As per case facts, M/s Tata Projects Ltd (Applicant) was contracted by Chhattisgarh Infotech Promotion Society (Respondent No. 1) for the Bharat-Net Project, involving network installation across the state, with ...
1
2026:CGHC:6014
AFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
ARBR No. 28 of 2025
M/s Tata Projects Ltd Having Its Registered Office At Corporate Centre, 3rd
Floor, Building Block B, 34 Sant Tukaram Road, Carnac Bunder, Mumbai
400009
And Its Corporate Office At 14th - 15th Floor, Cignus, Plot No. 71A, Kailash
Nagar, Mayur Nagar, Passpoli Powai, Mumbai 400087 Represented Through
Its Power Of Attorney Holder Shri Rahul Jadwani
... Applicant
versus
1- Chhattisgarh Infotech Promotion Society Having Its Registered Office At
SDC Building, 2nd Floor, Near Police Control Room, Civil Lines, Raipur,
Chhattisgarh 492001 Represented Through Its Chief Executive Officer
2- State Of Chhattisgarh Through Secretary, Department Of Electronics And
Information Technology, Mahanadi Bhawan, Mantralaya, Nava Raipur Atal
Nagar, District - Raipur, Chhattisgarh
3- Union of India Through The Secretary, Department Of Telecommunications,
Ministry of Communications, Sanchar Bhawan, 20 Ashoka Road, New Delhi –
110001
... Respondent(s)
For Petitioner(s) :Mr. Tushad Cooper, Senior Advocate assisted
by Ms. Shrishti Kumar and Mr. Abhishek Vinod
Deshmukh, Advocates.
2
For Respondent(s) :Mr. Abhishek Sinha, Senior Advocate assisted
by Mr. Rishabh Garg, Advocate.
For Respondent No. 2 :Mr. S.S.Baghel, Government Advocate.
For Respondent No. 3 :Mr. Ramakant Mishra, Deputy Solicitor General
alongwith Mr. Tushar Dhar Diwan and Mr.
Rishabh Deo Singh, Advocates.
Date of Hearing :22.01.2026
Date of Judgment : 03.02.2026
Hon’ble Mr. Ramesh Sinha, Chief Justice
C A V Order
1.Heard Mr. Tushad Cooper, Senior Advocate assisted by Ms. Shrishti
Kumar and Mr. Abhishek Vinod Deshmukh, learned counsel for the
Applicant. Also heard Mr. Abhishek Sinha, Senior Advocate assisted by
Mr. Rishabh Garg, learned counsel for the Respondent No. 1, Mr.
S.S.Baghel, learned Government Advocate for the Respondent No. 2 as
well as Mr. Ramakant Mishra, learned Deputy Solicitor General alongwith
Mr. Tushar Dhar Diwan and Mr. Rishabh Deo Singh, learned counsel for
the Respondent No. 3.
2.By this application under Section 11(6) of the Arbitration and Conciliation
Act, 1996 (for short, the Act of 1996), the Applicant has prayed for the
following relief(s):
“a) Appoint an independent and impartial person as the
second arbitrator towards constitution of the arbitration
tribunal under and in connection with the Master
Services Agreement dated 18 July 2018;
b) Pass any such other order(s) as this Hon’ble Court
may deem fit and proper in the facts and circumstances
of the case.”
3.The facts, as projected by the Applicant are that the Applicant is a
Company incorporated under the provisions of Companies Act, 1956. It
3
is one of India’s leading Engineering, Procurement and Construction
(EPC) companies with over 45 years of experience in executing large and
complex urban and industrial infrastructure projects, and provides
turnkey solutions for construction of roads, bridges, rail and metro
systems, commercial buildings, airports, power plants, transmission and
distribution systems, chemical process plants, water and waste
management, and mining systems. The Respondent No. 1, Chhattisgarh
Infotech Promotion Society (for short, the CHiPS), is a registered Society
promoted by the Government of Chhattisgarh. Respondent No. 1 is the
nodal agency for propelling Information Technology (IT) growth and
implementation of IT plans in the State and acts as the State Designated
Agency (for short, the SDA) for implementation of the Bharat-Net Project.
The Respondent No. 2, State of Chhattisgarh is implementing the Bharat-
Net Project through Respondent No. 1 and is the beneficiary of the
Project including the works performed under the Master Services
Agreement (for short, the MSA) and was directly monitoring the
execution of the Project. The Respondent No. 3 is Union of India,
Department of Telecommunications.
4.Bharat-Net Project is one of the flagship schemes of the Respondent No.
3 launched to provide broadband connectivity to 2.5 lakh Gram
Panchayats in the country. Respondent No. 3 supervises the
implementation of the Project in Chhattisgarh in co-ordination with
Respondent No. 1 and 2. The majority of the funding of the Bharat-Net
Project is provided by Respondent No. 3 through Universal Service
Obligation Fund (for short, the USOF) with the objective to provide
affordable broadband connectivity throughout the country. The MSA was
for the benefit of respondents No. 2 and 3 who had actively participated
4
in and monitored the progress of the Project. The Project is entirely
funded by Respondent No.3 who also owns all the Project assets.
5.Mr. Tushad Cooper, learned Senior Advocate appearing for the Applicant
would submit that the Bharat-Net Project is one of the biggest rural
telecom projects in the world, implemented in a phased manner to
provide broadband connectivity to approximately 2.5 lakh Gram
Panchayats in the country. It is a project of national importance and part
of the ‘Digital India’ initiative. In the State of Chhattisgarh, Phase-II of the
Project was being implemented on a State-led model, in collaboration
with Respondent No. 2. Respondent No. 1, being the State-designated
agency, invited bids for design, supply, installation, integration, testing
and commissioning of optical fiber cables (OFC) (underground) IP-MPLS
network, radio network and State network operations center (S-NOC)
including operations and maintenance for 8 years. The tender evaluation
process involved active participation of representatives from Respondent
No. 2 and Respondent No. 3 through various committees. Technical and
financial evaluation was conducted with oversight from USOF and DOT
officials. The selection of successful bidder was approved at multiple
levels including state and central government authorities. On 18.04.2018,
the Applicant submitted its bid for the Project in consortium with Tata
Communications Transformation Services Limited and Dinesh Engineers
Private Limited. The Applicant was the lead bidder and was authorized to
execute the contract and represent the Consortium under and in relation
to the contract. Upon evaluation of bids, the Applicant emerged as the
successful bidder and on 18.07.2018, the MSA was executed between
the Applicant (referred to as the Master System Integrator or MSI in the
MSA) and Respondent No.1, for a total contract value of Rs.
3056,69,43,538/- (inclusive of GST) which included total Capital
5
Expenditure (CAPEX) of Rs.1975,99,99,180/- to be paid during the
implementation phase and Operating Expenditure (OPEX) of
Rs.1080,69,44,357/- to be paid during the O&M phase. In terms of the
MSA, the Applicant was required to complete the implementation phase
within 1 year and then operate and maintain the Project for 7 years.
However, while implementing the Project, the Applicant encountered
several delays and impediments for reasons not attributable to the
Applicant and attributable to the Respondents. Consequently, the
implementation phase was substantially delayed, and the Project Go-live
finally came into effect from 11.09.2023 (on which date as well, about 4%
of the works remained due to Respondent No. 1’s failure to provide Right
of Way). This led to significant additional costs being incurred by the
Applicant. Further, to make the matters worse, the Respondents also
failed to make timely payments to the Applicant for completion of the
works. The Respondent No. 1 committed multiple material and
fundamental breaches of the MSA including, but not limited to: (a) non-
payment of contractual dues; (b) unilateral imposition of penalty; (c)
encashment of performance bank guarantee; (d) arbitrary and unilateral
cancellation of project go-live; (e) interim O&M work orders and failure to
make payment; (f) non-issuance of the work order towards the O&M
works; (g) abandonment of the MSA; and (h) failure to pay prolongation
costs.
6.Mr. Cooper would submit that due to Respondent No. 1’s continued
defaults and non-cooperation, the Applicant was compelled to invoke the
formal dispute resolution mechanism provided under the MSA to protect
its legitimate contractual rights. In terms of clause 1.36 of the MSA, on
20.03.2025, the Applicant issued a notice of dispute setting out its claims
and seeking amicable resolution of disputes but no response was issued
6
to the Applicant’s notice and the disputes were not amicably settled
despite all the efforts of the Applicant. Further, considering the persistent
fundamental defaults committed by the Respondent and the repudiation
of the MSA, the Applicant terminated the MSA by its notice dated
24.04.2025 and the MSA stood terminated with effect from 02.05.2025.
Thereafter, on 08 May 2025, the Applicant issued the Notice of
Arbitration, referring the disputes to arbitration and nominating an
arbitrator, viz. Hon’ble Justice (Retd.) Dilip Babasaheb Bhosale, former
Chief Justice of Allahabad High Court, and requesting the Respondents
to nominate an Arbitrator towards constitution of the Tribunal, wherein
various disputes were referred, as detailed in paragraph 18 of the
petition. Subsequently, on 19.05.2025, Respondent No. 1 issued its
response to the termination notices dated 24.04.2025 and 02.05.2025
issued by the Applicant. Respondent No. 1’s response contained wholly
baseless allegations and was a mere counter blast to the termination of
the MSA by the Applicant. On 28.05.2025, Respondent No. 1 replied to
the Notice of Arbitration refusing to appoint an arbitrator on frivolous
grounds. On the same date, Respondent No. 3 also responded to the
Notice of Arbitration raising a frivolous ground that it is not a party to the
MSA and that the disputes do not pertain to it. The Respondent No. 2 did
not reply to the Notice of Arbitration.
7.Mr. Cooper would further submit that prior to filing of the present petition,
the Applicant had filed two writ petitions, being WPC 3351/2024 and
WPC 2724/2025 before this Hon’ble Court and a petition under Section 9
of the Arbitration Act (being MJC No. 27 of 2025) before the learned
Commercial Court, Raipur seeking interim relief relating to the
performance bank guarantee issued under the MSA. The Notice of
Arbitration was received by Respondent Nos. 1 to 2 on 09.05.2025 and
7
Respondent No. 3 on 13.05.2025. Despite expiry of 30 days from the
receipt of the Notice of Arbitration, the Respondents have failed to
appoint an Arbitrator towards constitution of the Arbitral Tribunal.
Therefore, the Applicant is filing the present application seeking
appointment of an independent and impartial person as the Second
Arbitrator so that the tribunal may be constituted at the earliest. The
conditions required to be fulfilled under Section 11 of the Arbitration Act,
have been satisfied in the present case. As such, an arbitrator must be
appointed in terms of Section 11 of the Arbitration Act.
8.On the other hand, Mr. Abhishek Sinha, learned Senior Advocate
appearing for the Respondent No. 1 has raised preliminary objection that
there is lack of authority of Tata Projects Limited to file Section 11
application on behalf of the consortium. Admittedly, the contract in
question was entered into and executed by a Consortium comprising the
Applicant, M/s Tata Communications Transformation Services Limited
and M/s Dinesh Engineers Limited (DEL). The present Application under
Section 11 of the Act has been filed unilaterally by Tata Projects Limited,
allegedly on behalf of the Consortium, without any authorisation or
consent from the co-members, M/s Tata Communications
Transformation Services Limited and DEL. As such, the Applicant lacks
the requisite locus standi to maintain the instant proceedings, rendering
the Application non-maintainable in law. The Applicant lacks any
express authorisation from the other members of the Consortium for
contesting legal proceedings. It does not have the authority to initiate
legal proceedings unilaterally without express authorisation or joinder of
the other members of the Consortium. Such unilateral legal proceedings
violate the principle of joint and several liability inherent in the Consortium
Agreement. Accordingly, the application is defective, misconceived and
8
liable to be dismissed for the want of proper authorisation and
maintainability. Furthermore, this objection was raised by the
Respondent No. 1 in the previous round of litigation as well, more
particularly in its reply in MJC No. 27 of 2025 before the Hon’ble
Commercial Court, Naya Raipur, filed by the Applicant on the direction of
this Hon’ble High Court seeking a stay on the encashment of Bank
Guarantee which has been disposed of for becoming infructuous.
Despite being aware of this objection, the Applicant has failed to cure this
defect. It is thus clear that the other Consortium members have not
authorised the Applicant to contest the Application on their behalf.
Secondly, the dispute pertains to a Works Contract and falls under the
Exclusive Jurisdiction of the Chhattisgarh Madhyastham Adhikaran
Adhiniyam, 1983 (for short, the Act of 1983). The dispute arises out of a
works contract, as defined under Section 2(i) of the Act of 1983. The Act
of 1983 mandates that all disputes relating to works contracts involving
the State Government or its public undertakings, valued at Rs. 50,000 or
more, shall be exclusively adjudicated by the Arbitration Tribunal
constituted under Section 3 of the Act of 1983. Section 7 of the Act of
1983 provides that party to a works contract, irrespective of an arbitration
clause, shall refer the dispute to the Tribunal. Further, Section 20 of the
1983 Act bars jurisdiction of Civil Courts. Admittedly, the Respondent
No. 1 - the signatory to the contract in question - is an undertaking of the
State of Chhattisgarh. Further, the works under the contract in question
relates to supplying and laying of PLB HDPE Duct (Permanent
Lubricated High – Density Polyethylene Pipe), which is covered under the
definition of works contract under the 1983 Act. The purpose for the
contract in question is to create a digital highway by laying Optical Fibre
Cable from the Block to the Gram Panchayat, in order to enable the
9
intended services, such as internet, telephone, e-services, value-added
services, among others, to customers. As per the scope of works, the
Applicant had to cover a total ring length of 32,466 km in 5964 Gram
Panchayats. As per the BOQ, the Petitioner had to supply 32,466 Km of
PLB HDPE Duct / Pipe and lay down the same under the contract in
question. As such, the work predominantly relates to first supplying and
then laying down pipes for further laying down of Optical Fibre Cable
from Block to Gram Panchayat. Out of the total contract value of Rs.3056
Crores, Rs.1975 Crores was granted for CAPEX. The work of supplying
and laying down the PLB HDPE Duct / Pipe itself amounts to
approximately Rs.1410 Crores as per the rates quoted by the Petitioner
in its bid, which is approximately 75% of the CAPEX value. Therefore, it
is clear that the contract in question is a works contract. Consequently,
the present application for the appointment of a Second Arbitrator under
Section 11(6) of the Act is not maintainable, as the subject matter of the
dispute is statutorily reserved for adjudication by the Tribunal under the
Act of 1983.
9.Mr. Sinha would submit that the parties consent or a prior participation in
the proceedings under the Act of 1996 or the existence of an arbitration
clause in the contract referring to the Act of 1996is immaterial for the
reason that statutory mandate overrides contractual agreements. The Act
of 1983 is a special statute designed to govern disputes arising from
works contracts involving the State Government. The Supreme Court in
M.P. Rural Road Development Authority & Anr. v. M/s L.G.
Chaudhary Engineers and Contractors (2018) 10 SCC 826 held that
disputes arising from works contracts must be referred to the Tribunal
under the Act of 1983, and the Act of 1996 is excluded in such cases.
The Court emphasized that the statutory mandate of the Act of 1983
10
cannot be circumvented by contractual stipulations or conduct of the
parties. Further, there is no waiver by conduct or agreement. The
respondent’s participation in prior proceedings or agreement to an
arbitration clause under the Act of 1996 does not amount to a waiver of
the statutory jurisdiction of the Act of 1983 Act. In Lion Engineering
Consultants v. State of M.P. [(2018) 16 SCC 758], the Apex Court
clarified that objections to the jurisdiction of an Arbitral Tribunal under the
Act of 1996, on the ground that the dispute falls under the Act of 1983,
can be raised even under Section 34 of the Act of 1996, without formal
amendment, and are not barred by prior participation or failure to raise
objections under Section 16(2) of the Act of 1996. The Hon’ble Court
held that the statutory bar under the Act of 1983 Act pertains to the
subject matter being incapable of arbitration under Section 34(2)(b)(i) of
the 1996 Act, and such objections cannot be waived. Any proceeding or
Award passed under the Act of 1996 in a subject matter reserved under
the Act of 1983 Act is a nullity.
10.Mr. Sinha would submit that the contract in question comes under the
definition of “works contract”. Even though the phrase “all types of pipe
supply and pipeline laying work” was expressly inserted by way of
amendment in 2019, the said insertion is merely clarificatory in nature,
and the scope of the pre-amendment definition was already broad
enough to encompass such works. The definition of “works contract” is
wide enough. It is necessary to first go through the pre-amendment
definition of works contract under the Act of 1983 Act. The same is given
below:
“Section 2(i) - works-contract means an agreement in
writing or a letter of intent or work order issued for the
execution of any work relating to construction, repair or
11
maintenance of any building or superstructure, dam, weir,
canal, reservoir, tank, lake, road, well, bridge, culvert,
factory, work-shop, powerhouse, transformer or such other
works of the State Government or public undertakings or of
the Corporations of the State as the State Government may,
by notification, specify in this behalf at any of its stages,
entered into by the State Government or by any official of
the State Government or by public undertakings or
Corporation or by any official of the State Government for
and on behalf of such Corporation or public undertakings
and includes an agreement for supply of goods or material
and all other matters relating to execution of any of the said
works and also includes the services so hired for carrying
out the aforesaid works and shall also include all
concession agreement, so entered into by the State
Government or public undertakings or Corporation, wherein
a State support is involved or not”.
11.Mr. Sinha would submit that a bare perusal of the pre-amendment
definition of "works contract" under Section 2(i) of the Act of 1983 clearly
reveals that the expression is couched in broad and inclusive language,
indicative of the Legislature’s intent to confer it with wide amplitude. The
definition encompasses “any work relating to construction, repair or
maintenance of any building” as well as “such other works of the State
Government which may, by notification, be specified at any of its stages”.
The repeated use of the word “any”—both in reference to the nature of
the work and the type of infrastructure—manifests that the scope of the
definition is not confined solely to the enumerated items, but extends to
other similar works which contain the essential characteristics of a works
contract, irrespective of whether the specific nature of the work is
expressly mentioned. The term “any”, as explained in Black’s Law
Dictionary, carries a diversity of meanings and may imply “all,” “every,”
“some,” or “one”, depending on the context. It is frequently synonymous
with “either,” “each,” or “all.” When interpreted contextually in the present
statutory scheme, it affirms the Legislature’s intent to encompass a wide
spectrum of construction-related activities under the umbrella of “works
12
contract.” This interpretation finds authoritative support in the judgment
of the Hon’ble Madhya Pradesh High Court in Kamini Malhotra v. State
of M.P., (2002) 3 MPJR 389- a pertinent issue analogous to the present
matter came up for consideration before the Hon’ble Madhya Pradesh
High Court. The dispute arose from a contract entered into by the
petitioner for the installation and construction of Water Treatment Plants.
The Petitioner had instituted proceedings under Section 9 of the
Arbitration and Conciliation Act, 1996 seeking interim protection.
However, a preliminary objection was raised by the Respondent-State,
challenging the maintainability of the petition on the ground that the
contract in question qualified as a “works contract” as per Section 2(i) of
the Act of 1983, and hence, by operation of Sections 7 and 20 of the said
Act, the Civil Court’s jurisdiction stood ousted. The Petitioner vehemently
argued that the statutory definition of “works contract” was exhaustive
and rigid, and since the Water Treatment Plant or similar works were not
expressly enumerated within the statutory language, the agreement could
not be brought within its scope. It was further contended that unless a
specific item was listed, the contract should fall outside the jurisdiction of
the Arbitration Tribunal constituted under the Adhiniyam. Conversely, the
Respondent emphasized the wide amplitude of the statutory language,
particularly the repeated use of the term “any”, in reference to “any work
relating to construction, repairs, or maintenance” of “any building,
superstructure, tank, canal, reservoir,” etc. It was argued that the use of
the term “any”, coupled with the inclusive nature of the definition, clearly
manifested the legislative intent to bring within its sweep all such
contracts that involve essential components of construction, even if not
expressly mentioned in the statute. The Hon’ble High Court, after
examining the contract and the relevant provisions of the Adhiniyam,
13
upheld the Respondent’s contention and held that “It is clear that the
word ‘any’ in Section 2(i) of the Adhiniyam appears to have a very wide
spectrum, because it relates to the execution of any work relating to
construction, repairs or maintenance of ‘any’ building or superstructure,
tank, canal, reservoir, etc. The repetition of the word ‘any’ in the said
definition prior to the word ‘work’ as well as before the nature of
construction, e.g., building, superstructure, etc., clearly indicates the
intention of legislature to provide for its wide amplitude and application.”
Applying this reasoning to the facts of the case, the Hon’ble Court further
observed that “The basic work constituting the Water Treatment Plant
included construction of buildings as well as storage tanks and
reservoirs. Ancillary equipment and gadgets for water purification and
treatment may also be involved, but such ancillary items would not alter
the fundamental nature of the work, which essentially remained the
construction of civil structures like buildings and tanks.” Accordingly, the
Hon’ble High Court concluded that the contract was in the nature of a
works contract, falling within the exclusive jurisdiction of the Arbitration
Tribunal constituted under the Act of 1983, and that the jurisdiction of
the Civil Court under Section 9 of the 1996 Act was barred. Similarly, in
D.D.Sharma v. Madhya Pradesh Rural Roads Development
Authority, the Hon’ble High Court addressed the issue of whether
consultancy services rendered for supervision of rural road construction
would fall within the ambit of a “works contract.” The Court held in the
affirmative, reasoning that where the contract involves consultancy
services intrinsically linked with the execution and development of public
works infrastructure, the same falls within the inclusive limb of the
statutory definition, namely “all other matters relating to execution of the
said works i.e., the roads.”
14
12.Mr. Sinha would further submit that the contract in question, though
executed prior to the 2019 amendment to the Act of 1983, nonetheless
falls squarely within the ambit of a “works contract” as defined under the
unamended Act. The nature of the work involves civil construction
activities for laying underground pipelines intended for subsequent laying
of optical fibre cables, which inherently involves trenching, duct
installation, back-filling, and related infrastructure works activities that
are functionally and structurally similar to road construction and utility
infrastructure works. This Hon’ble Court may take judicial notice that
OFC pipeline work often runs along public roads and highways, involves
public right-of-way excavation, and forms part of State-led infrastructure
development. Such activities are essentially civil engineering and public
utility infrastructure works that fall within the broader scope of
“construction and maintenance” activities relating to telecommunication,
electricity, or public service infrastructure. It is a well-established
principle that the true character and substance of the contract, not its
nomenclature or form must guide its classification under any statute.
Accordingly, even in the absence of an express reference to “pipelines”
in the unamended definition, the contract in question satisfies all the
essential indicia of a works contract and was thus, at all relevant times,
amenable to the jurisdiction of the Hon’ble Madhyastham Adhikaran. The
pre-amendment definition of “works contract” itself grants the State
Government the authority to include ‘other works’ within its broad and
inclusive scope. The phrase “…or such other works of the State
Government or public undertakings or of the Corporations of the State as
the State Government may, by notification, specify in this behalf at any of
its stages…” explicitly empowers the State Government to expand the
definition by issuing a notification at any stage of an ongoing works
15
contract involving the government, a public undertaking, or corporation of
the State. As discussed earlier, the expansive nature of the pre-
amendment definition already encompasses the present contract. In line
with this, during the ongoing contract, the government, by way of the
2019 notification, lawfully included pipe supply and pipeline laying work
within the scope of the definition. Even though the definition was
amended during the subsistence of the contract, such a change was well
within the State Government’s powers and squarely falls within the
jurisdiction of Arbitration Tribunal, notwithstanding that it occurred after
the parties had entered into the agreement.
13.In the alternative, Mr. Sinha would submit that the 2019 amendment is
merely clarificatory in nature and is retrospective in its operation. It is a
settled principle of statutory interpretation that clarificatory amendments
are retrospective in nature and operate to explain the law as it always
stood. Such amendments do not create new rights or obligations but are
intended to clarify existing provisions where ambiguity may have existed.
In this context, the 2019 amendment to the Act of 1983, whereby the
term “pipelines” was expressly included within the definition of “works
contract”, is merely clarificatory in nature and does not amount to a
substantive legislative change. The insertion only affirms what was
already implicit within the wide and inclusive language of the original
definition. This principle has been upheld in Viva Highways Ltd. v.
Madhya Pradesh Road Development Corporation, (2018) 3 ESC
1675, wherein a Division Bench of the Madhya Pradesh High Court
considered whether the amended definition of “works contract” in the
Madhya Pradesh Madhyastham Adhiniyam, 1983—introduced by way of
a 2017 amendment—was clarificatory and therefore applicable to
pending and future contracts. The Court affirmed that “Whether a
16
concession agreement or any agreement by whatever name is called
constitutes a works contract must be determined by assessing whether
the essential ingredients of a works contract are satisfied—namely, that
the agreement must be in writing and must involve the execution of any
work relating to construction, repair, or maintenance of the entities listed
in the statute. The nature or label of the contract is immaterial, and any
agreement that substantively involves such work would fall within the
ambit of a works contract, regardless of additional elements that may not
be specifically enumerated.” The Court further observed that the words
“construction,” “repair,” and “maintenance” are broad in scope and may
be divided into multiple categories or subcategories, but such division
does not alter the essential nature of the work. It was also held that the
nomenclature of an agreement is irrelevant in determining its legal
character, and that procedural provisions, including those that govern
jurisdiction or forum, are retrospective in nature unless the statute
expressly provides otherwise. Reliance was also placed on the dictum of
Lord Denning in Blyth v. Blyth, 1966 (1) All ER 524, wherein it was
observed that “The rule that an Act of Parliament is not to be given
retrospective effect applies only to statutes which affect vested rights. It
does not apply to statutes which merely alter the form of procedure or
the admissibility of evidence, or the effect which the court gives to
evidence.”
14.In view of the above legal position, the Madhya Pradesh High Court in
Viva Highways (supra) categorically held that the amendment to the
definition of works contract was clarificatory, and therefore applicable to
pending and future contracts alike. Applying the aforesaid principles to
the present case, Mr. Sinha would submit that the contract at hand—
pertaining to the laying of underground pipelines for the facilitation of
17
optical fiber connectivity—is in essence a civil engineering and
infrastructure contract. The execution of such work involves trenching,
ducting, excavation, backfilling, and surface restoration across public
lands and roadways, all of which are construction-related activities that
fall squarely within the scope of “construction” under the pre-amendment
definition of a “works contract.” The 2019 amendment merely made
explicit what was already implicit in the original definition and was
introduced to dispel any doubt as to the inclusion of such public utility
works. It is, therefore, declaratory in nature. Accordingly, the contract in
question is amenable to the jurisdiction of the Madhyastham Adhikaran,
irrespective of the date of its execution.
15.Without conceding for the sake of argument that the amendment is not
clarificatory, Mr. Sinha would submit that it is a well-established principle
of law that the law in force on the date of trial or final adjudication of a suit
or proceeding is the law to be applied, particularly in matters relating to
procedural rights and jurisdiction. In Sudhir G. Angur & Ors. v. M.
Sanjeev & Ors., (2006) 1 SCC 141, the Hon’ble Supreme Court
categorically held that it is the law prevailing on the date of trial which
governs the rights and remedies available to the parties. The Court
observed that procedural provisions must be construed as retrospective
in nature, unless the statute expressly provides otherwise. Further
reliance is placed on the judgment of the Hon’ble Bombay High Court in
Bhagwan Moti Ram Saraoji v. Onkarmal Ishar Dass, AIR 1952 Bom
365, wherein it was held that no party has a vested right in the
continuation of a particular procedural mechanism or forum, and that it is
a settled principle of interpretation that procedural laws are retrospective
unless expressly stated to be prospective. The Court also held that the
law in force at the time when the matter comes up for trial or final hearing
18
must be applied, and that the court is duty-bound to take judicial notice of
changes in the law and administer justice in accordance with the law as it
stands on the date of trial. In view of the said judicial pronouncements,
without prejudice to above submissions, that even if the contract was
executed prior to the 2019 amendment, the procedural change brought in
by such amendment—particularly with regard to jurisdiction under the
Madhyastham Adhikaran Adhiniyam—would apply to the present
proceedings, as the matter is being adjudicated after the coming into
force of the amendment.
16.Mr. Sinha would next submit that change in forum is procedural in nature
and does not affect vested rights. Even if the amendment changed the
forum, the forum change is procedural. It is a well-settled principle of law
that a party has no vested right in a particular forum or procedural
mechanism. The right to be prosecuted or defended lies only in
accordance with the procedure prescribed by law for the time being in
force. As stated in Maxwell on the Interpretation of Statutes “No person
has a vested right in any course of procedure. He has only the right to
prosecution or defence in the manner prescribed for the time being by or
for the court in which the case is pending, and if, by an Act of
Parliament, the mode of prosecution is altered, he has no other right
than to proceed according to the altered mode.” The principle that
changes in the forum as a part of procedural law apply retrospectively
has been upheld by the Hon’ble Supreme Court in SEBI v. Classic
Credit Ltd., (2018) 13 SCC 1. Further, this position has been analysed
and upheld in the case by the Supreme Court in the case of Neena
Aneja v. Jai Prakash Associates Ltd., (2022) 2 SCC 161.
19
17.In the present case, no proceedings had been initiated or any remedy
availed of prior to the 2019 amendment to the Act of 1983. The dispute
arose and the remedy was sought only after the amendment came into
force. As such, the parties had no crystallised or vested right in a
particular forum, and the change introduced by the amendment is purely
procedural in nature, governing the forum of adjudication. It is therefore
submitted that the amendment merely substitutes the forum before which
disputes arising from “works contracts” are to be resolved, without
affecting any substantive or constitutional rights of the petitioner. The
same shall apply retrospectively in accordance with the established
principles of procedural law.
18.The applicability of the Act is determined by the date on which the
dispute arose, not the date of the contract execution. A bare reading of
Section 7-B(2-a) of the Act of 1983 clearly demonstrates that a reference
petition under the Act is required to be filed within three years from the
date on which the contract is terminated, foreclosed, abandoned, or
otherwise comes to an end, or from the date on which the dispute arises
during the subsistence of the contract. The legislative scheme thus
makes it evident that the determinative point for the application of the Act
is the occurrence of the dispute, and not the date of execution of the
contract. Had the legislature intended to limit the applicability of the
amended provisions to contracts executed after the amendment, it would
have expressly provided so. In the present case, the dispute arose only
after the 2019 amendment came into effect. Consequently, at the time of
filing of the reference petition, the amended definition of “works contract”
which expressly includes “all types of pipe supply and pipeline laying
work” stood incorporated in the Act. The jurisdiction of the Arbitration
Tribunal must be assessed with reference to the law as it stood on the
20
date of the dispute and filing of the reference, and not on the date of
contract execution. The reference petition is accordingly maintainable
under the amended statute. Further, in the absence of a savings and
repeal clause in the Amendment Act of 2019, the intent of the legislature
can be inferred by referring to the savings and repeal clause under the
Act of 1983. The Act of 1983 contains a narrowly tailored savings clause
that exempts only those disputes which were pending before any
arbitrator, umpire, or authority under the provisions of the Arbitration Act
or any other law relating to arbitration. In other words, the Act of 1983
created an exemption solely for matters that were already pending before
an arbitrator or other competent authority under the relevant arbitration
law. In the present case, no proceedings were pending prior to the
commencement of the 2019 Amendment. The dispute arose only after
the amendment came into force. The absence of any such pending
proceedings, coupled with the settled position of law that a change of
forum—being procedural in nature—has retrospective application,
supports the conclusion that the present dispute falls within the
jurisdiction of Madhyastham. Further, the jurisdiction is conferred by law
and cannot be conferred or waived merely by consent or agreement of
the parties. In any event, and without prejudice to the above contentions,
it is a settled principle of law that jurisdiction is conferred by statute and
cannot be assumed by mere agreement, acquiescence, or consent of the
parties. Even assuming, that the Applicant contests the retrospective
applicability of the 2019 amendment to the Act of 1983, and contends
that this Hon’ble Court has exclusive jurisdiction, such contention is
wholly untenable in law. The jurisdiction of the Madhyastham is clearly
reflected in the statement of objects and reasons of the Act of 1983. The
intent behind the legislation is to establish a Tribunal for arbitrating
21
disputes in which the State Government or a public undertaking wholly or
substantially owned by the State Government is a party, along with
matters incidental or connected thereto. The purpose of the legislation is
to provide a forum for resolving such disputes involving the State
Government. Therefore, since the present dispute arises from an
agreement involving a public undertaking, and keeping in view the intent
of the legislation, the contention that the present dispute falls outside the
jurisdiction of the Madhyastham Adhikarn is untenable. The jurisdiction of
a Court is determined by the law applicable on the date the cause of
action arises or when the suit or application is taken up for trial, and not
merely by contractual stipulation. In this regard, reliance is placed on the
judgment of the Apex Court in Harshad Chiman Lal Modi v. DLF
Universal Ltd., {(2005) 7 SCC 791} and a judgment of this High Court in
State of Chhattisgarh vs. Ram Avatar Agrawal Road Construction
Pvt. Ltd., {ARBA No. 22 of 2011}, in which the decision of the Apex
Court in Madhya Pradesh Rural Road Development Authority and
another v. L.G. Chaudhary Engineers and Contractors, {2018 (10)
SCC 826}, was taken note of.
19.Mr. Sinha would submit that the parties’ contractual agreement, if any,
regarding jurisdiction is immaterial where statutory jurisdiction has been
expressly conferred on a specific forum. The Arbitration Tribunal under
the Act of 1983, alone has jurisdiction in respect of the present works
contract. Moreover, it is a well-settled principle that a decree passed
without jurisdiction is a nullity and is non est in the eyes of law. Whether
the defect in jurisdiction is pecuniary, territorial, or subject-matter related,
it vitiates the very authority of the court or forum, and such a defect
cannot be waived or cured by the conduct or consent of the parties. This
application under Section 11(6) for the appointment of an arbitrator is not
22
maintainable, as the dispute pertains to a “works contract” and falls
exclusively under the jurisdiction of the Arbitration Tribunal constituted
under the Act of 1983. He would further submit that the Applicant itself,
in a proceedings before the learned Micro and Small Enterprises
Facilitation Council, Raipur (for short, the MSEFC) titled M/s SVS & Co.
vs Tata Projects Limited: Application No. CG / 15 / S / CGH / 00509 /
1117-18, in its reply dated 19.12.2023, on affidavit, has itself stated that
the Bharat Net Project is a works contract. In view of the said admission
by the Applicant itself, it is submitted that the instant application is not
maintainable and is liable to be dismissed.
20.Mr. Sinha would further submit that the subject matter of the dispute is
not arbitrable since the performance of the work under the agreement is
vitiated by serious fraud and ought to be tried in an open Court. Further,
the work is of national importance. The Applicant refused to participate in
the joint inventory inspection, citing baseless and unfounded grounds of
malice on the part of the Respondent No. 1. Despite the multiple
directions given by the Respondent No. 1 to secure and protect the
interest of the Applicant, the refusal of the Applicant to participate in the
joint inventory inspection was a deliberate attempt to evade a
confrontation on the fraud, forgery and cheating carried out by the
Applicant during the execution of the works under the MSA. The
Respondent No. 1, on 20.06.2025 had entered into a contract with
Telecommunications Consultant India Ltd. (for short, TCIL) a PSU under
the ownership of the Department of Telecommunications, for assessing
and evaluating performance, efficiency and operational status of the
network infrastructure established under the Bharat Net Phase II project.
TCIL has given its initial report dated 04.08.2025 to the Respondent No.
1 a perusal of which would reveal that the Applicant led consortium has
23
failed to comply with the key requisits for execution of the works under
the MSA, and have generated false and fabricated /forged reports in
connivance with the then third party auditor, to extract monies from the
Respondent No. 1 and as such, the Applicant has caused loss to the
public exchequer. The Applicant led consortium generated fake ITPs in
order to extract money without actually executing the works as per the
terms of the MSA. Apart from the same, the Applicant led consortium
engaged on Galaxy Synergy Private Ltd. to implement the project. The
Applicant led consortium has committed serious forgery, fraud and
cheating in the performance of works under the MSA and has thereby
caused a huge loss to the public exchequer at large since not a single
household as on date is connected with the internet. The investigation is
at a nascent stage and the extent of fraud that the Applicant led
consortium has committed is yet to be assessed and evaluated. In such a
scenario, where the fraud is grave and is of a nature that impacts the
public at large, the disputes between the parties cannot be adjudicated
by way of Arbitration since (i) the confidentiality/closed nature of
proceedings attached to Arbitration would not let these facts come out in
the public, thereby, restricting public participation and further disclosure
of crucial facts relating to the case, (ii) several sub-contractors engaged
by the Applicant led Consortium, who are a part of the fraud that has
been committed, would not be a party to the Arbitration proceedings, (iii)
the Arbitrators cannot go beyond the four corners of the MSA, therefore,
it would not be possible for the Respondent No. I to rely upon the extra-
contractual acts of the Applicant led Consortium, such as, engaging sub-
contractors for the purpose of liaising with the Respondent No 1; (iv)
disputes involved are not rights in personam anymore and are now rights
in rem, which are not arbitrable; (v) disputes now relate to rights and
24
liabilities which give rise to criminal offences involving public officials, (vi)
disputes relate to questions arising in the public law domain, among
others. As such, the present dispute is not arbitrable since, inter alia, the
performance of the MSA is vitiated by serious fraud and fabrication of
documents, which has a severe impact in the public domain.
21.Mr. Sinha would next submit that Applicant is not authorised to contest or
initiate legal proceedings on behalf of the other consortium members.
Further, a bare perusal of the Power of Attorney makes it evident that the
Applicant does not have the authority to unilaterally file the present
application. The Applicant lacks the requisite consent from its co-
members to file the present Application. Therefore, the Applicant does
not have any locus to file this application before this Hon’ble Court. The
Applicant has failed to complete the project within the originally stipulated
timeline of 1 year, and its implementation phase remains incomplete even
today, despite several years have passed since the MSA was signed
between the parties. It is vehemently denied that the Applicant has
encountered delays and impediments for reasons attributable to the
Respondent. It is further denied that the implementation phase was
delayed on account of the Respondent’s fault. The Applicant has not
achieved the full project Go Live even in 2023 due to its incompetence
and the Respondent No. 1 has no responsibility for these delays caused
by the Applicant. The Applicant’s default in the completion of the project
timeline is self-evident from the inception of the project. The Respondent
has made payments to the Applicant despite the continuous delays and
non-fulfilment of project milestones without even accounting for the
penalties. Therefore, the Respondent No. 1 has made payments over
and above the amount that way payable to the Applicant. The Applicant
never achieved full project go-live status within the stipulated timeline, as
25
a result, the Respondent No. 1 was entitled to cancel the Go live as per
clause 1.1.14 and clause 1.49 of the MSA. Further, he would submit that
they were compelled to withhold the work orders of O&M due to the non-
completion of implementation phase by the Applicant. It is vehemently
denied that the Respondent No. 1 has abandoned the MSA at any point
in time. Lastly, it is denied that the Applicant incurred any prolongation
costs, and the Respondent No. 1 failed to pay them. It is further
submitted that it was the Applicant who failed to achieve the prescribed
milestone timelines under the MSA. Instead of acknowledging its own
shortcomings, the Applicant attempts to shift the blame onto the
Respondent. Since the contract in question is a “works contract” the
Applicant cannot invoke Arbitration under the Act of 1996 as disputes
relating to “works contract” fall within the jurisdiction of the tribunal
constituted under the Act of 1983.
22.There is no provision under the RFP or MSA that authorises Applicant
to terminate the MSA. On the contrary, 1.32 of the MSA, expressly
vests the right to terminate solely on the purchaser, i.e. the
respondent. It is clear from the contents of the notice of termination
dated 24.04.2025 that the Applicant has shown its unreadiness and
unwillingness to execute the works under the contract. The contents
of the notice of termination dated 24.04.2025 make it clear that the
Applicant intended to breach its obligations after admittedly receiving
Rs. 1509 Crores as payments. Hence, it is stated that the termination
notice dated 24.04.2025 by the Applicant is misconceived and without
any contractual backing. Further the 7 day period stipulated therein
has no contractual backing. The notice was nothing but an attempt to
deflect accountability and fabricate the narrative. Hence, it is
26
vehemently denied that the MSA stood terminated with effect from
02.05.2025. The letter dated 19.05.2025 of the Respondent No. 1
was a reply to the Applicant’s termination notices dated 24.04.2025
and 02.05.2025. It is denied that the Respondent’s reply was a
counterblast to the termination notice and did not contain any valid
grounds. The Applicant did not have any contractual backing or
power for issuing a termination notice under the MSA. In fact, it was
the Applicant who was deflecting their responsibility of non-
performance onto the Respondent. The Applicant was attempting to
threaten the Respondent by issuing such baseless termination notice
to take unfair advantage of their shortcomings to fulfill the contractual
obligations. The Respondent at the very outset of clarified that the
present dispute is governed under the Chhattisgarh Madhyastham
Adhikaran Adhiniyam, 1983 and hence the mechanism under the
1996 Act of nominating the arbitrators will not apply to the present
dispute. Hence, the arbitration notice lacks the jurisdiction and is
devoid of any statutory backing and legal precedents. Without
prejudice to the aforementioned, the Respondent further clarified in its
response that the disputes raised by the Applicant are a consequence
of its non-performance of the contract and cannot be simply shifted
towards the Respondent by twisting the events and fabricating the
narrative. As such, the present application be dismissed.
23.Mr. S.S.Baghel, learned Government Advocate appearing for the
State/Respondent No. 2 basically reiterated the submissions advanced
by Mr. Sinha, learned Senior Advocate appearing for the Respondent No.
1 and prays for dismissal of this arbitration request application. He would
submit that the applicant lacks express authorization from the other
members of the consortium for contesting the legal proceedings and that
27
the dispute arose out of a works contract as defined under Section 2(i) of
the Act of 1983. Since the present dispute arises from an agreement
involving a public undertaking and keeping in view the intent of the
legislation, the present application would not be maintainable.
24.Mr. Ramakant Mishra, learned Deputy Solicitor General, placing reliance
on the written statement filed on behalf of the Respondent No. 3/Union of
India, would submit that the MSA was executed between the State
Implementing Agency (for short, the SIA) which is the CHiPS and the
Project Implementing Agency (for short, the PIA) which is the Applicant
herein and does not involve the Digital Bharat Nidhi (DBN) or Department
of Telecommunications (DoT) as the parties to the contract. The DBN
has already vide letter dated 28.05.2025 intimated the Applicant that
DBN (erstwhile USOF) is not a party to the MSA and therefore, the
dispute does not pertain to DBN and as such, no relief can be sought
against DoT/DBN as they are neither the party to the MSA nor
responsible for execution of obligations under the State-led Bharat Net
implementation in Chhattisgarh.
25.Mr. Cooper, placing reliance on the rejoinder to the return filed by the
Respondent No. 1, would submit that the objections raised by
Respondent No. 1 are frivolous and vexatious and merely an attempt to
avoid constitution of the arbitral tribunal for adjudication of the disputes
through arbitration proceedings as agreed between the parties. As such,
the objections raised must be rejected at the outset itself. It is settled law
that for appointment of an arbitrator under section 11 of the Act, the only
relevant issue to be decided is the ‘prima facie’ existence of an
arbitration clause. All other issues are to be decided by the arbitral
tribunal. In this regard, Mr. Cooper places reliance on the decision of the
28
Apex Court in in Vidya Drolia v. Durga Trading Corporation, (2021) 2
SCC 1, wherein it has been held that the scope of judicial review under
Section 11 of the Arbitration Act is extremely limited and restricted and
that based on the principle of severability and competence-competence,
it is the arbitral tribunal that is the preferred first authority to determine
and decide all questions of non-arbitrability. Particularly, when the facts
are contested, the Hon’ble Court must leave the issues for the arbitrator
to decide since a mini trial is not permissible under Section 11. In the
present case, Respondent No. 1 has admitted the existence of the
arbitration clause and had in fact prayed for adjudication of the disputes
through arbitration (in its Reply dated 16.12.2024 to WPC No. 3351 of
2024). Therefore, the disputes must be referred to arbitration and all
objections raised by Respondent No. 1, i.e. the nature of the contract,
applicability of Act of 1983 etc., can be decided by the arbitral tribunal.
The issues raised by Respondent No. 1 cannot be decided in
proceedings under Section 11 of the Arbitration Act as any such decision
would require a mini trial. Mr. Cooper further places reliance on the
decision of the Apex Court Aslam Ismail Khan Deshmukh v. ASAP
Fluids Pvt. Ltd., (2025) 1 SCC 502, SBI General Insurance Co. Ltd.
v. Krish Spinning, 2024 SCC OnLine SC 1754. He would further submit
that the objection of lack of authority of the Applicant to file application
under Section 11(6) of the Arbitration Act on behalf of the Consortium is
wholly misconceived and contradicted by Respondent No. 1’s own
conduct. Throughout the execution of the MSA, Respondent No. 1
exclusively dealt only with the Applicant. Even in other legal proceedings
(viz. the Writ Petitions filed before this Hon’ble Court, being WPC No.
3351 of 2024 and 2724 of 2025), the Respondent No. 1 did not raise any
such objections and accepted the Applicant’s authority to institute and
29
pursue the said proceedings. Therefore, it is wholly frivolous and
baseless for Respondent No. 1 to now contend that the Applicant does
not have the requisite authority to institute the present proceedings.
Having consistently recognised the Applicant’s authority throughout the
contract execution and in multiple legal proceedings, the said objection is
wholly frivolous and is being taken only to delay the adjudication of the
present application.
26.So far as the contention of the respondents that the present is a works
contract is denied and Mr. Cooper would submit that it does not fall under
the jurisdiction of the Act of 1983 as the Union of India is also a party to
the arbitration proceedings. The Act of 1983, being a State Act, is
applicable only to contracts concerning the State/Public Undertaking.
This is expressly set out in the Preamble and Sections 2 and7 of the Act
of 1983. However, in the present case, Respondent No. 3, viz. the Union
of India is also party to the arbitration proceedings initiated by the
Applicant. The notice of arbitration was issued to and received by
Respondent No. 3 and Respondent No. 3 is also party to the present
proceedings. Therefore, the question of applying the Act of 1983 does
not arise. It is settled law that only the arbitral tribunal can adjudicate
(after reviewing the relevant documents and evidence) whether a non-
signatory is a party to the arbitration agreement. In this regard, Mr.
Cooper places reliance on the decision of the Apex Court in Cox &
Kings Ltd. v. SAP India Pvt. Ltd, 2023 INSC 1051. Further, the
Bharat-Net Project was conceived by the Respondent No. 3 and it
participated in the negotiations of the MSA. The Respondent No. 3 also
actively participated in the performance of the MSA. Even during the
actual implementation of the MSA, the Respondent No. 3 actively
participated in the meetings, regular updates of the work progress,
30
participated in State level implementation Committee meetings, release
of funds. The Respondent No. 3 has not only been aware of the present
dispute but has been actively involved in various discussions relating to
the dispute. The Applicant issued various communications to
Respondent No. 3 to resolve the present dispute and make payment of
the Applicant’s contractual outstanding. For example, Respondent No. 3
was part of the review meeting dated 05 July 2024, for resolution of
issues and ‘Reconciliation of invoices raised by M/s TPL and payments
made so far by CHiPS’. The entire project has been financed solely by
the Respondent No. 3. Further, the order dated 30.04.2025 passed by
this Court in WPC No. 3351/2025, the Respondent No. 1 gave its no
objection to the applicability of the provisions of the Act of 1996. The
Respondent No. 1 is estopped from raising any objection relating to
applicability of Act of 1983 and has waived of his rights. Mr. Cooper
places reliance on the decision of the Apex Court in Mumbai
International Airport P Ltd. v. Golden Chariot Airport, (2010) 10
SCC 422 and Premlata v. Naseeb Bee, (2022) 6 SCC 585, to contend
that having agreed and elected to arbitration under the Act of 1996, the
Respondent No. 1 is estopped from contending that the dispute between
the parties must be resolved under the Act of 1983.
27.Mr. Cooper would further submit that the judgment of Lion Engineering
(supra) was clarified by the Apex Court in Sweta Construction v.
CSPGC (2024) 4 SCC 722; and Gayatri Projects Limited v. MPRDCL:
2025 INSC 698 and in light of what has been laid down in these case, the
Respondent No. 1’s contention that the parties cannot waive the
application of the Act of 1983 is incorrect and even assuming that the Act
of 1983 is applicable, by its reply to the first Writ Petition, the Respondent
No. 1 waived this objection in terms of Section 4 of the Arbitration Act. So
31
far as the contention of the respondents that the present is a works
contract, the same is vehemently denied as the MSA was executed for
execution of the Project in the State of Chhattisgarh, i.e., to set up an
Optical Fibre Cable Network from the Block Head Quarters to Gram
Panchayats to provide high speed broadband connectivity by connecting
85 Blocks, 5987 Gram Panchayats across the State. Therefore, the
contract is not a construction or a works contract, but a telecom contract
for providing high speed internet to Gram Panchayats. Firstly, the word
“any” is used to state any work “relating to” construction, repair or
maintenance of any building or superstructure, dam, weir, canal,
reservoir, tank, lake, road, well, bridge, culvert, factory, work-shop,
powerhouse, transformer or such other works of the State Government or
Public Undertaking as the State Government may, by notification, specify
in this behalf. Therefore, “any works” is only in relation to construction,
repair, maintenance of the 15 items specified in the definition of the works
contract. Any work not relating to construction, repair, maintenance of the
15 items obviously cannot be included in the definition of “works
contract”. Unless specifically enumerated in section 2 of the Act of 1983
or notified by the Government, a contract cannot be considered a “works
contract” irrespective of the nature of the contract. Respondent No. 1’s
contention that ‘similar’ contracts are included in definition of works
contract under the Act of 1983 is therefore incorrect. Firstly, the MSA is
not a contract for pipe supply or pipeline laying work. It is a rural telecom
project for providing broadband to rural areas by laying Optical Fibre
Cables (OFC). In the process of laying OFC, the Applicant had to lay
PLB HDPE Duct but that, by itself, would not change the basic nature of
the contract to a pipeline laying contract.
32
28.According to Mr. Cooper, reliance placed by Mr. Sinha on the decision of
the Madhya Pradesh High Court in Viva Highways (supra) in fact
supports the case of the Applicant. In the said judgment, the dispute
related to the 2017 Amendment to the definition of works contract under
the Act of 1983. The 2017 Amendment stated that since in one judgment,
courts had not considered concession agreements to be part of works
contract definition was being substituted to include concession
agreements. In the Viva Highways judgment, the court held that since
the purpose of the amendment was only clarificatory (no new liability was
fastened but for the same construction works, even concession
agreements were also clarified to be part of the definition) and since the
amendment ‘substituted’ the earlier definition, it was clarificatory in
nature. It is further added here that the 2017 Amendment does not
specify any date of applicability of said amendment, i.e., as to when the
said amendment was brought with effect from, whereas in the present
case, the section 1 (3) of the 2019 Amendment expressly mentions that it
shall come into force from the date of publication in Official Gazette. In
the present case, by the 2019 Amendment, 11 new categories of
contracts were added to the existing 15 categories of contracts contained
in the definition of works contracts under the Act of 1983 and there was
no substitution but an insertion of these new categories of works.
Therefore, the amendment was clearly substantive and therefore
prospective. It is also apposite to state here that under Clause 1.36.5 of
the MSA, the arbitral proceedings are to be governed by the substantive
laws of India. The law at the time of execution of the contract was not the
Act of 1983 since it came into force only on 05 July 2019, i.e., after the
execution of the MSA on 18 July 2018. The Respondent No. 1’s reliance
Classic Credit Ltd. (supra) and Neena Aneja (supra) for the
33
proposition that forum change is purely procedural is wholly misplaced.
The issue is whether the 2019 Amendment is prospective or
retrospective. This does not relate to any change in forum, but it adds
new categories of works in the definition of works contract as defined
under the Act of 1983.
29.Mr. Cooper would further argue that the Respondent No. 1’s contention
that the Applicant had itself admitted that Bharat-Net Project is a works
contract is fundamentally flawed and misleading. The Respondent No. 1
has made a wholly misconceived averment in para 9 of its reply claiming
that in some proceedings before the MSME Council, the Applicant has
made an admission that the Bharat Net Project is a works contract. This
averment is based on a deliberate misrepresentation and constitutes an
attempt to mislead this Hon’ble Court. In the MSME proceedings, viz.
M/s SVS & Co. v. Tata Projects, the Applicant’s reference as a “works
contract” was made specifically to establish that the MSMED Act does
not apply to such contracts. The legal position under the MSMED Act is
that it covers only “goods” and “services” contracts, not “works
contracts”. The Applicant relied on the constitutional definition under
Article 366(29A)(b) to demonstrate that the MSA falls within the genre of
works contracts that are specifically excluded from MSMED Act benefits.
Multiple High Court judgments have consistently held that MSMED Act
benefits are restricted to pure “supply” and “service” contracts and do
not extend to composite “works contracts”. This distinction is based on
the constitutional framework and the specific statutory scheme of the
MSMED Act. However, in the context of Act of 1983, Section 2(i)
provides a narrow, specific definition of works contract limited to
“construction, repair or maintenance” of enumerated items for
establishing jurisdiction of the state statutory tribunals under the Act of
34
1983. These definitions serve completely different statutory purposes and
cannot be conflated. The meaning of works contract under the
Constitution is completely different from the restricted meaning of works
contract under the Act of 1983. In the present case, the MSA is a
composite contract for supply and services. However, it is not covered
under the restricted items of work mentioned in the Act of 1983.
Therefore, Respondent No. 1’s reliance on the MSME proceedings is
wholly misplaced. The Respondent No. 1's attempt to create false
equivalence is legally impermissible. The same contract can be classified
differently under different statutes serving different purposes. The
constitutional definition for excluding MSMED benefits cannot be used to
establish the Act of 1983 jurisdiction, as these are entirely different legal
frameworks with different objectives and scope. In any event, even the
scope of works awarded to the sub-contractor before the MSME was not
the entire scope of works under the MSA. For this reason as well, the
reliance on the MSME proceedings is misplaced. As such, the assertion
of the Respondent No. 1 that the Applicant had itself admitted that the
Project is a works contract is wholly misconceived and misleading and
liable to be rejected.
30.With respect to allegations of fraud, Mr. Cooper would submit that they
are totally misconceived, baseless and without any foundation. The
Respondent No. 1 has made such irresponsible allegations merely in an
attempt to wriggle out of the binding arbitration clause between the
parties and the dispute is not rendered non-aribtrable on the allegation of
fraud. Even assuming, without admitting any fraud, the arbitration
agreement does not cease to exist on allegation of fraud and continues to
bind the parties. The Hon’ble Supreme Court, in A. Ayyasamy v. A.
Paramasivam, (2016) 10 SCC 386, has held that arbitral tribunals are
35
fully competent to adjudicate allegations of fraud, forgery, and criminal
conduct and that if an allegation of fraud can be adjudicated upon in the
course of a trial before an ordinary civil court, there is no reason or
justification to exclude such disputes from arbitration. Further, in Swiss
Timing Limited v. Commonwealth Games 2010 Organizing
Committee, (2014) 6 SCC 677, the Hon’ble Supreme Court has, inter-
alia, held that to shut out arbitration at the initial stage would destroy the
very purpose for which parties had entered into arbitration. Furthermore,
there is no inherent risk of prejudice to any party in permitting arbitration
to proceed simultaneously with criminal proceedings since findings
recorded by Arbitral Tribunal are not binding in criminal proceedings. In
an eventuality where ultimately award is rendered by arbitral tribunal and
criminal proceedings result in conviction rendering the underlying
contract void as provided for in the contract, necessary plea can be taken
on the basis of such conviction to resist execution / enforcement of
award. Conversely, if matter is not referred to arbitration and criminal
proceedings result in an acquittal and thus leaving little or no ground for
claiming that underlying contract is void or voidable, it would result in
undesirable delay in arbitration. Therefore, the Court ought to act with
caution and circumspection whilst examining the plea that the contract is
void/voidable. Further reliance is placed on the judgment of the Apex
Court in Managing Director Bihar State Food Corporation v. Sanjay
Kumar, 2025 INSC 933.
31.Placing reliance on the rejoinder to the return filed by the Respondent No.
2 and 3, Mr. Cooper would deny the submissions advanced by the
Respondent No. 2 and 3, respectively. He would submit that the
Applicant has the authority to file application on behalf of the consortium.
36
He would submit that the objections filed by the respondents are nothing
but an attempt to delay the adjudication of the dispute in any manner.
32.Lastly, Mr. Sinha, learned Senior Advocate appearing for the respondent
No. 1 would submit that in case this Court appoints any retired High
Court Judge as the Sole Aribtrator, he would have no objection. This
submission has been objected to by Mr. Cooper, learned Senior
Advocate appearing for the Applicant on the ground that the agreement
provides for appointment of one Arbitrator from each side and thereafter
the third Arbitrator with the consensus of the two Arbitrators and as such,
this Court should appoint an Arbitrator for the respondents only and
thereafter, both the Arbitrators may appoint the third Arbitrator.
33.I have heard learned counsel appearing for the parties, perused the
pleadings and documents appended thereto.
34.Clause 1.36 of the MSA contains the procedure for resolution of the
disputes which is quoted hereinbelow:
“1.36 Dispute Resolution
1.36.1 The Purchaser and the MSI shall make every effort to
resolve amicably by direct informal negotiations, any
disagreement or disputes, arising between them under or in
connection with the MSA.
1.36.2 If, after Thirty (30) days from the commencement of such
direct informal negotiations, the Purchaser and the MSI have been
unable to resolve amicably a MSA dispute, either party may
require that the dispute be referred for resolution to the formal
mechanism specified in Clause 1.37.3 and Clause 1.37.4.
1.36.3 The Arbitration and Conciliation Act 1996, the rules
hereunder and any statutory modification or reenactment thereof,
shall apply to the arbitration proceedings.
37
1.36.4 The Arbitration proceedings shall be held in Raipur,
Chhattisgarh, India.
1.36.5 The Arbitration proceeding shall be governed by the
substantive laws of India.
1.36.6 The proceedings of Arbitration shall be in English language
1.36.7 If any dispute, difference, question or disagreement arises
between the parties hereto or their respective representatives or
assignees, at any time in connection with construction, meaning,
operation, effect, interpretation or out of the MSA or breach thereof
the same shall be decided by an Arbitral Tribunal consisting of
three Arbitrators. Each party shall appoint one Arbitrator, and the
Arbitrators so appointed shall appoint the third Arbitrator who shall
act as Presiding Arbitrator.
1.36.8 In case, a party fails to appoint an arbitrator within 30 days
from the receipt of the request to do so by the other party or the
two Arbitrators so appointed fail to agree on the appointment of
third Arbitrator within 30 days from the date of their appointment
upon request of a party, the Chief Justice of High Court or any
person or institution designated by him (in case of International
commercial Arbitration) shall appoint the Arbitrators/ Presiding
Arbitrator.
1.36.9 If any of the Arbitrators so appointed dies, resigns,
incapacitated or withdraws for any reason from the proceedings, it
shall be lawful for the concerned party/ arbitrator to appoint
another person in his place in the same manner as aforesaid.
Such person shall proceed with the reference from the stage
where his predecessor had left if both parties consent for the
same; otherwise, he shall proceed de novo.
1.36.10 It is a term of the MSA that the party invoking arbitration
shall specify all disputes to be referred to arbitration at the time of
invocation of arbitration and not thereafter.
1.36.11 It is also a term of the MSA that neither party to the MSA
shall be entitled for any interest on the amount of the award.
1.36.12 The Arbitral Tribunal shall give reasonable award and the
same shall be final, conclusive and binding on the parties.
38
1.36.13 The fees of the arbitrator shall be borne by the parties
nominating them and the fee of the Presiding Arbitrator, costs and
other expenses incidental to the arbitration proceedings shall be
borne equally by the parties.
1.36.14 Subject to as aforesaid the provisions of the Arbitration
and Conciliation Act, 1996 and any statutory modifications or re-
enactment in lieu thereof shall apply to the arbitration proceedings
under this clause.”
35.The first and foremost objection raised by the Respondent No. 1 is that
the present being a ‘works contract’, the works contracts involving the
State Government or its public undertakings, valued at Rs.50,000 or
more, shall be exclusively adjudicated by the Arbitration Tribunal
constituted under Section 3 of the Act of 1983. The second objection is
with regard to the competence of the Applicant to file this present
application as the Applicant is a consortium and the Applicant has not
been authorised by other Consortium members to contest the Application
on their behalf. The next contention is that there exists element of fraud,
forgery and cheating carried out by the Applicant during the execution of
the works under the MSA which cannot be decided in arbitration
proceedings.
36.Admittedly, the MSA was executed between the Applicant and the
Respondent No. 1 on 18.07.2018 and the said MSA contains the
mechanism for resolution of the disputes at clause 1.36 which provides
that each party shall appoint one Arbitrator, and the Arbitrators so
appointed shall appoint the third Arbitrator who shall act as Presiding
Arbitrator. Further, clause 13.6.8 provides that if a party fails to appoint
an Arbitrator within 30 days from the receipt of the request to do so by
the other party or the two Arbitrators so appointed fail to agree on the
appointment of third Arbitrator within 30 days from the date of their
39
appointment upon request of a party, the Chief Justice of High Court or
any person or institution designated by him (in case of International
commercial Arbitration) shall appoint the Arbitrators/ Presiding Arbitrator.
37.Whether or not the dispute pertains to ‘works contract’ is also an issue
which can be adjudicated in the arbitration proceedings. Since the
respondents have raised an objection with regard to maintainability of
this application on the ground that the Applicant has not obtained
consent from other consortium members, that is also an issue which can
be looked into by the Arbitrator. Even otherwise, the Respondent No. 1
has been dealing with the Applicant only from the very beginning and as
such, this objection of the respondents is not of much significance.
38.In SBI General Insurance Co. Ltd. (supra), the Apex Court held as
under:
“114. In view of the observations made by this Court in In
Re: Interplay (supra), it is clear that the scope of enquiry at
the stage of appointment of arbitrator is limited to the
scrutiny of prima facie existence of the arbitration
agreement, and nothing else. …....
xxx xxx xxx
125. We are also of the view that ex-facie frivolity and
dishonesty in litigation is an aspect which the arbitral
tribunal is equally, if not more, capable to decide upon the
appreciation of the evidence adduced by the parties. We
say so because the arbitral tribunal has the benefit of
going through all the relevant evidence and pleadings in
much more detail than the referral court. If the referral court
is able to see the frivolity in the litigation on the basis of
bare minimum pleadings, then it would be incorrect to
doubt that the arbitral tribunal would not be able to arrive
at the same inference, most likely in the first few hearings
itself, with the benefit of extensive pleadings and
evidentiary material.”
40
39.In Aslam Ismail Khan Deshmukh (supra), the Apex Court held that at
Section 11 stage, the Courts must refrain from conducting a mini trial or
entering into disputed factual questions that fall within the arbitral
domain. This approach upholds the intention of the parties at the time of
entering into the agreement, to refer all disputes arising between
themselves to arbitration. Similarly, in Vidya Drolia (supra), the Apex
Court has held that the Arbitral Tribunal is the preferred first authority to
determine and decide all questions of non-arbitrability, hence, at this
stage, whether the dispute involves works contract or nor can also be
decided by the Aribtrator so appointed by this Court.
40.Further, with respect to the allegation of the Respondent No. 1 that the
Applicant has committed fraud and cheating, that aspect can also be
looked into by the Arbitrator, in view of the observations made by the
Apex Court in Deccan Paper Mills Co. Ltd. v. Regency Mahavir
Properties {(2021) 4 SCC 786}. The relevant paragraph reads as under:
“6…...If the subject matter of an agreement between
parties falls within Section 17 of the Indian Contract Act,
1872, or involves fraud in the performance of the contract,
as has been held in the aforesaid judgment, which would
amount to deceit, being a civil wrong, the subject matter of
such agreement would certainly be arbitrable. Further, we
have also held that merely because a particular
transaction may have criminal overtones as well, does not
mean that its subject matter becomes non-arbitrable. ….”
41.Since the Agreement provides for appointment one Arbitrartor from each
side and then appointment of third Arbitrator with the consent of both the
Arbitrators, this Court is of the view that in the fitness of things, it would
be more appropriate that an independent Sole Arbitrator, preferably a
retired Judge of the Hon’ble Supreme Court is appointed to resolve the
41
dispute between the parties, where both the Applicant as well as the
respondents would be at liberty to raise all the grounds as has been
raised in this petition.
42.In view of above, Hon’ble Mr. Justice S. Ravindra Bhat, a retired
Judge of the Hon’ble Supreme Court of India, is appointed to act as the
Sole Arbitrator to resolve the dispute between the parties. As clause
1.36.4 of the Agreement provides that the Arbitration proceedings shall
be held in Raipur, Chhattisgarh, the venue shall be at Raipur.
43.The Registry is directed to communicate this order to Hon’ble Mr. Justice
S. Ravindra Bhat, in the proper address.
44.The remuneration of the Arbitrator shall be settled with the mutual
consent of the parties.
45.The arbitration application, accordingly, stands disposed of. No order
as to costs.
Sd/-
(Ramesh Sinha)
CHIEF JUSTICE
Amit
42
Head Note
The scope of enquiry at the stage of appointment of Arbitrator is limited
to the scrutiny of prima facie existence of the arbitration agreement,
and nothing else. The Courts must refrain from conducting a mini trial
or entering into disputed factual questions that fall within the arbitral
domain.
Legal Notes
Add a Note....