As per case facts, the Applicant was a successful bidder for a contract with the Respondent Railways, which was later terminated. The Applicant challenged the termination through a Writ Petition ...
Neeta Sawant CARAP-688-2025
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION APPLICATION NO. 688 OF 2025
M/s. Sowil Limited …..APPLICANT
: VERSUS :
Deputy Chief Engineer
(Construction) Bhusawal ….RESPONDENT
Mr. Shardul Singh with Mr. Smeet Savla & Ms. Priyal Gandhi i/b
M/s. SHS Chambers, for Applicant
Mr. Narayan Bubna with Ms. Pooja Malik, for Respondent
CORAM : SANDEEP V. MARNE, J.
Reserved On :14 January 2026.
Pronounced On : 28 January 2026.
Judgment:
1) This is an application under Section 11 of the Arbitration
and Conciliation Act, 1996 (Arbitration Act) for appointment of
arbitrator for adjudication of disputes and differences between the
parties arising out of contract dated 7 May 2018. While there is no
dispute between the parties about existence of arbitration
agreement, the clause contains a restrictive condition for
arbitration. The relevant clause in the contract provides for
resolution of disputes by arbitration only to the extent of 20% of the
value of the contract. The value of the contract was
Rs.84,52,157.61/- whereas the estimated claim amount is Rs.3
crores and accordingly Railways have opposed appointment of
arbitrator.
_____________________________________________________________________________
PAGE NO. 1 of 36
28 JANUARY 2026
NEETA
SHAILESH
SAWANT
Digitally
signed by
NEETA
SHAILESH
SAWANT
Date:
2026.01.28
18:55:26
+0530
Neeta Sawant CARAP-688-2025
2) A tender notice was issued by the Respondent-Central
Railways on 10 November 2017 for execution of work of preparation
of design and structural drawings for major and important bridges
for the upcoming Manmad- Jalgaon 3
rd
line project. The Applicant
participated in the tender process and was a successful bidder.
Letter of Acceptance dated 12 February 2018 was issued in favour
of the Applicant which indicated that the total value of the contract
as Rs.84,52,157.61/-. Under the contract, the Applicant was
supposed to complete the entire scope of work by provision of
detailed designs and drawings for 22 bridges within 9 months.
Various extensions were granted in favour of the Applicant for
completion of the work. The contract has been terminated by the
Respondent on 23 December 2021 and the Applicant was debarred
from executing the remaining scope of work. Applicant challenged
termination by �ling Writ Petition No.2887/2023, which was
disposed of on 11 June 2025 granting liberty to the Applicant to �le
application under Section 11 of the Arbitration Act. Accordingly, the
Applicant has �led the present Application under Section 11 of the
Arbitration Act.
3) Mr. Singh, the learned counsel appearing for the
Applicant submits that the parties have agreed to resolve the
disputes and differences by arbitration and that the contract
contains Clause-39 providing that the stipulations under Clauses-63
and 64 of the General Conditions of Contract (GCC) would be
applicable for settlement of claims of the contractor. He would
therefore submit that unreasonable condition is put in Clause 39 of
the contract that provisions of Clauses 63 and 64 of the GCC are
applicable only for settlement of claims of disputes between the
parties for value less than or equal to 20% of the value of the
contract. He submits that imposition of this condition is both
_____________________________________________________________________________
PAGE NO. 2 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
arbitrary, as well as discriminatory. That there is no cap for the
Respondent-Railways to have its claims/counterclaims decided
through arbitration and the maximum cap is arbitrarily and
selectively applied to the Applicant. He would then take me through
Clause-64 of the GCC in support of his contention that no restriction
is imposed for decision of counterclaims by the Railways.
4) Mr. Singh further submits that the restriction of non-
arbitrability of claims exceeding 20% of the value of contract is
aimed at discouraging the Contractors from raising full claims and to
restrict them within the limit of 20%. That such unfair bargain
between the parties cannot be permitted to operate and that
therefore the restriction of 20% claim value is required to be
invalidated while preserving the balance part of arbitration
agreement.
5) Mr. Singh would submit that while deciding application
under Section 11 of the Arbitration Act, this Court is empowered to
decide on validity or reasonableness of condition stipulated in the
arbitration clause. In support, he relies on judgment of the Apex
Court in Lombard Engineering Limited Versus. Uttarakhand Jal
Vidyut Nigam Limited
1
. He relies on judgment of the Apex Court in
ICOMM Tele Limited Versus. Punjab State Water Supply and
Sewerage Board and Another
2
in support of his contention that
when an arbitration clause provides for unfair bargaining strength
between the parties, the same can be declared invalid by the Court.
That in ICOMM Tele Limited though the restriction for deposit of
10% claim amount is applied equally to both the parties, the Apex
Court still declared the clause to be invalid as being arbitrary to
Article 14 of the Constitution of India. Relying on Constitution bench
1 2024 4 SCC 341
2 2019 4 SCC 401
_____________________________________________________________________________
PAGE NO. 3 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
judgment of Central Organisation for Railway Electri�cation Versus
ECI SMO MCML JV A Joint Venture Company
3
(CORE), Mr. Singh
submits that the principle of equality applies even at the stage of
appointment of arbitrator. He would submit that in the present case,
the arbitration clause creates inequality by restricting the claims of
the Contractor at 20% while not imposing similar restriction on the
Railways. He relies upon judgment of the Apex Court in Shin
Satellite Public Company Limited Versus Jain Studios Limited
4
where stipulation in the arbitration clause for waiver of right of
appeal is held to be invalid. He submits that the Apex Court has
recognized the principle in Shin Satellite Public Company Limited
(supra) that if the contract is in severed parts, some of which are
legal and unenforceable, lawful parts can be enforced provided they
are severable.
6) Mr. Singh further submits that under Section 11 Court
can make appointment of arbitrator and leave the issue of
jurisdiction in the form of �nancial cap to be decided by the
arbitrator. He relies on judgment of Rajasthan High Court in Jai
Salasar Balaji Construction Company Versus. Union of India
5
. Mr.
Singh would accordingly pray for constitution of Arbitral Tribunal in
the light of express agreement between the parties to resolve the
disputes and differences by arbitration.
7) Mr. Bubna the learned counsel appearing for the
Respondent-Railways would oppose the Application submitting that
the parties have expressly agreed to resolve the disputes and
differences between them by arbitration only if the claim is below
20% of the contract value. That Clause 39 of the contract expressly
provides that if claim is above 20% of the contract value, the same
3 2025 (4) SCC 641
4 2006 (2) SCC 628
5 SB Arbitration Application No. 52 of 2016 decided on 18 August 2017
_____________________________________________________________________________
PAGE NO. 4 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
would not be governed by arbitration. He submits that the clause is
not aimed at discouraging the contractor from claiming more than
20% of the contract value and that the contractor is free to institute
civil suit against Railways if he wants to prosecute claim in excess of
20% of the contract value. That in the present case, the Applicant
has declared the estimated value of the claim at Rs.3 crores which is
400% more than the contract value of Rs.84,52,157.61/-.
8) Mr. Bubna relies on judgment of this Court in Railtech
Infraven Pvt. Ltd. versus. Union of India and Another
6
in support of
his contention that the condition restricting claim at 20% of the
contract value is upheld by this Court. He also relies upon judgment
of the Apex court in State of AP and another versus Obulu Reddy
7
in
support of his contention that similar monetary restriction for
references of disputes to arbitration is considered and applied by the
Apex Court. He also relies upon judgment of Madhya Pradesh High
Court in Seth Mohanlal Hiralal Construction Company Versus. Union
of India and Another
8
and of the Apex Court in Deepak Kumar
Bansal Versus union of India and Another
9
is referred to, in support
of the contention that the condition of 20% value of contract is
repeatedly applied by Courts. He would submit that the restriction of
reference of claim of only 20% of the contract value to arbitration is
provided considering peculiar practice followed by contractors to
raise baseless and escalated claims after securing the amounts
under the bills. He would pray for dismissal of the Application.
9) Rival contentions of the parties now fall for my
consideration.
6 2014 SCC Online Bom 1662
7 1999 (9) SCC 568
8 2018 SCC Online MP 847
9 2009 (3) SCC 293
_____________________________________________________________________________
PAGE NO. 5 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
10) The short issue that arises for consideration is whether
the Arbitral Tribunal can be constituted by this Court in exercise of
powers under Section 11(6) of the Arbitration Act in the light of
estimated claim of the Applicant exceeding 20% of the value of
contract. The total value of the contract awarded to the Applicant
was Rs.84,52,157.61/- whereas in para-46 of the Application, the
Applicant has declared that its estimated value of the claim is Rs. 3
crores towards losses suffered by it due to unlawful termination.
Para 46 of the Application reads thus:
46. The Applicant claims an estimated amount of Rs.3,00,00,000/-
(Rupees Three Crores) towards the losses suffered by the Applicant
due to the illegal and unlawful to rescission /termination, illegal
invocation of the Bank Guarantee, recovery of the amounts due to
the Application by the Respondent, etc under the Contract. The
Petitioner reserves its right to vary its claim at the time of
submitting claims before the Arbitral Tribunal.
11) The contract executed between the parties contains
arbitration Clause-39 which reads thus :-
39. ARBITRATION:
The provisions 63 and 64 of the GCC will be applicable only for
settlement of claims of disputes between the Parties for values less
than or equal to 20% of the value of the contract and when the
claims or disputes are of value more than 20% of the value of
contract, provision of clauses 63 & 64 and other relevant clauses of
GCC will not be applicable and arbitration will not be a remedy for
settlement of such disputes.
39.1 The contractor shall not be entitled to ask for reference to
arbitration before COMPLETION of the work assigned to him under
this contract. The contractor shall seek reference to arbitration to
settle disputes only ONCE within the ambit of condition 39.1 above.
39.2 In terms of clause 63 of General Conditions of Contract-2014,
the disputes and differences, for which provision has been made in
"Special Conditions of Contract" included in tender documents as
above, shall also be deemed as "Excepted matters' and decisions of
the Railway authority thereon shall be �nal and binding on the
contractor and these 'Excepted matter shall stand speci�cally
excluded from the purview of the arbitration clause and not
referred to arbitration.
_____________________________________________________________________________
PAGE NO. 6 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
39.3 Arbitrators to be appointed only by General Manager of
Railways.
39.4 The Claimant Contractor shall seek reference to Arbitration to
settle the disputes only within the ambit of conditions of mentioned
above.
39.5 CLAIMS: As per Clause No.43 (1) & 43(2) of General condition
of contract:-
Clause No:- 43(1):- Monthly statement of claims:- The contractor
shall prepare and furnish to the Engineer once in every month an
account giving full and detailed particulars of all claims for any
additional expenses to which the contractor may consider himself
entitled to and of all extra or additional works ordered by the
Engineer which he has executed during the preceding month and
no claim for payment for and such work will be considered which
has not been included in such particulars.
Clause No 43(2)- Signing of "NO CLAIM Certi�cate: The contractor
shall not be entitled to make any claim whatsoever against the
Railway under or by virtue of or arising out of this contract, nor
shall the railway entertain or consider any such claim, if made by
the contractor, after he shall have signed a "NO CLAIM" Certi�cate
in favour of the railway in such form as shall be required by the
railway after the works are �nally measured up. The contractor
shall be from disputing the correctness of the items covered by "NO
CLAIM Certi�cate or demanding a clearance to Arbitration In
respect thereof.
(emphasis added)
12) Thus, under Clause 39 of the contract, the provisions of
Clauses 63 and 64 of the GCC applies only for settlement of claims
between the parties for value less than or equal to 20% of the value
of contract. Clause-39 further provides that when claims or disputes
exceed 20% of the contract value, provisions of Clauses 63 and 64
and other relevant clauses of GCC would not be applicable and
arbitration would not be a remedy for settlement of such disputes.
13) Since Clause 39 refers to Clauses 63 and 64 of the GCC, it
would be necessary to refer to the said clauses as well:-
63. Matters Finally Determined By The Railway: All disputes and
differences of any kind whatsoever arising out of or in connection
with the contract, whether during the progress of the work or after
its completion and whether before or after the determination of the
_____________________________________________________________________________
PAGE NO. 7 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
contract, shall be referred by the contractor to the GM and the GM
shall, within 120 days after receipt of the contractor's
representation, make and notify decisions on all matters referred
to by the contractor in writing provided that matters for which
provision has been made in Clauses 8, 18, 22(5), 39, 43(2), 45(a),
55, 55-A(5), 57, 57A,61(1), 61(2) and 62(1) to (xlll)(B) of
Standard General Conditions of Contract or in any Clause of the
Special Conditions of the Contract shall be deemed as 'excepted
matters' (matters not arbitrable)and decisions of the Railway
authority, thereon shall be �nal and binding on the contractor;
provided further that 'excepted matters' shall stand speci�cally
excluded from the purview of the Arbitration Clause.
64.(1) Demand For Arbitration:
64.(1) (1) In the event of any dispute or difference between the
parties hereto as to the construction or operation of this contract,
or the respective rights and liabilities of the parties on any matter
in question, dispute or difference on any account or as to the
withholding by the Railway of any certi�cate to which the
contractor may claim to be entitled to, or if the Railway fails to
make a decision within 120 days, then and in any such case, but
except in any of the "excepted matters" referred to in Clause 63 of
these Conditions, the contractor, after 120 days but within 180
days of his presenting his �nal claim on disputed matters shall
demand in writing that the dispute or difference be referred to
arbitration.
64.(1) (ii) The demand for arbitration shall specify the matters
which are in question, or subject of the dispute or difference as also
the amount of claim item-wise. Only such dispute(s)or
difference(s) in respect of which the demand has been made,
together with counter claims or set off, given by the Railway, shall
be referred to arbitration and other matters shall not be included in
the reference.
64.(1) (iii) (a) The Arbitration proceedings shall be assumed to
have commenced from the day, a written and valid
demand for arbitration is received by the Railway.
(b) The claimant shall submit his claim stating the
facts supporting the claims alongwith all the relevant
documents and the relief or remedy sought against
each claim within a period of 30 days from the date of
appointment of the Arbitral Tribunal.
(C) The Railway shall submit its defence statement
and counter claim(s), if any, within a period of 60
days of receipt of copy of claims from Tribunal
thereafter, unless otherwise extension has been
granted by Tribunal.
(d) Place of Arbitration: The place of arbitration
would be within the geographical limits of the
_____________________________________________________________________________
PAGE NO. 8 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
Division of the Railway where the cause of action
arose or the Headquarters of the concerned Railway
or any other place with the written consent of both
the parties.
64.(1) (iv) No new claim shall be added during proceedings by
either party. However, a party may amend or supplement the
original claim or defence thereof during the course of arbitration
proceedings subject to acceptance by Tribunal having due regard to
the delay in malding it.
64.(1) (v) If the contractor(s) does/do not prefer his/their speci�c
and �nal claims in writing, within a period of 90 days of receiving
the intimation from the Railways that the �nal bill is ready for
payment, he/they will be deemed to have waived his/their claim(s)
and the Railway shall be discharged and released of all liabilities
under the contract in respect of these claims.
64.(2) Obligation During Pendency Of Arbitration: Work under the
contract shall, unless otherwise directed by the Engineer, continue
during the arbitration proceedings, and no payment due or payable
by the Railway shall be withheld on account of such proceedings,
provided, however, it shall be open for Arbitral Tribunal to consider
and dedde whether or not such work should continue during
arbitration proceedings.
64.(3) Appointment of Arbitrator:
64.(3) (a)(i) In cases where the total value of all claims in question
added together does not exceed Rs. 25,00,000 (Rupees twenty �ve
lakh only), the Arbitral Tribunal, shall consist of a Sole Arbitrator
who shall be a Gazetted Of�cer of Railway not below JA Grade,
nominated by the General Manager. The sole arbitrator shall be
appointed within 60 days from the day when a written and valid
demand for arbitration is received by GM.
64. (3) (a)(ii) In cases not covered by the Clause 64(3)(a)(i), the
Arbitral Tribunal sh consist of a Panel of three Gazetted Railway
Of�cers not below JA Grade or 2 Railway Gazett Of�cers not below
JA Grade and a retired Railway Of�cer, retired not below the rank
of SAG Of�cer, as the arbitrators. For this purpose, the Railway will
send a panel of more than 3 names of Gazetted Railway Of�cers of
one or more departments of the Railway which may also include
the names of retired railway of�cer empanelled to work as Railway
Arbitrator to the contractor within 60 days from the day when a
written and valid demand for arbitration is received by the GM.
Contractor will be asked to suggest to General Manager at least 2
names out of the panel for appointment as contractor's nominee
within 30 days from the date of dispatch of the request by Railway.
The General Manager shall appoint at least one out of them as the
contractor's nominee and will, also simultaneously appoint the
balance number of arbitrators either from the panel or from outside
the panel, duly indicating the 'presiding arbitrator" from amongst
_____________________________________________________________________________
PAGE NO. 9 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
the 3 arbitrators so appointed. GM shall complete this exercise of
appointing the Arbitral Tribunal within 30 days from the receipt of
the names of contractor's nominees. While nominating the
arbitrators, it will be necessary to ensure that one of them is from
the Accounts Department. An of�cer of Selection Grade of the
Accounts Department shall be considered of equal status to the
of�cers in SA grade of other departments of the Railway for the
purpose of appointment of arbitrator.
64.(3) (a)(iii) If one or more of the arbitrators appointed as above
refuses to act as arbitrator, withdraws from his of�ce as arbitrator,
or vacates his/their of�ce/of�ces or is/are unable or unwilling to
perform his functions as arbitrator for any reason whatsoever or
dies or in the opinion of the General Manager fails to act without
undue delay, the General Manager shall appoint new
arbitrator/arbitrators to act in his/their place in the same manner
in which the earlier arbitrator/arbitrators had been appointed.
Such re-constituted Tribunal may, at its discretion, proceed with
the reference from the stage at which it was left by the previous
arbitrator (s).
64.(3) (a)(iv) The Arbitral Tribunal shall have power to call for
such evidence by way of af�davits or otherwise as the Arbitral
Tribunal shall think proper, and it shall be the duty of the parties
hereto to do or cause to be done all such things as may be necessary
to enable the Arbitral Tribunal to make the award without any
delay. The Arbitral Tribunal should record day to-day proceedings.
The proceedings shall normally be conducted on the basis of
documents and written statements.
64.(3) (a)(v) While appointing arbitrator(s) under Sub-Clause (i),
(ii) & (iii) above, due care shall be taken that he/they is/are not the
one/those who had an opportunity to deal with the matters to
which the contract relates or who in the course of his/their duties
as Railway servant(s) expressed views on all or any of the matters
under dispute or differences. The proceedings of the Arbitral
Tribunal or the award made by such Tribunal will, however, not be
Invalid merely for the reason that one or more arbitrator had, in
the course of his service, opportunity to deal with the matters to
which the contract relates or who in the course of his/their duties
expressed views on all or any of the matters under dispute.
64.(3) (b)(i) The arbitral award shall state item wise, the sum and
reasons upon which it is based. The analysis and reasons shall be
detailed enough so that the award could be inferred therefrom.
64.(3) (b)(ii) A party may apply for corrections of any
computational errors, any typographical or clerical errors or any
other error of similar nature occurring in the award of a Tribunal
and interpretation of a speci�c point of award to Tribunal within 60
days of receipt of the award.
64(3) (b) (iii) A party may apply to Tribunal within 60 days of
receipt of award to make an additional award as to claims
_____________________________________________________________________________
PAGE NO. 10 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
presented in the arbitral proceedings but omitted from the arbitral
award
64.(4) In case of the Tribunal, comprising of three Members, any
ruling on award shell be made by a majority of Members of
Tribunal. In the absence of such a majority, the views of the
Presiding Arbitrator shall prevail.
64.(5) Where the arbitral award is for the payment of money, no
interest shall be payable on whole or any part of the money for any
period till the date on which the award is made.
64.(6) The cost of arbitration shall be bome by the respective
parties. The cost shall inter-alla include fee of the arbitrator(s), as
per the rates �xed by Railway Board from time to time and the fee
shall be borne equally by both the parties. Further, the fee payable
to the arbitrator(s) would be governed by the instructions issued
on the subject by Railway Board from time to time Irrespective of
the fact whether the arbitrator(s) is/are appointed by the Railway
Administration or by the court of law unless speci�cally directed by
Hon'ble court otherwise on the matter.
64.(7) Subject to the provisions of the aforesaid Arbitration and
Conciliation Act 1996 and the rules thereunder and any statutory
modi�cations thereof shall apply to the arbitration proceedings
under this Clause.
14) Since the claim of the Applicant exceeds 20% value of the
contract (it is approximately 400% of the value of contract)
Railways have opposed constitution of Arbitral Tribunal contending
that there is no arbitration agreement for adjudication of disputes
and differences in respect of the claims raised by the Applicant.
Existence of arbitration agreement under Section 7 of the
Arbitration Act is a
sine-qua-non for exercise of power by the Court
under Section 11 for appointment of an arbitrator. In the present
case, there is arbitration agreement between the parties. However,
there is a restrictive covenant in the arbitration agreement and
parties have agreed that the disputes only to the extent of claims
upto 20% of the contract value would be resolved through private
arbitration and disputes concerning claims exceeding 20% of the
contract value would not be resolved by arbitration. There is positive
as well as negative covenant in Clause 39 of the contract which not
_____________________________________________________________________________
PAGE NO. 11 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
only provides for dispute resolution mechanism by arbitration in
respect of claims only upto and below 20% of the contract value but
it speci�cally provides that any claim exceeding 20% of contract
value shall not be adjudicated through arbitration. There is thus no
agreement between the parties to resolve disputes relating to the
claim of the Applicant, which is almost 400% of the contract value.
Faced with the above situation, the Applicant has sought to
challenge the restrictive stipulation of 20% of the contract value.
Before considering the challenge of the Applicant, it must however
be observed at the very outset that though oral challenge is raised to
the said restrictive covenant, no speci�c ground in that regard is
pleaded in the arbitration application. Ordinarily therefore this
Court would have been justi�ed in not permitting the Applicant to
raise a challenge to the restrictive covenants in the Arbitration
Agreement in absence of pleadings, however since parties have
canvassed detailed submissions on enforceability of the restrictive
covenant in the arbitration agreement, I proceed to decide the
challenge raised by the Applicant.
15) According to the Applicant, restrictive covenant in the
arbitration agreement providing for dispute resolution mechanism
of claims upto 20% of the contract value is discriminatory since such
restrictive covenant does not apply to Railways. In my view, the
submission is not only misplaced but also speculative. Careful
perusal of Clause 39 of the contract indicates that the same uses the
expression ‘only for settlement of claims of disputes between the
parties for values less than or equal to 20% of the value of contract’.
Thus use of the expression ‘between the parties’ does not seem to
suggest that the restrictive covenant is applicable only
qua the
Applicant and not to Railways. In any case, it is not necessary to
delve deeper into this aspect as the issue of appointment of
_____________________________________________________________________________
PAGE NO. 12 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
arbitrator is required to be decided before any counterclaim can be
made by the Railways. The Court cannot speculate whether
Railways would raise any counterclaim and what would be the value
of such counterclaim. Clause 39.4 uses the words ‘claimant
contractor’ who is required to seek reference to arbitration to settle
the disputes only within the ambit of conditions mentioned in Clause
39.3. Clause 39.3 provides for appointment of arbitrator by the
General Manager which now cannot be enforced in the light of
development of law on the subject of unilateral appointment of
arbitrator. However, when an application is made to the Court for
appointment of Arbitrator, the Court would consider only the value
of the claim of the Contractor and then constitute the Arbitral
Tribunal. What would be the value of the counterclaim �led by the
Railways would be in the realm of speculation at that point of time.
Therefore, the value of counterclaim raised by the Railways cannot
be a determinative factor for deciding whether the dispute can be
referred to arbitration or not in the light of restrictive covenant in
the arbitration agreement. I am therefore not impressed by the
submission of Mr. Singh that the restrictive covenant in the
arbitration agreement is discriminatory.
16) It is further sought to be contended that the restrictive
covenant for arbitration in respect of the claims upto only 20% of the
contract value is aimed at discouraging the contractors from raising
claims in excess of 20% of the contract value against the railways. I
am unable to agree. What parties have agreed under Clause 39 is
that claims upto 20% of the contract value would be adjudicated
through arbitration and that the claims exceeding 20% of the
contract value can be adjudicated in other proceedings. Thus, Clause
39 does not seek to prevent the contractors from seeking
adjudication of claims exceeding 20% of the contract value. In the
_____________________________________________________________________________
PAGE NO. 13 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
event the contractor decides to claim amount in excess of 20% of
contract value from the Railways, he needs to �le civil suit since
such disputes are not agreed to be resolved by arbitration.
17) The principle of party autonomy would apply and the
intention of parties in agreeing for resolution of disputes through
arbitration must be appreciated. Party autonomy is the foundational
principle granting parties the freedom to mutually de�ne their
dispute resolution process. Party autonomy would therefore also
include freedom to mutually agree that only part of dispute would be
resolved by arbitration. Once arbitration agreement is arrived at, it
does not mean that every dispute has to be resolved only by
arbitration. It is for parties to decide whether all or selective
disputes are to be resolved by arbitration. Parties here have clearly
intended that claims of only particular value would be adjudicated
through arbitration while claims exceeding the agreed value would
be resolved through other remedies. It is for the parties to agree as
to whether the disputes would be resolved through arbitration or not
and the Court cannot force the parties to have the disputes resolved
through the mechanism of private arbitration. If there was no
arbitration agreement at all, could Applicant have insisted for
appointment of arbitrator? The answer is obviously in the negative.
Therefore, since parties have expressly agreed that disputes
exceeding 20% of the contract value would not be resolved through
arbitration, the Court cannot force parties to resolve their disputes
through arbitration. The Court would have no jurisdiction to appoint
an arbitrator under Section 11 of the Arbitration Act if there is no
arbitration agreement between the parties to decide the claim of a
particular value.
18) Imposition of restriction of reference of dispute for
arbitration only in respect of the claims upto 20% of the contract
_____________________________________________________________________________
PAGE NO. 14 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
value is sought to be justi�ed by Railways by contending that the
same is imposed essentially to curb tendency on behalf of the
Contractors to �rst receive certi�ed bill amount and thereafter raise
baseless and escalated claims against the Railways. It is contended
that therefore only genuine claims upto 20% of the contract value
can be permitted leaving open remedy for contractors to adopt other
civil remedies if claims exceed 20% of the contract value. In my
view, it is not really necessary to go into validity of reasons as to
why the restriction is imposed in the arbitration agreement. As
observed above, arbitration is essentially governed by the principle
of ‘party autonomy’. The Applicant has agreed that only claims upto
20% of contract value would be adjudicated through arbitration and
that the remedy of arbitration would not be available if claim
amount exceeds 20% of contract value. Once there is agreement
between the parties for adjudication of only certain disputes, it is not
for the Court to overstep its jurisdiction and direct that even those
disputes which are not covered by arbitration agreement must also
be referred to arbitration. The stated objective of the Railways
behind the restrictive covenant is to curb raising of baseless and
in�ated claims by the contractors. However, the restriction still does
not prevent or restrict the contractor from raising claims above 20%
of contract value. The parties have agreed that if claim is below 20%
of contract value, the same can be adjudicated in an informal
manner through private arbitration and if claim exceeds 20% of
contract value, the Contractor will adopt usual civil remedy of �ling
a suit. In my view, therefore a restrictive covenant in the
arbitration agreement cannot be unreasonable for putting an
embargo on right to sue of the Contractor. It does not violate the
provisions of Section 28 fo the Contract Act in any manner.
_____________________________________________________________________________
PAGE NO. 15 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
19) Now I proceed to examine the challenge raised by the
Applicant to the restrictive covenant in the arbitration agreement,
which does not permit adjudication of disputes exceeding 20% of the
contract value through the mechanism of arbitration. It is contended
by the Applicant that the restrictive covenant is both
discriminatory, as well as arbitrary and causes violence to equality
clause enshrined in Article 14 of the Constitution.
20) Before proceeding to examine Applicant’s challenge to
the restrictive covenant in the arbitration agreement, it is �rst
required to be considered as to whether this Court, while exercising
power of appointment of arbitrator under Section 11(6) of the
Arbitration Act, can consider validity of condition in the arbitration
agreement. The law in this regard is now settled by the three Judge
Bench judgment of the Apex Court in Lombardi Engineering Limited
(supra). It Is held that while considering an application under
Section 11(6) of the Arbitration Act for appointment of arbitrator,
the Court can also test the validity or reasonableness of condition
stipulated in the arbitration clause on the touchstone or anvil of
Article 14 of the Constitution of India. The Apex Court held in
Lombardi Engineering Limited paras-70 to 72, 75 ,78, 80, 81 and
83 as under :-
70. The vociferous submission on the part of the learned counsel
appearing for the respondent, that this Court while considering an
application under Section 11(6) of the 1996 Act for the
appointment of arbitrator should not test the validity
reasonableness of the conditions stipulated in the arbitration
clause on the touchstone or anvil of Article 14 of the Constitution,
is without any merit or substance.
71. It would be too much for the respondent to say that it is only the
writ court in a petition under Article 226 of the Constitution that
can consider whether a particular condition in the arbitration
clause is arbitrary.
72. It is not for the �rst time that this Court is looking into the
arbitration clause falling foul of Article 14 of the Constitution while
deciding Section 11(6) application.
_____________________________________________________________________________
PAGE NO. 16 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
75. What is relevant to note in all the above referred decisions of
this Court is the phrase "operation of law". This phrase is of wider
connotation and covers the 1996 Act as well as the Constitution of
India and any other Central or State law.
78. Our Constitution is the paramount source of law in our country.
All other laws assume validity because they are in conformity with
the Constitution. The Constitution itself contains provisions that
clearly provide that any law which is in violation of its provisions is
unlawful and is liable to be struck down. As contained in Article 13,
which provides that all laws which were made either before the
commencement of the Constitution, or are made after it, by any
competent authority, which are inconsistent with the fundamental
rights enshrined in the Constitution, are, to the extent of
inconsistency, void. This again unveils the principle of Grundnorm
which says there has to be a basic rule. The Constitution is the basic
and the ultimate source of law.
80. Thus, in the context of the arbitration agreement, the layers of
the Grundnorm as per Kelsen's theory would be in the following
hierarchy:
(i) Constitution of India, 1950;
(ii) Arbitration and Conciliation Act, 1996 & any other
Central/State law;
(iii) Arbitration agreement entered into by the parties in
light of Section 7 of the Arbitration and Conciliation Act,
1996.
81. Thus, the arbitration agreement, has to comply with the
requirements of the following and cannot fall foul of:
(i) Section 7 of the Arbitration and Conciliation Act;
(ii) any other provisions of the Arbitration and Conciliation
Act, 1996 & Central/State Law;
(iii) Constitution of India, 1950.
83. The concept of "party autonomy" as pressed into service by the
respondent cannot be stretched to an extent where it violates the
fundamental rights under the Constitution. For an arbitration
clause to be legally binding it has to be in consonance with the
"operation of law" which includes the Grundnorm i.e. the
Constitution. It is the rule of law which is supreme and forms parts
of the basic structure. The argument canvassed on behalf of the
respondent that the petitioner having consented to the pre-deposit
clause at the time of execution of the agreement, cannot turn
around and tell the Court in a Section 11(6) petition that the same
is arbitrary and falling foul of Article 14 of the Constitution is
without any merit.
(emphasis added)
_____________________________________________________________________________
PAGE NO. 17 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
21) Thus, Court exercising power of appointing arbitrator
under Section 11 of the Arbitration Act can also determine validity
of condition in the arbitration agreement. Now I proceed to examine
whether the restrictive covenant in the arbitration agreement is
discriminatory or arbitrary or causes violence to Article 14 of the
Constitution of India.
22) I have already held that the restrictive covenant not
providing for arbitration in respect of claims above 20% of contract
value is not discriminatory. For holding the clause to be
discriminatory, the Applicant �rst needs to establish that the same
puts any unreasonable restriction on legal action to be initiated by it.
Thereafter it needs to be demonstrated that such unreasonable
restriction is not applicable to the Railways. In the present case
however the Applicant is unable to demonstrate that the restrictive
covenant is unreasonable or it prevents it from exercising legal
remedies in respect of its claims. Therefore it is not even necessary
to examine the second aspect of applicability of the said restriction
to Railways. The plea of discrimination is sought to be raised in a
speculative manner that Railways can �le a counterclaim exceeding
20% of the contract value. The parties have agreed that when the
claim is to be raised by the contractor, arbitration would be available
only in respect of claims upto 20% of the contract value. In my view
therefore it cannot be contended that the clause is discriminatory.
Having failed to demonstrate that the restrictive covenant in the
arbitration agreement is discriminatory, it is sought to be suggested
that the restriction is arbitrary.
23) Applicant has relied upon judgment of the Apex Court in
ICOMM Tele Limited (supra) in which the arbitration clause
provided for deposit of 10% of the claim amount by the claimant
_____________________________________________________________________________
PAGE NO. 18 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
with further covenant for forfeiture of the deposited 10% amount.
Such condition in the arbitration agreement was challenged as being
unfair bargain between the contractor and the principal. The
condition was justi�ed by the Principal by contending that the same
applied equally to both parties. The Apex Court held that the
condition was not discriminatory as it applied equally to both the
parties. The Apex Court however held that arbitrariness is a
separate and distinct facet of Article 14 and found that the said
condition in the arbitration agreement was arbitrary and violative of
Article 14 of the Constitution of India. Referring to the judgment in
ABL International limited Versus. Export Credit Guarantee
Corporation
10
, the Apex Court held that even within the contractual
spheres, the requirement of Article 14 to act fairly, justly and
reasonably by persons, who are State authorities or
instrumentalities, continues. The Apex Court held that the condition
of deposit of 10% claim amount was unjust to a party losing in the
arbitration on account of provision for forfeiture of the same. The
Apex Court further held that such condition for deposit amounted to
a clog on the process of alternate dispute resolution process through
arbitration. It is held that deterring a party to arbitration from
invoking the alternate dispute resolution process by condition of
pre-deposit of 10% claim amount would discourage arbitration
contrary to the object of declogging the Court system. The Apex
Court held in paras-16, 17, 19, 23 to 27 as under :-
16. Thus, it must be seen as to whether the aforesaid Clause
25(viii) can be said to be arbitrary or discriminatory and violative
of Article 14 of the Constitution of India.
17. We agree with the learned counsel for the respondents that the
aforesaid clause cannot be said to be discriminatory in that it
applies equally to both However, Respondent 2 and the appellant.
arbitrariness is a separate and distinct facet of Article 14.
10 2004 3 SCC 553
_____________________________________________________________________________
PAGE NO. 19 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
19. We have thus to see whether Clause 25(viii) can be said to be
arbitrary and violative of Article 14 of the Constitution of India.
23. The important principle established by this case is that unless it
is �rst found that the litigation that has been embarked upon is
frivolous, exemplary costs or punitive damages do not follow.
Clearly, therefore, a "deposit-at-call" of 10 per cent of the amount
claimed, which can amount to large sums of money, is obviously
without any direct nexus to the �ling of frivolous claims, as it
applies to all claims (frivolous or otherwise) made at the very
threshold. A 10 per cent deposit has to be made before any
determination that a claim made by the party invoking arbitration
is frivolous. This is also one important aspect of the matter to be
kept in mind in deciding that such a clause would be arbitrary in
the sense of being something which would be unfair and unjust and
which no reasonable man would agree to. Indeed, a claim may be
dismissed but need not be frivolous, as is obvious from the fact that
where three arbitrators are appointed, there have been known to
be majority and minority awards, making it clear that there may be
two possible or even plausible views which would indicate that the
claim is dismissed or allowed on merits and not because it is
frivolous. Further, even where a claim is found to be justi�ed and
correct, the amount that is deposited need not be refunded to the
successful claimant. Take for example a claim based on a
termination of a contract being illegal and consequent damages
thereto. If the claim succeeds and the termination is set aside as
being illegal and a damages claim of Rupees One crore is �nally
granted by the learned arbitrator at only ten lakhs, only one-tenth
of the deposit made will be liable to be returned to the successful
party. The party who has lost in the arbitration proceedings will be
entitled to forfeit nine-tenths of the deposit made despite the fact
that the aforesaid party has an award against it. This would render
the entire clause wholly arbitrary, being not only excessive or
disproportionate but leading to the wholly unjust result of a party
who has lost an arbitration being entitled to forfeit such part of the
deposit as falls proportionately short of the amount awarded as
compared to what is claimed.
24. Further, it is also settled law that arbitration is an important
alternative dispute resolution process which is to be encouraged
because of high pendency of cases in courts and cost of litigation.
Any requirement as to deposit would certainly amount to a clog on
this process. Also, it is easy to visualise that often a deposit of 10
per cent of a huge claim would be even greater than court fees that
may be charged for �ling a suit in a civil court. This Court in State
of J&K v. Dev Dutt Pandit 16, has held: (SCC pp. 349-50, para 23)
"23. Arbitration is considered to be an important alternative
disputes redressal process which is to be encouraged
because of high pendency of cases in the courts and cost of
litigation. Arbitration has to be looked up to with all
earnestness so that the litigant public has faith in the speedy
process of resolving their disputes by this process. What
happened in the present case is certainly a paradoxical
_____________________________________________________________________________
PAGE NO. 20 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
situation which should be avoided. Total contract is for Rs
12,23,500. When the contractor has done less than 50 per
cent of the work the contract is terminated. He has been
paid Rs 5,71,900. In a Section 20 petition he makes a claim
of Rs 39,47,000 and before the arbitrator the claim is
in�ated to Rs 63,61,000. He gets away with Rs 20,08,000
with interest at the rate of 10 per cent per annum and penal
interest at the rate of 18 per cent per annum. Such type of
arbitration becomes subject of witticism and do not help the
institution of arbitration. Rather it brings a bad name to the
arbitration process as a whole. When claims are in�ated out
of all proportions not only that heavy costs should be
awarded to the other party but the party making such
in�ated claims should be deprived of the costs. We,
therefore, set aside the award of costs of Rs 7500 given in
favour of the contractor and against the State of Jammu and
Kashmir."
25. Several judgments of this Court have also reiterated that the
primary object of arbitration is to reach a �nal disposal of disputes
in a speedy, effective, inexpensive and expeditious manner. Thus,
in Centrotrade Minerals & Metal Inc. v. Hindustan Copper Ltd. 12,
this Court held: (SCC p. 250, para 39)
"39. In Union of India v. U.P. State Bridge Corpn. Ltd. 18 this
Court accepted the view 19 that the A&C Act has four
foundational pillars and then observed in para 16 of the
Report that: (SCC p. 64)
'16. First and paramount principle of the �rst pillar is 'fair,
speedy and inexpensive trial by an Arbitral Tribunal'.
Unnecessary delay or expense would frustrate the very
purpose of arbitration. Interestingly, the second principle
which is recognised in the Act is the party autonomy in the
choice of procedure. This means that if a particular
procedure is prescribed in the arbitration agreement which
the parties have agreed to, that has to be generally resorted
to."
(emphasis in original)
26. Similarly, in Union of India v. Varindera Constructions Ltd. 20,
this Court held: (SCC p. 797, para 12)
"12. The primary object of the arbitration is to reach a �nal
disposition in a speedy, effective, inexpensive and
expeditious manner. In order to regulate the law regarding
arbitration, legislature came up with legislation which is
known as the Arbitration and Conciliation Act, 1996. In
order to make arbitration process more effective, the
legislature restricted the role of courts in case where matter
is subject to the arbitration. Section 5 of the Act speci�cally
restricted the interference of the courts to some extent. In
_____________________________________________________________________________
PAGE NO. 21 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
other words, it is only in exceptional circumstances, as
provided by this Act, the court is entitled to intervene in the
dispute which is the subject-matter of arbitration. Such
intervention may be before, at or after the arbitration
proceeding, as the case may be. In short, court shall not
intervene with the subject-matter of arbitration unless
injustice is caused to either of the parties."
27. Deterring a party to an arbitration from invoking this
alternative dispute resolution process by a pre-deposit of 10 per
cent would discourage arbitration, contrary to the object of de-
clogging the court system, and would render the arbitral process
ineffective and expensive.
24) In my view, the judgment of the Apex Court in ICOMM
TELE Limited (supra)would have no application to the peculiar facts
and circumstances of the case. In ICOMM Tele Limited, there was no
option left to the contractor/claimant but to deposit 10% of the claim
amount as a precondition for arbitration. Since there was an
arbitration clause, �ling of suit by a party not willing to deposit 10%
of claim value, was not an option. Thus, the contractor/claimant
incapable of depositing 10% of claim value was debarred from
exercising any remedy to enforce the claim. The clause did not
provide that if 10% deposit of claim value was not made, the
contractor/claimant was free to exercise remedy before Civil Court.
Furthermore, the clause provided for forfeiture of 10% deposit in the
event of the claimant losing in the claim. Thus, as against well-
established principles governing award of costs of arbitration
against the losing party, the contract provided for forfeiture of
entire 10% of deposited amount. It is in the light of these peculiar
circumstances where the condition in the arbitration clause
discouraged the contractor/claimant from raising any claim that the
condition is held to be violative of Article 14 of the Constitution by
the Apex Court. In the present case, however, the arbitration clause
does not put any restriction on the claimant from exercising the
remedies in respect of the claim. So long as the claim is below 20% of
_____________________________________________________________________________
PAGE NO. 22 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
the contract value, the disputes can be resolved through arbitration.
It is only when the claim exceeds 20% of the contract value, that the
arbitration clause does not apply and the contractor is free to �le a
Civil Suit to enforce the claim. In my view, therefore the arbitration
clause does not impose any embargo on the contractor in enforcing
the entire claim against the Railways. Therefore, the judgment in
ICOMM Tele Limited is clearly distinguishable and the principles
discussed therein would have no application to the peculiar facts of
the present case.
25) The judgment of the Constitution Bench in CORE (supra)
is relied upon in support of the contention that the concept of
equality applies right since the stage of appointment of arbitrator.
The Apex Court has held in pars-67, 68, 70 and 71 as under:
67. Section 18 contains the principle of natural justice to give full
opportunity to parties to present their case. In Union of India v.
Vedanta Ltd. , Indu Malhotra, J., writing for a three-Judge Bench,
observed that the "[f]air and equal treatment of the parties is a
non-derogable and mandatory provision, on which the entire edi�ce
of the alternative dispute resolution mechanism is based". The
purpose of Section 18 is to give the arbitral process a semblance of
judicial proceedings by infusing the principles of equality and
fairness. The theoretical basis for this understanding stems from
the fact that arbitrators are authorities vested with powers to
resolve disputes under the law.
68. The �rst part of Section 18 provides that "parties shall be
treated with equality". The broad nature of the prescription has to
be complied with not only by the Arbitral Tribunals, but also by the
parties while giving expression to party autonomy. The principle
has to be followed in all procedural contexts of arbitral proceedings,
including the stage of appointment of arbitrators. According to
Peter Binder, the principle of equal treatment of parties "means
that no party may be given preference in the arbitrator-selection
process regardless of how strong its bargaining power may be".
Countries such as Germany, the Netherlands, Spain, and Estonia
allow the party that has been disadvantaged by an asymmetric
appointment clause to request courts to appoint an arbitrator or
arbitrators. The underlying principle is that the courts should not
recognise and enforce agreements that are unfair and biased.
70. The concept of equality under Article 14 enshrines the principle
of equality of treatment. The basic principle underlying Article 14
is that the law must operate equally on all persons under like
_____________________________________________________________________________
PAGE NO. 23 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
circumstances. The implication of equal treatment in the context of
judicial adjudication is that "all litigants similarly situated are
entitled to avail themselves of the same procedural rights for relief,
and for defence with like protection and without discrimination" . In
Union of India v. Madras Bar Assn., a Constitution Bench held that
the right to equality before the law and equal protection of laws
guaranteed by Article 14 of the Constitution includes a right to
have a person's rights adjudicated by a forum which exercises
judicial power impartially and independently. Thus, the
constitutional norm of procedural equality is a necessary
concomitant to a fair and impartial adjudicatory process.
71. Arbitration is an adversarial system. It relies on the parties to
produce facts and evidence before the Arbitral Tribunal to render a
decision. Procedural equality is generally considered to contain the
following indicia (1) equal capability of parties to produce facts and
legal arguments; (ii) equal opportunities to parties to present their
case; and (iii) neutrality of the adjudicator. In an adversarial
process, formal equality is important because it helps secure
legitimate adjudicative outcomes and create a level playing �eld
between parties.
26) In CORE, (supra) the Apex Court has dealt with the issue
of unilateral appointment of arbitrator and has accordingly
highlighted the issue of equal treatment to both the parties to
arbitration. The observations are made in the Apex Court in the light
of power conferred on one party to arbitration to choose the
arbitrator. While there can be no dispute about the principle that
equality would apply even at the stage of appointment of arbitrator,
in the present case, the restrictive covenant in the arbitration
agreement does not suffer from the vice of discrimination nor it
causes violence to the principle of equality enshrined in Article 14 of
the Constitution.
27) Judgment of the Apex Court in Shin Satellite Public
Company Limited (supra) is relied upon by the Applicant, in which
the arbitration clause provided for a condition that the arbitrator’s
determination shall be �nal and binding between the parties and
that parties waive all rights of appeal or objection in any jurisdiction.
Since the arbitration agreement sought to give �nality to the award
_____________________________________________________________________________
PAGE NO. 24 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
and prevented parties from exercising remedies under Sections 34
and 37 of the Arbitration Act, the Apex Court held such condition to
be invalid. The judgment is relied on to highlight the principle that a
Court can severe legal and enforceable part of the contract from
unenforceable and invalid part. The Apex Court held in paras-15 and
27 as under:-
15. It is no doubt true that a court of law will read the agreement as
it is and cannot rewrite nor create a new one. It is also true that the
contract must be read as a whole and it is not open to dissect it by
taking out a part treating it to be contrary to law and by ordering
enforcement of the rest if otherwise it is not permissible. But it is
well settled that if the contract is in several parts, some of which
are legal and enforceable and some are unenforceable, lawful parts
can be enforced provided they are severable.
27. The proper test for deciding validity or otherwise of an
agreement or order is "substantial severability" and not "textual
divisibility". It is the duty of the court to sever and separate trivial
or technical parts by retaining the main or substantial part and by
giving effect to the latter if it is legal, lawful and otherwise
enforceable. In such cases, the court must consider the question
whether the parties could have agreed on the valid terms of the
agreement had they known that the other terms were invalid or
unlawful. If the answer to the said question is in the af�rmative, the
doctrine of severability would apply and the valid terms of the
agreement could be enforced, ignoring invalid terms. To hold
otherwise would be
"to expose the covenanter to the almost inevitable risk of
litigation which in nine cases out of ten he is very ill-able to
afford, should he venture to act upon his own opinion as to
how far the restraint upon him would be held by the court to
be reasonable, while it may give the covenantee the full
bene�t of unreasonable provisions if the covenanter is
unable to face litigation".
28) Thus, in Shin Satellite Public Company Limited, (supra)
the Apex Court has recognized the principle of severance of
unenforceable and invalid part of contract from valid and
enforceable part. Ordinarily, therefore if a condition in the
arbitration agreement is found to be unconstitutional, invalid or
unenforceable, the entire arbitration agreement would not be
rendered invalid and can be severed and preserved. However, in the
_____________________________________________________________________________
PAGE NO. 25 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
present case, the condition of adjudication of disputes only upto 20%
of the contract value by arbitration is not found to be
unconstitutional, invalid or unenforceable and therefore there is no
occasion to apply the principle of severance.
29) Mr. Singh has relied upon judgment of Single Judge of
Rajasthan High Court in Jai Shankar Balaji Construction Company
(supra) which involved similar arbitration clause of applicability of
Clauses 63 and 64 of GCC only in respect of claims less than or equal
to 20% of the contract value. The other issue before the Rajasthan
High Court was about validity of Clauses 64(i) to 64(iv) of GCC,
which prevented the party from raising any claims beyond the
period of 90 days after receiving intimation from Railways that �nal
bill was ready for payment, which clause in the GCC is held to be
invalid and unenforceable in the light of provisions of Section 28 of
the Indian Contract (Amendment) Act, 1996. So far as the validity
of condition of arbitrability of claims only upto 20% of the contract
value, the judgment of Rajasthan High Court is inconclusive. Though
the issue of validity of the said condition was raised before the
Rajasthan High Court, it was ultimately found that several work
orders were issued to the contractor and the Court held that value of
all work orders was required to be taken into consideration for
determining the total value of contract. The Rajasthan High Court
held as under:
Adverting now to the argument that wherever the claim is more
than 20% of the contract value, Clause 64 of the GCC would not be
applicable. Reliance in this connection is placed by the respondent –
the Railways on Clause 86 of the GCC, which reads as under:-
“The provision of Clause 63 & 64 of General
Conditions of Contract will be applicable only for
settlement of claims or disputes between the parties
for value less than or equal to 20% of the value of
contract and when claims and disputes are of value
more than 20% of the value of the contract,provision
of clause 63 & 64 and other clause of the General
_____________________________________________________________________________
PAGE NO. 26 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
Conditions of Contract will not be applicable and
arbitration will not b e a remedy for settlement of
such disputes.”
The Railways in this regard has relied on two judgments of a
coordinate bench of this court, namely, M/s. Sisram Bir Singh and
Others Vs. Union of India and Another – 2006 (3) WLC (Raj.574
and M/s. Trimurti Constructions Vs. Union of India and Another –
2006 (3) WLC (Raj.) 680. Opposing this argument,learned counsel
for the petitioner has relied on the judgment of the Supreme Court
in Deepak Kumar Bansal Vs. Union of India and Another – (2009) 3
SCC 223. In that case, the High Court refused to appoint Arbitrator
on the ground that the Circular of respondent Union of India dated
11.06.2003, inserting Clause 18 in the original contract, debarred
reference to arbitration if the claim amount was in excess of 20% of
the total contract value. It was canvassed before the Supreme
Court that in addition to the value of the work originally awarded,
three additional work orders were subsequently issued and if they
are all added together, the total value of the contract cannot be said
to be in excess of 20% of the contract value. The Supreme Court
reversed the judgment of the High Court and remitted the matter
for appointment of arbitrator. The judgment of the Supreme Court
in Deepak Kumar Bansal, supra, was followed by a coordinate
bench of this Court in Sh. Shyam Construction Vs. Union of India
and Another – 2013 (2) CDR 1046 (Raj).
The petitioner has also canvassed and in my view rightly, that the
respondents would not be justi�ed in refusing to make a reference
by relying on the value of the original contract of the work
awarded. Subsequently issued work orders also ought to be
considered for assessing the total value of the work vis-a-vis the
extent of the claim to decide whether or not it exceeds 20% of the
contract value. Besides, the claimant/contractor can also demand
the refund of the earnest money, and the security deposit and can
also claim interest, if not the damages, all of which have to be
treated as part of the claim. The Supreme Court in a recent
judgment in Hyder Consulting (UK) Ltd. Vs. State of Orissa –
(2015) 2 SCC 189, while interpreting the word “sum” mentioned in
Section 31(7) of the Act of 1996, vis-a-vis ‘claim” in the context of
the grant of pre-award interest under Section 31(7)(a) and post-
award interest under Section 31(7)(b) of the Act of 1996, held that
under Section 31(7)(a) of the Act of 1996 the arbitral tribunal is
empowered to include pre-award interest in the sum for which
award is made, which then becomes part and parcel of the same
award. It would however be always open to the Railways to raise
such objection before the Arbitrator, who is, as per Section 16 of
the Act, competent to rule on his own jurisdiction whether the
claim, being less than 20% of the total value of the work is
arbitrable or not but denying reference to arbitrator on this count
would neither be just nor lawful.
30) Mr. Singh has submitted that the Rajasthan High Court
in Jai Salaskar Balaji Construction Company has left it to the
_____________________________________________________________________________
PAGE NO. 27 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
Arbitrator to decide the objection of application of 20% limit to the
claim of the contractor under Section 16 of the Arbitration Act.
Though what Mr. Singh contends is not entirely wrong, the said
course of action is adopted by the Rajasthan High Court considering
the fact that there were multiple work orders/contracts and upon
consideration of cumulative value of all work orders/contracts, the
claim was not breaching the 20% ceiling. Thus what is left to be
decided by the Arbitral Tribunal is whether the claim exceeds 20% of
the value of all work orders or not. Also, the following quoted part of
the judgment of Rajasthan High Court in Jai Salasar Balaji
Construction Company seeks to create confusion as if the Court has
declared restrictive covenant for arbitration of only claims upto 20%
of the contract value as void :-
In view of the above analysis of law and facts, the condition
contained in Clause 64(1)(iv) of the GCC, which assumes waiver of
the claim by the contractor and discharge and release of the
Railways of all its liabilities under contract in respect of the claims,
is held to be void in view of Section 28(b) of the Indian Contract
Act.
31) However, what is declared void under Section 28(b) of
the Contract Act is Clause 64.1(iv) of the GCC which restricted the
contractor from raising any dispute after expiry of period of 90 days
from the date of receipt of intimation from Railways about �nal bill
being ready for payment. It is well established principle of law that a
judgment is an authority for what it decides and not for what can be
decided therefrom. (SEE: Commissioner Of Customs (Port), Chennai
Versus. Toyata Kirloskar Motor Pvt. Ltd.
11
and Secundrabad Club
and Others Versus. CIT-V and Another
12
) Therefore, the judgment of
the Rajasthan High Court in Jai Salasar Balaji Construction
Company is not an authority on the issue of validity of condition in
11 2007(5) SCC 371
12 2024 (18) SCC 310
_____________________________________________________________________________
PAGE NO. 28 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
the arbitration agreement for resolution of disputes in respect of
only those claims which do not exceed 20% of the contract value.
32) On the other hand, a learned Single Judge of this Court in
Railtech Infraventure Pvt Ltd (supra) has considered enforceability
of condition of 20% ceiling for arbitrability. In case before the
learned Single Judge, there was similar arbitration clause which is
quoted in para-5 of the judgment as under :-
5. The Respondents have �led their Af�davit-in-Reply dated 22 nd
September, 2014, wherein it is contended that the above
Application �led by the Applicant is not maintainable as the
Applicant has deliberately suppressed clause 31.1 of the tender
document. It is submitted that the said Clause 31.1 restricts the
operation of Clauses 63 and 64 of the GCC. The said clause 31.1 of
the tender conditions is reproduced hereunder:
"31.1 The provision of clauses 63 and 64 of General
Conditions of contract will be applicable only for settlement
of claims of disputes between the parties for value less than
or equal to 20% of the value of the contract and when the
claims or disputes are of value more than 20% of the value of
contract, provision of clause 63 and 64 and other relevant
clauses of the General Conditions of Contract will not be
applicable and arbitration will not be a remedy for
settlement of such disputes."
33) It was sought to be contended before the learned Single
Judge in Railtech Infraventure Pvt Ltd that the issue of arbitrability
of claim exceeding 20% of the value of contract needs to be left open
to be decided by the arbitrator. This Court, however rejected the
contention and held in para-11 as under :-
11. In the present case, the Applicant has not contended that
Clause No. 31.1 of the tender document is not applicable, or that
the same should not be read with Clauses 63 and 64 of the GCC. The
Learned Advocate for the Applicant has informed the Court that
though the claim of the Applicant exceeds more than 20 per cent of
the value of the Contract, the issue as to whether the same is
arbitrable or not has to be decided by the learned Arbitrator. In my
view, this submission cannot be accepted. The issue as to whether
there exists an Arbitration Agreement between the Parties has to
be decided by the Court, once the same is raised in an Application
_____________________________________________________________________________
PAGE NO. 29 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
under Section 11 of the Act by the Respondent. Reading of Clauses
63 and 64 along with Clause 31.1 of the tender document, leaves no
doubt that the Parties have agreed to refer their disputes to
arbitration only if the claim between the parties is for a value less
than or equal to 20 per cent of the value of the Contract, and it is
further agreed that when the claims or dispute are of a value more
than 20 per cent of the value of the Contract, the provision of
Clauses 63 and 64 and other relevant Clauses of the GCC will not be
applicable, and arbitration will not be a remedy for settlement of
such disputes. In view thereof and more so since the Applicant has
admitted before this Court that the value of its claim before the
Arbitrator exceeds 20 per cent of the value of the contract, there
exists no Arbitration Agreement between the parties to refer their
disputes to arbitration. The issue involved in the present case
cannot be compared with the issues raised by the parties before the
Hon'ble Supreme Court in the case of National Insurance Company
Ltd. (supra) and Arasmeta Captive Power Company Pvt. Ltd.
(supra), and therefore the ratio of the said Judgment is not
applicable to the present case. The same is the case with the
decision of the learned Single Judge of this Court in the case of
Sanjay B. Jawlekar (supra). In view thereof, the above Arbitration
Application is dismissed.
34) It also appears that in Deepak Kumar Bansal, (supra)
the Apex court has taken note of similar restrictive covenant in the
arbitration agreement wherein claims exceeding 20% of the total
costs of the work were not agreed to be resolved through arbitration.
The Apex Court did not hold such restrictive covenant to be
unenforceable but held that the supplementary work orders were
also required to be taken into consideration while determining the
entire contract value for application of 20% limit. It would be
apposite to quote paras-11, 12 and 13 which reads thus :-
11. The respondents, in their objection to the application under
Section 11(6) of the Act, raised a plea that question of appointment
of an arbitrator, in the facts and circumstances of the present case,
could not arise in view of the fact that the claim, as put forward by
the appellant, was an amount being an excess of 20% of total cost of
the work, which is prohibited in terms of the Circular issued on 11-
6-2003. The High Court accepted this plea of the respondent and
rejected the application on the grounds mentioned hereinearlier.
12. In our view, the High Court has misdirected itself in holding
that the claim was in excess of 20% of the total cost of the work.
Admittedly, the work was for a sum of Rs 32,17,641.29 (original)
and three additions viz. Rs 4,99,471.36, Rs 3,25,865.02 and Rs
2,17,748.63 totalling Rs 42,60,726.30, which cannot be in excess
of 20% of the total cost of the work.
_____________________________________________________________________________
PAGE NO. 30 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
13. The High Court has only considered the original work order
that was for Rs 32,17,641.29, which, in our view, must be taken
into account along with three supplementary work orders of Rs
4,99,471.36, Rs 3,25,865.02 and Rs 2,17,748.63 as mentioned
hereinearlier. Therefore, the High Court was wrong in holding that
since the value of the claim of the appellant was more than 20% of
the value of the work and in view of the circular issued by the
respondent, the claim must be held to be more than 20% of the
value of the work and, therefore, disputes could not be referred to
arbitration. Even assuming that the claim was in excess of 20% of
the total cost of the work, even then, the Circular, which came into
effect from 11-6-2003 would not be applicable in the case of the
appellant.
35) The judgment in Deepak Kumar Bansal is followed by
Madhya Pradesh High Court in Seth Mohanlal Hiralal Construction
Company in which it is held in paras-9, 10, 11 as under :-
9. This Court in the matter of Diamond Agencies v. Union of India,
2014 (3) MPLJ 137 considering the general conditions of contract
63 and 64 and also taking note of the special condition II in a case
where the similar controversy was involved has held as under:-
"5. However, it is pertinent to mention here that at the stage
of consideration of application under section 11(6) of the
Act the Court may not be able to decide whether the
particular dispute can be referred to the arbitration, but the
Court can examine whether a particular dispute falls within
the purview of the arbitration clause on admitted facts and
in such a case as it is not necessary to record evidence. In
case of Deepak Kumar Bansal v. Union of India, 2010 (2)
MPLJ (SC) 516 = (2009) 3 SCC 223 2009 Arb. W.L.J.
252(SC), the supreme Court dealt with pan materia clause,
which prohibited the reference of dispute to an Arbitrator, in
case the claim was more than 20% of the value of contract
and, therefore, it was held that dispute can be referred to the
Arbitrator. In other words, if the claim is more than 20% of
the value of contract the dispute cannot be referred for
arbitration.
6. In the backdrop of well-settled legal proposition, the facts
of the case may be seen. Admittedly, the value of the
contract is Rs. 1,24,12,320/-. The petitioner has, admittedly,
submitted the claim to the tune of Rs. 32,24,472/-, which is
25.98% of the contract value.
Clauses 63 and 64 of the General Conditions of Contract provide for
reference of the dispute between the parties to the arbitration. The
relevant extract annexed by the petitioner himself Page 58 of the
application, reads as under:-
_____________________________________________________________________________
PAGE NO. 31 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
"11. Arbitration. The provisions of Clauses 63 and 64 of the
General Conditions of Contract will be applicable only for
settlement of claims or disputes between the parties for
values less than or equal to 20% of the value of the contract."
7.- Thus, in view of the preceding analysis, on admitted acts
of the case, the dispute raised by the petitioner falls beyond
the purview of Clauses 63 and 64 of the General Conditions
of Contract, which provide for arbitration. Therefore, the
dispute cannot be referred for arbitration and the
respondents have rightly rejected the claim of the petitioner
for referring the dispute to the arbitration."
10. In the present case also the record re�ects that the claim of the
petitioner is of about a sum of Rs. 253.77 lakhs which is more than
20% of the total contract value ie. Rs. 5,55,34,728.73. Hence, no
arbitration agreement exists in respect of dispute in question.
11. Counsel for applicant has placed reliance upon the order dated
14/7/2017 passed by the Rajasthan High Court in SB Arbitration
Application No. 15/16, but in view of the judgment of this court in
the matter of Diamond Agencies (supra), the applicant is not
entitled to the bene�t of the single bench order of Rajasthan High
Court.
36) In State of AP Versus Obulu Reddy, (supra) the issue
before the Apex Court was about interpretation of certain GOMs
issued by the State Government. GOM No.403 dated 4 October 1983,
which governed the contract in question, provided for arbitration by
the panel as per valuation of amount. Arbitration was provided in
respect of the claims only upto Rs.50,000/- and for claims above
Rs.50,000/- the Court of competent jurisdiction was to decide the
disputes. The claim in question raised by the Respondent therein
was for Rs.83 lakhs and accordingly the reference was denied. The
Respondent �led application under Section 8 of the Arbitration Act,
1940 which was allowed and the disputes were referred to sole
arbitrator. The State Government challenged the appointment of
arbitrator before the High Court which dismissed the Government’s
Revision. During pendency of Appeal before the Division Bench of
the High Court, another GOM No. 160 dated 1 June 1987 was issued
by the State Government clarifying that if claims were over
_____________________________________________________________________________
PAGE NO. 32 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
Rs.50,000/-, the same could be decided by the Arbitrator or by a
Civil Court. It appears that there were two con�icting decisions in
State of Andhra Pradesh Versus. I Devendra Reddy
13
it was held
that GOM dated 1 June 1987 was only prospective and did not apply
to cases where claims arose out of contracts prior to issuance of the
said GOM. On the other hand, in Vishakhapatnam Urban
Development Authority Versus V. Narayana Raju
14
, the Apex Court
held that the subsequent GOM was clari�catory in nature. The
dispute has been referred to large Bench as to whether the GOM
No.160 dated 1 June 1987 is clari�catory or prospective in nature.
Though we are concerned with the said dispute about the nature of
GOM dated 1 June 1987, what Mr. Bubna wants this Court to note is
the fact that the Apex Court has given effect to the clause in the
arbitration agreement which restricted arbitration only in respect of
the claims upto particular value. Though judgment of the Apex Court
in State of AP Versus. Obulu Reddy cannot be cited as an authority in
support of an abstract principle that a condition speci�ed in
arbitration agreement restricting arbitration only to claim for
speci�ed value is constitutional or enforceable, this Court does take
note of the fact that the Apex Court in three decisions in I. Devendra
Reddy, Vishakapatnam Urban Development Authority and State of
AP Versus Obulu Reddy did not strike down the restrictive covenant
in the arbitration agreement providing for arbitration only in
respect of the claim of speci�ed value. Far from setting aside the
said clauses as unconstitutional or unenforceable, the Apex Court
has interpreted the same.
37) The conspectus of the above discussion is that parties
have speci�cally agreed for resolution of disputes and differences in
respect of the claims upto 20% of the contract value. The restrictive
131999 (9) SCC 571
14 1999 (9) SCC 572
_____________________________________________________________________________
PAGE NO. 33 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
covenant in the arbitration agreement does not defeat the remedy of
the Applicant in any manner. All that it does is to restrict the
mechanism of dispute resolution through private arbitration to
claims upto 20% of the contract value. Applicant is free to pursue
the remedy in respect of the claim exceeding 20% of the contract
value and Clause 39 of the contract or Clauses 63 and 64 of the GCC
do not restrict such remedy of the Applicant in any manner. All that
the Applicant will have to do is to pursue remedy before Civil Court
and not before the Arbitrator.
38) No doubt, the dispute resolution mechanism through
private arbitrations is increasingly encouraged. The mechanism of
dispute resolution through arbitration has de-clogged the pressure
on conventional courts to a large extent. However, the dispute
resolution mechanism through arbitration still continues to be a
matter of agreement between the parties. Parties are free to agree
whether to resolve the disputes through arbitration or not. When
they have the freedom to choose the dispute resolution mechanism,
what must necessarily be recognized is also the freedom to choose
arbitration as dispute resolution mechanism only in respect of the
agreed claims. It cannot be that once there is an arbitration
agreement, every claim under the contract must be resolved
through such arbitration especially when parties speci�cally agree
for exclusion of certain nature of claims. A classic illustration in this
regard is to be found in the insurance contracts. Many times, the
dispute resolution mechanism by arbitration is agreed by the parties
in an insurance contract only in respect of quantum of claim and not
disputes relating to repudiation of the claim. In such contracts,
disputes relating to repudiation cannot be subject to private
arbitration. In several judgments, this restrictive covenant has been
enforced. In Oriental Insurance Company Limited Versus.
_____________________________________________________________________________
PAGE NO. 34 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
Narbheram Power and Steel Private Limited
15
the Apex Court has
held as under :-
23. It does not need special emphasis that an arbitration clause is required
to be strictly construed. Any expression in the clause must unequivocally
express the intent of arbitration. It can also lay the postulate in which
situations the arbitration clause cannot be given effect to. If a clause
stipulates that under certain circumstances there can be no arbitration,
and they are demonstrably clear then the controversy pertaining to the
appointment of arbitrator has to be put to rest.
39) In insurance contracts, the restrictive covenant not
providing for arbitration for resolution of disputes relating to
repudiation has been enforced by the Courts in Vulcan Insurance Co.
Ltd. Versus Maharaj Singh and another
16
and M/s. Mallak
Specialities Pvt. Ltd. Versus. The New India Assurance Co. Ltd
17
.
40) Applying the above principles to the present case, in my
view, Railways cannot be forced to go for arbitration when it has not
agreed for resolution of disputes relating to claims exceeding 20% of
the contract value by arbitration.
41) In my view, therefore there is no agreement between the
parties for arbitration in respect of the Applicant’s claim which it
has quanti�ed at Rs.3 crores in the light of contract value merely
being Rs.84,52,157.61/-. In absence of arbitration agreement, this
Court is unable to exercise jurisdiction under Section 11 of the
Arbitration Act.
15 (2018) 6 SCC 534
16 (1976) 1 SCC 943
17 CARBAP 65 OF 2022 DECIDED ON 30 November 2022
_____________________________________________________________________________
PAGE NO. 35 of 36
28 JANUARY 2026
Neeta Sawant CARAP-688-2025
42) Consequently, the Application fails. It is accordingly
dismissed. Considering the facts and circumstances of the case,
there shall be no order as to costs.
[SANDEEP V. MARNE, J.]
_____________________________________________________________________________
PAGE NO. 36 of 36
28 JANUARY 2026
Legal Notes
Add a Note....