section 74 were the subject

matter of consideration by this Court in M/s Construction and

Design Services (supra) wherein it was held in the context of delay

in providing a public utility service that in such a case, the delay

in commissioning of such utility service itself can be taken to have

resulted in loss in the form of environmental degradation. In the

said case, the contract was in relation to the construction of a

sewerage pumping station. It was observed that providing for a

sewerage pumping station was of public utility to maintain and

preserve clean environment. It was held that if the parties had pre-

estimated the loss likely to be caused, it would be unjustified to

arrive at the conclusion that the party that had committed the

breach was not liable to pay compensation.

13. The learned Single Judge while exercising jurisdiction under

Section 34 of the Act of 1996 relied upon the aforesaid decision

and while exercising discretion in the matter of award of

reasonable compensation proceeded to grant 50% of the amount

of damages that NVVNL was entitled to under Clause 4.6 of the

PPA. The Division Bench in appeal recorded its agreement with the

view of the learned Single Judge that it was necessary to compute

a fair and reasonable amount of compensation while balancing the

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 16 of 23

equities. The Division Bench, however, proceeded to modify the

order passed under Section 34 of the Act of 1996 and thereafter

reduced the amount of compensation taking into consideration the

period of delay caused by SEL.

14. It has been urged on behalf of SEL that the majority award

having granted an amount of ₹ 1.20 crores to NVVNL in view of the

delay in commission the power plant, the Section 34 Court could

not have modified the award so as to grant higher compensation.

The modification was beyond the permissible limits recognized in

Gayatri Balasamy (supra).

The Constitution Bench in Gayatri Balasamy (supra) has

recognised the power of the Section 34 Court to modify an award

to a limited extent. It has held in paragraphs 40 to 46 as under:

“IV. A Limited Power of Modification Can Be Located in Section 34

40. A core principium of arbitration, an Alternative Dispute

Resolution mechanism, is to provide a quicker and cost-effective

alternative to courtroom litigation. While this suggests minimal

judicial interference, the role of domestic courts remains crucial,

as they function in a supportive capacity to facilitate and expedite

the resolution of disputes. Therefore, it follows that judicial

intervention is legitimate and necessary when it furthers the ends

of justice, including the resolution of disputes.

41. To deny courts the authority to modify an award-particularly

when such a denial would impose significant hardships, escalate

costs, and lead to unnecessary delays-would defeat the raison

d'être of arbitration. This concern is particularly pronounced in

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 17 of 23

India, where applications under Section 34 and appeals under

Section 37 often take years to resolve.

42. Given this background, if we were to decide that courts can

only set aside and not modify awards, then the parties would be

compelled to undergo an extra round of arbitration, adding to the

previous four stages: the initial arbitration, Section 34 (setting

aside proceedings), Section 37 (appeal proceedings), and Article

136 (SLP proceedings). In effect, this interpretation would force the

parties into a new arbitration process merely to affirm a decision

that could easily be arrived at by the court. This would render the

arbitration process more cumbersome than even traditional

litigation.

43. Equally, Section 34 limits recourse to courts to an

application for setting aside the award. However, Section 34 does

not restrict the range of reliefs that the court can grant, while

remaining within the contours of the statute. A different relief can

be fashioned as long as it does not violate the guardrails of the

power provided under Section 34. In other words, the power

cannot contradict the essence or language of Section 34. The court

would not exercise appellate power, as envisaged by Order XLI of

the Code of Civil Procedure, 1908.

44. We are of the opinion that modification represents a more

limited, nuanced power in comparison to the annulment of an

award, as the latter entails a more severe consequence of the

award being voided in toto. Read in this manner, the limited and

restricted power of severing an award implies a power of the court

to vary or modify the award. It will be wrong to argue that silence

in the 1996 Act, as projected, should be read as a complete

prohibition.

45. We are thus of the opinion that the Section 34 court can apply

the doctrine of severability and modify a portion of the award while

retaining the rest. This is subject to parts of the award being

separable, legally and practically, as stipulated in Part II of our

Analysis.

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 18 of 23

46. Mustill and Boyd have observed that an order varying an award

is not equivalent to an appellate process. The authors suggest that

a modification order would only be appropriate where the

modification, including any adjustment of costs, follows inevitably

from the tribunal’s determination of a question of law. This

approach would be beneficial, as it would reduce costs and delays.

The courts need not engage in any fact -finding exercise. By

acknowledging the Court’s power to modify awards, the judiciary

is not rewriting the statute. We hold that the power of judicial

review under Section 34, and the setting aside of an award, should

be read as inherently including a limited power to modify the

award within the confines of Section 34.”

15. In our view, the modification of the award so as to enhance

the amount of reasonable compensation by the Section 34 Court

was a permissible exercise when viewed in the context of the law

laid down in Gayatri Balasamy (supra). The modification is in

exercise of jurisdiction under Section 34 of the Act of 1996 without

undertaking any examination of the merits of the dispute. To put

it plainly, the modification is only with a view to apply Clause 4.6.2

of the PPA to the facts of the case which exercise has also been

approved by the Section 37 Court. We, therefore, do not find that

on this count, the judgment of the Section 34 Court suffers from

any jurisdictional error.

16. SEL has strenuously sought to distinguish the decision of

this Court in M/s Construction and Design Services (supra) and

urge that the PPA entered into by the parties was merely a

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 19 of 23

commercial agreement to supply power. We do not find this

contention acceptable. The PPA indicates that NVVNL had been

appointed as a Nodal Agency for carrying out the objectives under

the JNNSM. The commissioning of the solar plant by SEL was with

a view to satisfy and take the solar mission forward. This activity

was definitely in public interest and with a view to promote green

energy. The objective of the PPA, therefore, involves public interest

and the environment at large. The timelines fixed by the parties,

therefore, are relevant. We are, therefore, of the view that M/s

Construction and Design Services (supra) in fact provides sufficient

indication of the manner in which the aspect of reasonable

compensation could be considered wherein a public utility project

is involved. In such cases, the burden would be on the party

committing the breach to show that no loss was caused by the

delay or that the amount stipulated as liquidated damages was in

the nature of penalty. In the facts of the present case, this burden

has not been discharged by SEL. In fact, it has remained content

by urging that NVVNL having failed to make any investment under

the PPA, it neither suffered any loss of capital or loss of interest,

notwithstanding the delay. Having agreed to incorporate Clause

4.6 in the PPA, it is clear that the rights of the parties ought to be

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 20 of 23

determined bearing in mind the terms agreed and SEL would not

be justified in contending that NVVNL had failed to indicate the

exact loss suffered by it due to the delay in commissioning of the

project. The learned Single Judge as well as the Division Bench

have in our view rightly approached this aspect of the matter and

have held that NVVNL in terms of Clause 4.6 of the PPA is entitled

to reasonable compensation. We, therefore, do not find any reason

whatsoever to take a different view of the matter in this regard.

17. Coming to the aspect of determination of the amount of

reasonable compensation, the learned Single Judge after referring

to Clause 4.6 of the PPA determined the claim as made by NVVNL

in terms of Clause 4.6 of the PPA at an amount of ₹ 54,12,32,000/-.

He found that granting 50% of the aforesaid amount by adjusting

₹ 25,00,000/- per month from the revenue to be received by SEL

would amount to reasonable compensation in favour of NVVNL.

The Division Bench in appeal, however, proceeded to modify the

amount of reasonable compensation by reading Clause 4.6 of the

PPA on the premise that a higher rate of damages was payable in

the initial three months period of delay and that amount was

reduced after three months. On that basis damages at the rate of

₹ 1,00,000/- per MW per day came to be worked out. The amount

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 21 of 23

of compensation was, thus, reduced to ₹ 20.70 crores.

18. In our view, the Division Bench exceeded its jurisdiction

under Section 37 of the Act of 1996 when it proceeded to re-work

and re-calculate the amount of reasonable compensation to which

NVVNL was entitled. The learned Single Judge having determined

the amount of reasonable compensation by relying upon Clause

4.6 of the PPA and thereafter awarding 50% of the amount so

determined, in the absence of this determination being shown to

be beyond the terms of Clause 4.6 of the PPA or arbitrary or

perverse, no interference with such determination was called for in

exercise of jurisdiction under Section 37 of the Act of 1996. In fact,

the Division Bench has not recorded any finding that such

determination of reasonable compensation by the learned Single

Judge suffered from arbitrariness or that it travelled beyond what

was provided by Clause 4.6 of the PPA. Having held in paragraph

28 of the impugned judgment that it was in agreement with the

view of the learned Single Judge of the need to balance equities

and compute a fair and reasonable amount of compensation

coupled with the fact that the majority award granting a paltry

amount of ₹ 1.2 crores was held to be contrary to the fundamental

policy of Indian law thus requiring interference, the further

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 22 of 23

exercise undertaken by it in modifying the amount of reasonable

compensation was not justified in the facts of the case. The

modification in the amount of reasonable compensation by the

Division Bench is merely a substitution of its view in place of the

plausible view taken by the learned Single Judge. Such course of

taking a different view of the same matter from the one taken under

Section 34 of the Act of 1996 would be beyond the scope of Section

37 of the Act of 1996. As held in AC Chokshi Share Broker

Private Limited vs. Jatin Pratap Desai and another

5 to which

one of us (P.S. Narasimha J) was a party, the Court under Section

37 must only determine whether the Section 34 Court had

exercised its jurisdiction properly and rightly, without exceeding

its scope. To that extent, we find that the Division Bench of the

High Court erred in interfering with the judgment of the learned

Single Judge.

19. For the aforesaid reasons, we are of the view that the

determination of the amount of reasonable compensation by the

learned Single Judge having been undertaken in terms of Clause

4.6 of the PPA and further discretion having been exercised by

awarding 50% of such amount as liquidated damages, the Division

5

2025 INSC 174

C.A. Nos.12892-12893 & 12894-12895 of 2024 Page 23 of 23

Bench was not justified in modifying the said decision.

Accordingly, the judgment of the Division Bench dated 18.01.2018

to that extent stands set aside. The judgment of the learned Single

Judge in OMP No.410 of 2015 and 446 of 2015 stands restored.

Civil Appeal Nos.12894-12895 of 2024 preferred by NVVNL, thus,

stands allowed and Civil Appeal No s.12892-12893 of 2024

preferred by SEL stands dismissed. The parties shall bear their

own costs.

……………………………………………..J.

[PAMIDIGHANTAM SRI NARASIMHA]

.…..………………………..J.

[ATUL S. CHANDURKAR]

NEW DELHI,

JANUARY 30, 2026.

Description

Supreme Court Clarifies Scope of Judicial Review in Arbitration: Liquidated Damages in Public Utility PPAs

The recent Supreme Court pronouncement in M/S SAISUDHIR ENERGY LTD. vs. M/S NTPC VIDYUT VYAPAR NIGAM LTD. (2026 INSC 103) brings critical clarity to the application of the Arbitration and Conciliation Act, 1996, particularly concerning the judicial review of arbitral awards and the enforcement of liquidated damages in PPA (Power Purchase Agreement) disputes. This significant ruling, now accessible on CaseOn, delves into the delicate balance between upholding arbitral autonomy and the limited supervisory role of courts, emphasizing adherence to contractual terms in projects of public interest.

Case Background: Saisudhir Energy Ltd. v. NTPC Vidyut Vyapar Nigam Ltd.

The dispute originated from a Power Purchase Agreement (PPA) dated January 24, 2012, between M/s Saisudhir Energy Limited (SEL), a Solar Power Developer, and M/s NTPC Vidyut Vyapar Nigam Limited (NVVNL), the nodal agency for the Jawaharlal Nehru National Solar Mission (JNNSM). The PPA mandated SEL to commission a 20 MW solar power project by February 26, 2013. However, SEL failed to meet this deadline, commissioning 10 MW after a two-month delay and the remaining 10 MW after a five-month delay.

Clause 4.6 of the PPA provided for liquidated damages in the event of delay, specifying a rate of Rs. 1,00,000/- per MW per day for delays exceeding three months. NVVNL invoked this clause, leading to arbitration. The Arbitral Tribunal, in a majority award, directed SEL to pay NVVNL ₹1.2 crores, being 20% of the original performance guarantee.

The Journey Through the Courts: Arbitral Tribunal to High Court

Arbitral Award and Section 34 Review

Aggrieved by the arbitral award, both parties approached the Delhi High Court under Section 34 of the Arbitration and Conciliation Act, 1996. The learned Single Judge found that SEL had indeed delayed commissioning the project. While acknowledging that NVVNL had not proved actual damages or made direct investments, the Single Judge modified the arbitral award. Citing the public utility nature of the project and the difficulty in proving exact losses, the court granted 50% of the damages awardable under Clause 4.6 of the PPA, which amounted to approximately ₹27.06 crores. This amount was to be recovered by adjusting ₹25 lakhs per month from payments due to SEL.

Section 37 Appeal: Division Bench's Modification

The parties further appealed to the Division Bench of the Delhi High Court under Section 37. The Division Bench largely concurred with the Single Judge on the public utility aspect and the difficulty in proving specific damages. However, it proceeded to re-calculate the liquidated damages, resulting in a reduced award of ₹20.70 crores. This re-calculation was based on its interpretation of varying damage rates specified in Clause 4.6 for different periods of delay.

Understanding the Legal Framework (IRAC - Rule)

Section 74, Indian Contract Act, 1872: Liquidated Damages

Section 74 of the Indian Contract Act, 1872, governs compensation for breach of contract where a sum is stipulated as a penalty or liquidated damages. It states that the aggrieved party is entitled to reasonable compensation not exceeding the amount named, *whether or not actual damage or loss is proved*. An exception exists for contracts involving public duty or public interest, where the whole sum mentioned may be payable upon breach.

The Supreme Court, referencing its earlier decisions in *Kailash Nath Associates vs. D. D. A.* (2015 INSC 22) and *M/s Construction and Design Services vs. D.D.A.* (2015 INSC 92), reiterated that while proof of actual damage is generally a *sine qua non* under Section 74, this requirement is relaxed for public utility projects. In such cases, the delay itself can be deemed to have caused loss, making it difficult to quantify, and thus, pre-estimated liquidated damages are justifiable. The burden shifts to the party in breach to prove that no loss was caused.

Judicial Review Under Arbitration and Conciliation Act, 1996

The Court also considered the scope of judicial intervention under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.

  • Section 34: Setting Aside/Modifying Awards

    In *Gayatri Balasamy vs. ISG Novasoft Technologies Limited* (2025 INSC 605), a Constitution Bench recognized the limited power of a Section 34 court to modify an arbitral award, particularly through the doctrine of severability, to avoid unnecessary delays and additional arbitration rounds. This power, however, must remain within the statutory contours and not amount to a merit-based re-evaluation of the dispute.

  • Section 37: Appeals

    The judgment referenced *AC Chokshi Share Broker Private Limited vs. Jatin Pratap Desai and another* (2025 INSC 174), which clarified that a Section 37 court's role is to determine if the Section 34 court exercised its jurisdiction properly and rightly, without exceeding its scope. It cannot substitute its own view for a plausible view taken by the Section 34 court, nor engage in a fresh fact-finding exercise or merit review.

Supreme Court's Analysis (IRAC - Analysis)

Admitted Delay and Public Interest Nature

The Supreme Court affirmed that SEL's delay in commissioning the solar power project was an undisputed fact, triggering Clause 4.6 of the PPA. It also unequivocally held that the JNNSM project, aimed at promoting green energy, was undeniably a public utility project. Consequently, NVVNL was not obligated to prove specific financial losses, as the delay itself constituted a loss in terms of missed policy objectives and environmental benefits. SEL failed to discharge its burden to prove that no loss was caused.

Section 34 Court's Permissible Modification

The Supreme Court upheld the Single Judge's decision to modify the arbitral award and grant 50% of the calculated liquidated damages. This modification was considered a permissible exercise of jurisdiction under Section 34, falling within the limited scope for modification as per *Gayatri Balasamy*. The Single Judge's computation, which applied Clause 4.6 and awarded approximately ₹27.06 crores (50% of the total claim under that clause), was deemed neither arbitrary nor beyond the terms of the PPA.

Legal professionals on CaseOn.in can swiftly grasp such jurisdictional nuances and the specific application of legal principles to factual scenarios through 2-minute audio briefs, enabling quick analysis of complex rulings like this one.

Section 37 Court Exceeded Jurisdiction

Critically, the Supreme Court found that the Division Bench of the High Court, in its Section 37 appeal, exceeded its permissible jurisdiction. By re-calculating the quantum of liquidated damages and reducing the amount to ₹20.70 crores, the Division Bench effectively substituted its own view for the plausible view taken by the Single Judge. This action amounted to a merit-based re-evaluation, which is outside the limited appellate powers of a Section 37 court, as established in *AC Chokshi*.

The Verdict (IRAC - Conclusion)

The Supreme Court concluded that the Division Bench was not justified in modifying the amount of reasonable compensation determined by the learned Single Judge. It set aside the Division Bench's judgment to that extent and restored the judgment of the learned Single Judge of the Delhi High Court in OMP No. 410 of 2015 and OMP No. 446 of 2015. Accordingly, NVVNL's appeals (Civil Appeal Nos. 12894-12895 of 2024) were allowed, and SEL's appeals (Civil Appeal Nos. 12892-12893 of 2024) were dismissed. The parties were directed to bear their own costs.

Why This Judgment Matters for Legal Professionals and Students

This Supreme Court judgment is an essential read for legal professionals and students for several reasons:

  • Clarification on Judicial Review: It precisely demarcates the boundaries of judicial intervention under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, reinforcing that appellate courts should not undertake a merit review or substitute their own findings for plausible ones arrived at by lower courts, especially under Section 34.
  • Liquidated Damages in Public Utility Contracts: The ruling reaffirms the principle that in contracts involving public interest, the need to prove actual loss for claiming liquidated damages under Section 74 of the Indian Contract Act is relaxed. The delay itself can constitute sufficient grounds for awarding compensation.
  • Application of Precedents: It effectively integrates and applies key precedents like *Kailash Nath Associates*, *Construction and Design Services*, *Gayatri Balasamy*, and *AC Chokshi*, providing a holistic understanding of these critical areas of law.
  • Contractual Sanctity: The judgment underscores the importance of upholding the terms of a contract, particularly Clause 4.6 in this case, and the entitlement of the aggrieved party to reasonable compensation as per agreed-upon stipulations.

Disclaimer

All information provided in this article is for informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers are advised to consult with a qualified legal professional for advice pertaining to their specific circumstances.

Legal Notes

Add a Note....