Tender dispute; Technical eligibility; Judicial review; Contract law; Article 14; Arbitrariness; Jharkhand High Court; Steel Authority of India; Work experience; Bid rejection
 02 Sep, 2026
Listen in 01:32 mins | Read in 39:00 mins
EN
HI

M/s United Air Express Vs. Steel Authority of India Limited

  Jharkhand High Court W.P. (C) No. 4210 of 2026
Link copied!

Case Background

As per case facts, M/s United Air Express, the petitioner, submitted a bid for outsourcing services to the Steel Authority of India Limited (SAIL). Their bid was rejected as technically ...

Hello! How can I help you? 😊
Disclaimer: We do not store your data.
Document Text Version

Neutral Citation No. 2026:JHHC:26463-DB

Page 1 of 26

IN THE HIGH COURT OF JHARKHAND AT RANCHI

W.P. (C) No. 4210 of 2026

M/s United Air Express, a partnership firm, through its partner, Mr.

Dinesh Kumar Sonthalia, aged about 54 years, son of Mr. Hari Shankar

Sonthalia, having his office at 12, Diagonal Road, Bistupur PO & PS –

Bistupur, Town – Jamshedpur, District – East Singhbhum.

... Petitioner

Versus

1. Steel Authority of India Limited, a public sector undertaking,

through its Chairman, having his office at Ispat Bhawan, Lodhi

Road, PO & PS – Lodhi Road, New Delhi.

2. The Chief Executive Officer, Bokaro Steel Plant, a unit of Steel

Authority of India Limited, having his office at Bokaro Steel Plant,

PO & PS – Bokaro Steel City, District - Bokaro Steel City;

3. The General Manager, Contract Cell Works, Bokaro Steel Plant,

having his office at Paryavaran Bhawan, PO & PS – Bokaro Steel

City, Bokaro Steel City;

4. The Deputy General Manager, Contract Cell Works, Bokaro Steel

Plant, having his office at Paryavaran Bhawan, PO & PS – Bokaro

Steel City, Bokaro Steel City;

5. The Assistant General Manager, Contract Cell Works, Bokaro Steel

Plant, having his office at Paryavaran Bhawan, PO & PS – Bokaro

Steel City, Bokaro Steel City.

6. FSNL Private Limited, a private limited company registered under

the Companies Act, 2013, through its Director, having its registered

office at FSNL Bhawan, Equipment Chowk, Central Avenue, PO &

PS – Bhilai, District – Bhilai, Chhattisgarh – 490001.

... Respondents

---------

CORAM: HON’BLE THE CHIEF JUSTICE

HON’BLE MR. JUSTICE RAJESH SHANKAR

---------

For the Petitioner: Mr Amit Kumar Das, Senior Advocate

Mr Rahul Lamba, Advocate

Mr Anish Kamal, Advocate

Ms Kanu Priya, Advocate

For Resp. Nos.1-5: Mr Indrajit Sinha, Advocate

Mr Shresth Gautam, Advocate

Neutral Citation No. 2026:JHHC:26463-DB

Page 2 of 26

Mr. Padmanav Shahdeo, Advocate

Mr Himanshu Harsh, Advocate

For Resp. No.6: Mr Sanjoy Piprawall, Advocate

Mr Prince Kumar, Advocate

Mr Jay Prakash, Advocate

---------

Reserved on: 31.08.2026 Pronounced on: 02/09/2026

Per M. S. Sonak, C.J.

1. Heard learned counsel for the parties.

2. Rule. The rule is made returnable immediately at the request and

with the consent of the learned counsel for the parties.

3. The petitioner, by instituting the instant petition, seeks the

following reliefs:-

(a) Setting aside the decision of the Respondent No.1

Company (Annexure 8) whereby the bid offer of the

petitioner has been rejected as technically not eligible

with respect to the Bid Invitation No.

W06/4010034183/7000020135 dated 04.11.2025 issued

by the Respondent No.1 Company for its Bokaro Steel

Plant;

(b) Also setting aside the decision of the Respondent No.1

Company, as contained in emails dated 26.03.2026

(Annexure 7), 21.03.2026 (Annexure 5) and 11.03.2026

(Annexure 3) of the Respondent No.1 Company,

whereby the bid offer of the petitioner has been

adjudged as technically not eligible;

Neutral Citation No. 2026:JHHC:26463-DB

Page 3 of 26

(c) Setting aside the outcome of the reverse auction

conducted by the Respondent No.1 Company pursuant

to the said bid invitation;

(d) Direction upon the respondents to conduct a fresh

reverse auction, permitting the petitioner to participate

in such reverse auction.

4. The above reliefs are sought in the context of a Bid Invitation

dated 04.11.2025, read with the modification/corrigendum dated

06.12.2025, issued by the Steel Authority of India Limited (SAIL),

the 1

st

respondent to this petition, seeking bids for the work/job

title “Comprehensive Outsourcing Services – MRD”.

5. The petitioner, along with others, submitted its bid offer. However,

by email dated 11.03.2026, the 1

st

respondent adjudged the

petitioner as technically ineligible and called upon the petitioner to

furnish experience of excavation of slag pits and processing of slag

in a single work order after self-attestation.

6. The petitioner responded to the email. However, the 1

st

respondent,

by yet another email dated 21.03.2026, declared the petitioner as

technically ineligible on the ground that the submitted work order

does not comply with the similar work criteria as detailed in BI

and the experience of excavation of slag pits and processing of slag

in a single work order with self-attestation.

7. The petitioner, vide letter dated 23.03.2026, submitted a work

completion certificate dated 16.03.2026 issued by Tata Steel

Limited to clarify the issue raised by the 1

st

respondent. Despite

Neutral Citation No. 2026:JHHC:26463-DB

Page 4 of 26

this, the 1

st

respondent, by yet another email dated 26.03.2026,

maintained that the petitioner was technically ineligible. Further,

on 31.03.2026, the 1

st

respondent rejected the petitioner’s bid offer,

holding that the petitioner was technically ineligible.

8. Post rejection of the petitioner’s bid offer, a reverse auction was

held on 01.04.2026 in which the 6

th

respondent was declared as L1.

Hence, the present petition seeks the above-referred reliefs.

9. Mr A.K. Das, learned Senior Advocate for the petitioner,

submitted that the reason disclosed for holding the petitioner

technically ineligible was that the petitioner does not have the

required experience in a single work order. He submitted that the

bid nowhere requires having such experience in one single work

order. The work experience certificates submitted by the petitioner

indisputably show that the petitioner had the required work

experience through two work orders which were a part of a single

work executed by the petitioner for Tata Steel Limited. Thus, the

impugned decision to hold the petitioner technically ineligible was

ex facie arbitrary and unreasonable. He relied on Kimberley Club

Pvt. Ltd. v. Krishna Utpadan Mandi Parishad and Others,

2025 SCC OnLine SC 2323, to support this contention.

10. Mr A.K. Das, without prejudice to the above contention, submitted

that the petitioner was eligible even going by the single work order

given, Work Order No. 3000139124/102, through which the

petitioner had done excavation of slag from the slag pit and its

processing. The value of the work in the said work order was Rs.

Neutral Citation No. 2026:JHHC:26463-DB

Page 5 of 26

55,18,77,901.95, which was much more than the required value

under the Bid Invitation. He therefore submitted that the decision

to hold the petitioner technically ineligible was vitiated by non-

application of mind, ignoring the experience certificate on record

and, otherwise, arbitrary and unreasonable.

11. Mr A.K. Das submitted that the 1

st

respondent has plants at

Burnpur, Durgapur and Bokaro. He submitted that the 1st

respondent invited Bid Invitations with similar experience

requirements for the said three plants. Based on the experience

certificate furnished by the petitioner in respect of the present Bid

Invitation, the 1st respondent adjudged the petitioner as technically

eligible for the plants at Burnpur, Durgapur and Bokaro. He

therefore submitted that the 1

st

respondent, which is a ‘State’ under

Article 12 of the Constitution, acted discriminatorily and has

treated the petitioner unequally when it comes to consideration of

the petitioner’s eligibility status in the present matter. He

submitted that such discrimination violates Article 14 of the

Constitution. He relied on Banshidhar Construction Private

Limited v. Bharat Coking Coal Limited and Others, (2024) 10

SCC 273, to support this contention.

12. Mr A.K. Das finally submitted that the interpretation now

suggested by the 1

st

respondent in its returns is contrary to the

plain reading of the terms and conditions of the Bid Invitation. He

submitted that the interpretation now suggested is belied by the

corrigendum/modification in the eligibility criteria dated

Neutral Citation No. 2026:JHHC:26463-DB

Page 6 of 26

06.12.2025 by specifically excluding the expression “hot” from the

original terms in the Bid Invitation dated 04.11.2025.

13. Based on the above, Mr Das submitted that the eligibility criteria

in the subject Bid Invitation could never be interpreted as requiring

the bidder to have experience in the excavation of hot slag or slag

from hot slag pits as was now sought to be contended. He

submitted that the modification in the eligibility criteria was made

only because the scope of the work in the Bid Invitation was not to

excavate hot slag but to excavate slag only after the same was

cooled. Accordingly, Mr Das submitted that there was legal mala

fides in the non-consideration of the petitioner’s bid offer after

holding the petitioner as technically ineligible.

14. For all the above reasons, Mr Das submitted that this petition may

be allowed, the adjudging of the 6

th

respondent be set aside, and

the petitioner be allowed to participate in the reverse bidding

process as contemplated under the Bid Invitation.

15. Mr Indrajit Sinha, the learned counsel for the 1

st

respondent, at the

outset, submitted that the scope for interference in such matters is

extremely limited, as held by the Hon’ble Supreme Court in the

cases of Tata Cellular v. Union of India, (1994) 6 SCC 651;

Central Coalfields Ltd. v. SLL-SML, (2016) 8 SCC 622;

Michigan Rubber (India) Ltd. v. State of Karnataka, (2012) 8

SCC 216; and Afcons Infrastructure Ltd. v. Nagpur Metrol

Rail Corpn. Ltd., (2016) 16 SCC 818.

Neutral Citation No. 2026:JHHC:26463-DB

Page 7 of 26

16. Mr Sinha submitted that the eligibility criteria, which included

completion of similar works, were clearly set out in the Bid

Invitation. Further, the expression “similar nature of work” was

also clearly defined. He submitted that the competent committee,

comprising experts, fairly considered the petitioner's case and,

based on documents such as the experience certificates produced

by the petitioner, adjudged the petitioner technically ineligible for

not fulfilling the prescribed eligibility criteria. This was after

affording the petitioner a suitable opportunity to clarify the matter

and produce evidence. He submitted that this decision was most

reasonable and arrived at after adopting a transparent and fair

process.

17. Mr Sinha submitted that there were no allegations of mala fides or

favouritism. He submitted that mere use of such words in some

places of the petition cannot be construed as proper pleadings to

raise a serious plea of mala fides or extraneous consideration. In

the absence of such pleadings and such charge, Mr Sinha

submitted that this Court may not interfere with the decision of

experts arrived at in a fair and reasonable manner.

18. Mr Sinha submitted that the terms of the Bid Invitation required

the bidder to have completed similar works each costing a

particular amount. The expression “similar work” was further

clarified as follows: for each work order, the required experience

was in excavation/extraction/digging of slag metal from

running/operating slag pits of a steel melting shop and processing

Neutral Citation No. 2026:JHHC:26463-DB

Page 8 of 26

the same in an operating steel plant. From the replies and the

certificates produced by the petitioner herein, it was apparent that

the petitioner did not meet such eligibility criteria. He submitted

that if the petitioner really believed that it fulfilled the eligibility

criteria based upon a single work or single work order, there was

no necessity of the petitioner producing two independent work

orders to showcase its eligibility.

19. Mr Sinha submitted that the eligibility criteria in the bid invites

concerning other plants of the 1

st

respondent could not be said to

be identical or similar to the eligibility criteria prescribed in the

present Bid Invitation. He submitted that there is no question of

any discrimination involved.

20. Mr Sinha submitted that the petitioner, along with a supplementary

affidavit filed in these proceedings without even seeking a leave of

this Court, has purported to bring on record an additional

experience certificate or a clarification from Tata Steel Limited

with regard to the experience certificate already furnished. He

submitted that such a certificate does not advance the petitioner's

case. In any event, such certificates or explanations in

supplementary affidavits after this matter was partly argued

indicate that the experience certificates and other evidence on

record were by no means sufficient to indicate the petitioner's

satisfaction of the eligibility criteria.

21. Mr Sinha submitted that the decision as well as the decision-

making process in this case was fair and transparent. No case of

Neutral Citation No. 2026:JHHC:26463-DB

Page 9 of 26

any factual mala fides or extraneous considerations has been

pleaded or made out. Given the limited scope of interference in

such matters, Mr Sinha submitted that this petition ought to be

dismissed.

22. The rival contentions now fall for our determination.

23. The Bid Invitation in the present matter was for “Digging,

Evacuation of Slag/Scrap/Debris from //slag pits and various bays

of SMS, Transportation of slag, Muck, debris to material recovery

plant and segregation and processing of scrap to chargeable size

and transport to magnetic yard of SMS.”

24. The eligibility criteria for the bidders were set out in Annexure–VI

of the Bid Invitation. Since in this matter we are concerned with

the clauses dealing with “UNIFORM TECHNICAL ELIGIBILITY”

and “Similar Nature of Work”, the relevant extracts are transcribed

below for the convenience of reference:-

“B. UNIFORM TECHNICAL ELIGIBLITY.

Experience of having successfully completed or substantially

completed similar work by the bidder during last seven (07) years

ending last day of month previous to the one in which tender is

issued should be either of the following:

i) Three similar completed works each costing not less than the

amount equal to 40% of Reference Value: (Rs.

23,59,46,195.32)

OR

ii) Two similar completed works each costing not less than the

amount equal to 50% of the Reference Value: (Rs.

29,49,32,744.148)

OR

iii) One similar completed work costing not less than the amount

equal to 80% of the Reference Value. (Rs. 47,18,92,390.66)

Neutral Citation No. 2026:JHHC:26463-DB

Page 10 of 26

C. Similar Nature of Work.

“Experience of Excavation of Slag, Metal from hot slag pits &

Processing of the same in a operating integrated Steel Plant

having atleast 2.5 MT annual capacity, where processing means

separation of slag and metal and its sizing, screening,

extraction/excavation/ crushing/ separate etc.”

25. The above eligibility criteria were modified on 06.12.2025,

providing for the following:-

i) Three similar completed works each costing not less than the

amount equal to 30% of Reference Value; (Rs.

17,69,59,646.49)

OR

ii) Two similar completed works each costing not less than the

amount equal to 37.5% of the Reference Value; (Rs.

22,11,99,558.11)

OR

iii) One similar completed work costing not less than the amount

equal to 60% of the Reference Value. (Rs. 35,39,19,292.98)

26. The petitioner submitted its bid along with a work experience

certificate issued by Tata Steel. The certificate referred to the two

work orders issued in 2018 and 2021, thereby prima facie

indicating that they pertain to two separate works. The 1

st

Respondent’s case is that the petitioner was attempting to club the

work experience of these two works and pass it off as a single

work, only to somehow project a case of meeting the prescribed

eligibility criteria.

27. Therefore, by email dated 11.03.2026, the 1st respondent informed

the petitioner that it had been adjudged “Technically Not Eligible”

after evaluation. However, the petitioner’s bid offer was not

Neutral Citation No. 2026:JHHC:26463-DB

Page 11 of 26

immediately rejected; instead, the petitioner was given an

opportunity to clarify or submit additional documents online

within seven days of the email being issued.

28. Further, the petitioner was informed of the following technical

reasons for which the petitioner was adjudged as technically not

eligible: -

“Technical reasons:

1. Submitted Work Order do not comply with the similar

nature of work criteria as detailed in the BI. Submit

experience of excavation of Slag Pit and processing of Slag

in a single Work order with self attested.

2. You have not submitted document(s) in compliance with the

Para-D of the eligibility criteria as detailed in the BI.

Submit the same (Declaration of site visit not submitted)”

29. The petitioner responded to the above-referred email dated

11.03.2026 on 18.03.2026. The petitioner enclosed a completion

certificate from Tata Steel by citing the same as “composite in

nature”, wherein “the overall scope covers the entire scope of

work of excavation of slag pits and processing of slag etc.” It was

explained that, “The said work was operationally executed through

two different interlinked work orders, details of which are as

below:

1. Mechanised Feeding of Slag at MRP

Work Order No.: 3000139124/102

Value: ₹55,18,77,901.95 (Excl. GST)”

30. The Petitioner’s clarification dated 18.03.2026 proceeded to offer

the following justification: -

Neutral Citation No. 2026:JHHC:26463-DB

Page 12 of 26

“Justification:

Both the above work orders are part of a single integrated project

under the same department and collectively fulfill the requirement of

scope and clarification of your queries.

Hence, the submitted completion certificate substantiates compliance

with the similar nature of work criteria as specified in the bid.

Attachments:

 Self-attested certificate from Tata Steel confirming both work orders

are part of a single work.

 Self-attested Completion Certificate

 Copies of both duly signed Work Orders.”

31. The petitioner, by way of “response to”, further went on to explain

that it has submitted Work Order No. 3000139124 dated

01.08.2021 for “Mechanised Feeding of Slag at MRP” having a

value of Rs. 55,18,77,901.95 (Excl. GST). The petitioner explained

that the scope of this work includes excavation of slag from slag

pits and processing of slag in MRP, along with screening,

handling, and transportation, etc., through mechanised means,

which complies with the required criteria.

32. After considering the petitioner’s clarification dated 18.03.2026

and the documents provided along with it, the Evaluation

Committee of the 1

st

respondent apparently did not agree with the

petitioner's contention that it fulfilled the eligibility criteria based

on the documents originally submitted or additionally provided on

18.03.2026.

33. Therefore, by email dated 21.03.2026, the 1

st

respondent informed

the petitioner that it was adjudged technically not eligible for the

following technical reasons:-

Neutral Citation No. 2026:JHHC:26463-DB

Page 13 of 26

“Technical reasons:

1. Submitted Work Order do not comply with the similar

nature of work criteria as detailed in the BI. Experience

of excavation of Slag Pit and processing of Slag in a

single Work Order with self attestation not submitted.”

34. By the above-referred email dated 21.03.2026, the petitioner was

given once again further opportunity to clarify the position by

24.03.2026. The petitioner availed of this opportunity vide letter

dated 23.03.2026, maintaining that the experience certificate

submitted by the petitioner related only to one work which was

divided into two work orders, much above the values prescribed in

the Bid Invitation documents. The petitioner attempted to make a

distinction between “one similar completed work” and “one

similar work order” and tried to argue that upon a conjoint reading

of the two work orders and treating them to be a part of one

composite work, the petitioner fulfilled the technical eligibility

criteria as prescribed in the Bid Invitation.

35. Again, after considering the petitioner’s repeated assertions, the

Evaluation Committee concluded that the petitioner was

technically not eligible. This was informed to the petitioner vide

email dated 26

th

March 2026. The technical reason for holding the

petitioner as technically not eligible was stated as follows:-

“Technical reasons:

1. Submitted Work Order do not comply with the similar

nature of work criteria as detailed in the BI. Experience

of excavation of Slag Pit and processing of Slag in single

Work order not submitted.”

Neutral Citation No. 2026:JHHC:26463-DB

Page 14 of 26

36. Again, vide email dated 26.03.2026, the petitioner was given a

further opportunity to clarify the matter by 28.03.2026. There is no

record of the petitioner further clarifying the matter. Finally, on

31.03.2026, the 1

st

respondent rejected the petitioner’s bid on the

ground that the petitioner was found technically ineligible.

37. From the above chronology of events, at least the charge of lack of

transparency or of a fair decision-making process fails. The

petitioner was informed of the precise reasons the committee was

troubled by the petitioner’s technical eligibility claims and the

petitioner was granted no fewer than three opportunities to clarify

or explain the matter and even to produce additional documents.

The record shows that the petitioner availed of such opportunities.

38. The committee may not have ultimately agreed with the

petitioner’s clarifications or been satisfied with the additional

material produced. But merely because the evaluation committee,

after duly considering the matter and the additional material

produced, did not agree with the petitioner's clarifications or was

not satisfied with the additional material produced, we cannot hold

that there was any lack of transparency or fairness in the decision-

making process.

39. As held by the Hon’ble Supreme Court in Tata Cellular (supra),

the principles of judicial review apply to the exercise of

contractual powers by Government Bodies to prevent arbitrariness

or favouritism. The right to choose cannot be an arbitrary power

Neutral Citation No. 2026:JHHC:26463-DB

Page 15 of 26

unless such power is exercised for any collateral purpose or is

actuated by mala fides.

40. Further, the Hon’ble Supreme Court has held that judicial review is

primarily concerned with the decision-making process itself, not

the merits of the decision on which the application for judicial

review is based. It is different from an appeal. The court cannot

substitute its own decision. Apart from the fact that the court is

hardly equipped to do so, it would not be desirable either. Where

the selection or rejection is arbitrary, certainly the court would

interfere. However, it is not the function of a judge to act as a

superboard, or with the zeal of a pedantic schoolmaster

substituting its judgment for that of the administrator.

41. In Tata Cellular (supra), the Hon’ble Supreme Court explained

that the court’s duty is to confine itself to the question of

legality. Its concern should be: (i) Whether a decision-making

authority exceeded its powers? (ii)Committed an error of law, (iii)

committed a breach of the rules of natural justice, (iv) reached a

decision which no reasonable tribunal would have reached, or (v)

abused its powers.

42. The Hon’ble Supreme Court further explained that in such matters,

the scope of judicial review must broadly extend to determining

illegality, irrationality and procedural impropriety. Further, in all

such cases, the test to be adopted is that a court should, “consider

whether something has gone wrong of a nature and degree which

requires its intervention".

Neutral Citation No. 2026:JHHC:26463-DB

Page 16 of 26

43. The principles deducible in such matters are as follows:

(i) The modern trend points to judicial restraint in

administrative action.

(ii) The court does not sit as a court of appeal but merely

reviews the manner in which the decision was made.

(iii) The court does not have the expertise to correct the

administrative decision. If a review of the administrative

decision is permitted it will be substituting its own

decision, without the necessary expertise which itself may

be fallible.

(iv) The terms of the invitation to tender cannot be open to

judicial scrutiny because the invitation to tender is in the

realm of contract.

Normally speaking, the decision to accept the tender or

award the contract is reached by process of negotiations

through several tiers. More often than not, such decisions

are made qualitatively by experts.

(v) The Government must have freedom of contract. In other

words, a fair play in the joints is a necessary concomitant

for an administrative body functioning in an administrative

sphere or quasi-administrative sphere. However, the

decision must not only be tested by the application of

Wednesbury principle of reasonableness (including its

other facts pointed out above) but must be free from

arbitrariness not affected by bias or actuated by mala fides.

Neutral Citation No. 2026:JHHC:26463-DB

Page 17 of 26

(vi) Quashing decisions may impose heavy administrative

burden on the administration and lead to increased and

unbudgeted expenditure.

44. As noted earlier, several opportunities were granted to the

petitioner to clarify the issue of eligibility, and the clarifications,

along with the additional documents submitted by the petitioner,

were duly considered by the Evaluation Committee, thereby

defeating any charge of lack of transparency or fairness in the

decision-making process. The fact that the petitioner’s

clarifications or explanations may not have been accepted by the

decision makers is not a ground to conclude that there was any

unfairness or unreasonableness or arbitrariness involved in the

decision-making process leading to the decision of declaring the

petitioner as technically ineligible.

45. Even on the merits, given the limited scope of interference in

judicial review proceedings, it is difficult to hold that the impugned

decision is so wrong in nature and degree as to require the court’s

intervention, or that the impugned decision is such that no

responsible authority acting in a responsible manner and in

accordance with the relevant law could ever have reached it.

46. In the eligibility criteria, whether contained in the Original Bid

Invitation or the Modified Bid Invitation, there was consistent

reference to completion of works “each costing” not less than the

amounts specified for the similar completed works. The expression

“similar nature of work” was also adequately defined. The

Neutral Citation No. 2026:JHHC:26463-DB

Page 18 of 26

documents submitted by the petitioner in respect of the eligibility

criteria, at least prima facie, did not refer to any single work but

rather to the two works completed by the petitioner under two

distinct work orders dated 04.05.2018 and 01.08.2021.

47. The contention that this relates to a single work executed under

two work orders cannot be accepted at face value. Similarly, the

contention regarding the scope or perceived scope of the works,

and whether omitting the word “hot” from the modified eligibility

criteria resulted in any significant alteration to the scope of the

works or the prescribed eligibility criteria, is a question best

addressed by the Evaluation Committee rather than a court of law,

which has neither the expertise in such matters nor is it expected to

sit in appeal over the decisions of such Evaluators and Evaluation

Committees.

48. The record shows that each time the petitioner came out with some

different explanations and grounds in support of its claim of

eligibility. In the petition, an attempt is made to draw out a

distinction between “works” and “work orders”. No such serious

distinction appears to have been drawn in the numerous

explanations offered by the petitioner when given an opportunity

to do so. Instead, the attempt was to insist that the Tata Steel

Project’s experience related only to a single work which was to be

executed through two distinct and separate work orders issued on

04.05.2018 and 01.08.2021.

Neutral Citation No. 2026:JHHC:26463-DB

Page 19 of 26

49. By filing a supplementary affidavit before this Court after the

arguments were partly concluded, and without even seeking the

leave of this Court, a certificate dated 28.08.2026 was sought to be

placed on record. This certificate, issued post hoc, purports to

explain that the two work orders were running concurrently and

pertained to a single work order that was not provided at the

tendering stage.

50. The argument based on one of the two work orders produced by

the petitioner in support of the petitioner’s contention about

fulfilling the eligibility criteria also cannot be accepted. If the

petitioner was indeed confident of such an argument, we fail to

understand why the petitioner produced more than one work order

over a period of three years.

51. Post facto explanations furnished by the issuer of the experience

certificate also cannot be ordinarily considered. The fact that such

explanations were sought to be produced on record after the matter

was argued substantially and that too, without the leave of this

Court, suggests some attempt to pass off the two works as parts of,

or as the same work. The theory that the two work orders were

running concurrently, though belatedly introduced, does not

explain why the two work orders were issued in 2018 and 2021,

i.e. almost three years apart.

52. The certificate produced along with a supplementary affidavit also

refers to this position not being clarified at the tendering stage.

Given this situation, we can hardly fault the decision of the 1

st

Neutral Citation No. 2026:JHHC:26463-DB

Page 20 of 26

respondent or its Evaluation Committee in holding the petitioner

technically ineligible. In any event, as we have stated, the fact that

we might have a different opinion is hardly a ground to substitute

our opinion for that of the decision maker.

53. These post facto explanations and contradictory stands adopted by

the petitioner are sufficient to hold that no case is made out to

interfere with the decision of the Experts comprising the

Evaluation Committee in declaring the petitioner as technically

ineligible. The 1

st

respondent or its Evaluation Committee is

expected to reach a fair decision by following a fair process. This

Court is not expected to sit in appeal over such a decision, unless

any case of mala fide or extraneous consideration is properly

pleaded and established.

54. Thus, even if some allowance is made for the primarily semantic

argument of a single work and a single work order, the

committee’s conclusion that the petitioner was technically

ineligible, given the time gap between the two work orders and the

scope of the works, can hardly be condemned as perverse, illegal

or irrational warranting judicial review.

55. In Tata Cellular (supra), the Hon’ble Supreme Court explained

that, when exercising judicial review, the court is mainly

concerned with the lawfulness of the decision, not its soundness.

Normally, the decision to accept the tender or award the contract is

reached through a process of negotiations across several tiers.

More often than not, such decisions are made qualitatively by

Neutral Citation No. 2026:JHHC:26463-DB

Page 21 of 26

experts. The court does not have the expertise to correct the

administrative decision. If a review of the administrative decision

is permitted, it would substitute its own decision, without the

necessary expertise, which itself may be fallible.

56. In Michigan Rubber (supra), the Hon’ble Supreme Court

explained that the court's interference is not warranted unless the

tendering authority's action is mala fide and a misuse of statutory

powers. The court should not interfere merely because it feels

other terms in the tender would have been fairer, wiser, or more

logical. The main issue to be adjudicated in a tender matter is

whether the process adopted or the decision made is mala fide or

intended to favour someone, or whether the process adopted or the

decision made is so arbitrary and irrational that the court can say

that the decision is such that no responsible authority acting in a

responsible manner and in accordance with the relevant law could

have ever reached.

57. In Afcons Infrastructure Ltd (supra), the Hon’ble Supreme

Court held that even in interpreting tender conditions, interference

is permissible if the decision is arbitrary or irrational, or such that

no responsible authority acting reasonably and in accordance with

law could have reached it. Further, perversity of the decision-

making process or the decision, not merely a faulty or erroneous

decision, is a ground for interference by the courts. Constitutional

Courts are expected to exercise restraint in interfering with

Neutral Citation No. 2026:JHHC:26463-DB

Page 22 of 26

administrative decisions and ought not to substitute their view for

that of the administrative authority.

58. The Hon’ble Supreme Court held that a mere disagreement with

the decision-making process or the decision of the administrative

authority is no reason for a Constitutional Court to interfere.

Constitutional Courts must defer to the authority’s understanding

and appreciation of the tender documents, unless there is mala fide

intent or perversity in the understanding or appreciation, or in the

application of the terms of the tender conditions. A different

interpretation given by the authority, which is not acceptable to the

court, is no ground for a Constitutional Court to interfere with the

authority’s interpretation unless it is proved to be perverse or mala

fide or intended to favour a particular bidder.

59. By applying the above principles, we are satisfied that the

impugned decision in this matter cannot be said to be vitiated by

illegality, irrationality or procedural impropriety. The decision-

making process by which such decision was reached was fair and

transparent, consistent with the rules of natural justice. There are

neither any pleadings nor any materials to infer mala fides or abuse

of power.

60. This is not a case where the petitioner was not given any

opportunity to make good its claim about fulfilling the prescribed

eligibility criteria. The clarification and the materials furnished by

the petitioner were duly considered. The decision can certainly not

be styled as so outrageous in its defiance of logic or of accepted

Neutral Citation No. 2026:JHHC:26463-DB

Page 23 of 26

moral standards that no sensible person who had applied his mind

to the question to be decided could have arrived at. The decision is

also not such that no authority properly directing itself on the

relevant law and acting reasonably could have reached it.

61. The decision in Kimberley Club Pvt. Ltd. (supra) cited by Mr

Das holds that the terms of an NIT must be clear and

unambiguous. It also reiterates that the court exercising judicial

review does not sit in appeal over the tendering authority's decision

to disqualify a bidder. Only in cases where such decision is de hors

the terms of the NIT or is patently arbitrary, would the court

exercise power of judicial review and set aside such a decision.

62. In the present case, there was no complaint that the terms of the

Bid Invitation were unclear or ambiguous. The decision reached by

the 1

st

respondent or its Evaluation Committee cannot be said to be

de hors the terms of the NIT or patently arbitrary. At the highest,

this is a case of interpretation of the terms of the bid invite and

determining whether, based on the material originally and

additionally produced, the petitioner could be regarded as

technically eligible. Once a decision is reached in a fair and

transparent manner and such decision is not perverse [ as opposed

to it being merely erroneous] or irrational, the scope to interfere in

the exercise of judicial review is indeed limited.

63. As held in Afcons Infrastructure (supra), the Constitutional

Courts must also defer to the tendering authorities' understanding

and appreciation of the tender documents, or to their interpretation

Neutral Citation No. 2026:JHHC:26463-DB

Page 24 of 26

of the terms, unless there is mala fides or perversity in the

understanding or appreciation, or in the application, of the terms of

the tender conditions. Even if the authority's interpretation may not

be acceptable to the courts, the Constitutional Courts must not

interfere with it unless it is established that it is perverse, mala

fide, or intended to favour a particular bidder.

64. The argument about discrimination also cannot be accepted in the

light of the facts and circumstances of the present case. It is

difficult, at least on a prima facie basis, to hold that the eligibility

conditions in the Bid Invitations for three other plants of the 1

st

respondent were the same as the eligibility criteria prescribed for

the present Bid Invitation. Secondly, it is difficult to accept that the

scope of the works and all the plants were identical and similar, as

was argued on behalf of the petitioner.

65. In any event, the petitioner cannot expect the Court to scrutinise

and interpret the terms and conditions and the experience

certificates of other bid invitations, comparing them with the

present bid invitation with a fine-toothed comb. A prima facie

examination is all that is warranted, particularly after the decision-

makers have evaluated the matters thoroughly and no case of mala

fides or favouritism has been pleaded or established.

66. Ultimately, these are matters which have been considered by the

Evaluation Committee of the 1

st

respondent, and unless it is

established that there was any infirmity in the decision-making

process or that the decision was perverse as opposed to merely

Neutral Citation No. 2026:JHHC:26463-DB

Page 25 of 26

erroneous, there is no scope to interfere. In fact, in such matters,

this Court is prohibited from acting as a superboard or with the

zeal of a pedantic schoolmaster, substituting its judgment for that

of the administrator.

67. In Banshidhar Construction (supra), the Hon’ble Supreme Court

held that Constitutional Courts, when exercising judicial review,

cannot examine the details of the terms of the contract entered by

the public body or the State. Courts have inherent limitations on

the scope of any such enquiry. At the same time, the courts can

examine whether the decision-making process was reasonable,

rational, or arbitrary, and violative of Article 14 of the

Constitution.

68. In this case, the petitioner invites us to examine the terms of the

Bid Invitation documents and to adopt the petitioner's

interpretation, in preference to the interpretation adopted by the 1

st

respondent and its Tender Evaluation Committee. Such an

invitation, if accepted, would run counter to the law laid down in

Afcons Infrastructure Limited (supra). That case holds that the

constitutional Courts must defer to the authority's interpretation of

the terms and conditions in the NIT.

69. For all the above reasons, we are satisfied that the impugned

decision is not perverse and is not actuated by any mala fide,

discrimination or undue favouritism. No case is made out for

interference with the impugned decision, having regard to the

limited scope of judicial review in such matters.

Neutral Citation No. 2026:JHHC:26463-DB

Page 26 of 26

70. The petition is, thus, liable to be dismissed and is hereby

dismissed, without any order for costs. IAs, if any, pending in this

petition will not survive and are disposed of.

(M. S. Sonak, C.J.)

(Rajesh Shankar, J.)

September 02, 2026

A.F.R.

Manoj/Cp.2

Uploaded on 02.09.2026

Reference cases

Description

Jharkhand High Court Upholds Tender Rejection: A Deep Dive into Judicial Restraint

The Jharkhand High Court's recent decision in W.P. (C) No. 4210 of 2026 provides crucial clarity on the judicial review of technical eligibility criteria for tenders. This significant ruling, along with many other pivotal judgments, is meticulously cataloged and available for in-depth analysis on CaseOn.in, offering legal professionals and students comprehensive access to the latest legal developments.

The Core Issue

At the heart of this case was the petitioner's challenge against the rejection of their bid by Steel Authority of India Limited (SAIL) on the grounds of technical ineligibility. The core legal question revolved around whether the respondent's decision to disqualify the petitioner, particularly concerning the interpretation of "similar work" and "single work order" in the tender document, was arbitrary, unreasonable, or mala fide, thereby warranting judicial intervention.

Legal Principles and Rules

The High Court reiterated the well-established legal principles governing judicial review in contractual matters, primarily drawing from several landmark Supreme Court judgments. Key among these are:

  • Tata Cellular v. Union of India (1994)

    Emphasizing judicial restraint, this case established that courts review the decision-making process, not the merits of the decision itself. Intervention is warranted only for arbitrariness, favouritism, illegality, irrationality, procedural impropriety, or abuse of power. The court is not a "superboard" to substitute its judgment for that of the administrator.

  • Central Coalfields Ltd. v. SLL-SML (2016)

    Reinforced the limited scope of judicial review, stressing that courts should not interfere merely because a different tender term might seem fairer.

  • Michigan Rubber (India) Ltd. v. State of Karnataka (2012)

    Held that court interference is justified only when the tendering authority acts mala fide or misuses statutory powers, or if the decision is so arbitrary and irrational that no responsible authority could have reached it.

  • Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd. (2016)

    Affirmed that even in interpreting tender conditions, courts defer to the authority's understanding unless it's perverse, mala fide, or intended to favor a specific bidder. It distinguishes between a faulty/erroneous decision and a perverse one.

  • Banshidhar Construction Private Limited v. Bharat Coking Coal Limited (2024)

    Underlined that Constitutional Courts cannot delve into the minute details of contract terms but must ensure the decision-making process is reasonable, rational, and not arbitrary or violative of Article 14 of the Constitution.

Analyzing the Dispute

Background of the Tender

The bid invitation, issued by SAIL (Respondent No. 1) for its Bokaro Steel Plant, was for "Comprehensive Outsourcing Services – MRD," involving the excavation, transportation, and processing of slag/scrap/debris. The eligibility criteria stipulated specific experience requirements for "similar works" based on their cost. These criteria were later modified, including changes to reference values.

Petitioner's Technical Ineligibility

The petitioner, M/s United Air Express, submitted its bid along with a work experience certificate from Tata Steel, referencing two separate work orders from 2018 and 2021. SAIL's Evaluation Committee deemed the petitioner technically ineligible, stating that the submitted work orders did not comply with the "similar nature of work" criteria requiring experience in "excavation of Slag Pit and processing of Slag in a single Work order with self attested." The petitioner was given multiple opportunities (three, in fact) to clarify and provide additional documentation.

Petitioner's Arguments

Mr. A.K. Das, senior advocate for the petitioner, contended that:

  • The bid invitation did not explicitly require experience in a single work order, and the petitioner's experience spanned two work orders that were part of a single integrated project for Tata Steel, fulfilling the value requirement.
  • The rejection was arbitrary and unreasonable, failing to consider the comprehensive experience.
  • SAIL had previously adjudged the petitioner technically eligible for similar tenders at its Burnpur and Durgapur plants based on similar experience certificates, implying discrimination in the current instance, a violation of Article 14.
  • The modification of the eligibility criteria on 06.12.2025 by removing the word "hot" from "hot slag pits" indicated that the scope of work was for cooled slag, aligning with the petitioner's experience. He alleged mala fides in the non-consideration.

Respondent's Counterarguments

Mr. Indrajit Sinha, representing SAIL, argued that:

  • The scope for judicial interference in such expert-driven tender matters is extremely limited.
  • The Evaluation Committee, comprising experts, fairly assessed the petitioner's case, providing ample opportunity for clarification. The decision was transparent and reasonable, without any mala fides or favouritism.
  • The eligibility criteria clearly referred to "each costing" (implying individual work orders meeting specific thresholds) and "single work order" for the required experience. The petitioner's attempt to club two distinct work orders, issued years apart, was an effort to circumvent the criteria.
  • The eligibility criteria for other plants were not identical or similar, thus ruling out discrimination.
  • The post hoc clarifications and supplementary affidavit filed by the petitioner in court, without leave, further indicated their inability to meet the criteria at the tendering stage.

The Court's Deliberation

The High Court meticulously reviewed the sequence of events and the arguments. It noted that the petitioner was indeed given multiple chances to explain their eligibility. The court emphasized that its role is not to substitute its judgment for that of the expert committee or to sit in appeal over their decision.

Addressing the 'single work order' versus 'single integrated project' argument, the court found the petitioner's explanations inconsistent and belated. The post hoc certificate, introduced without court leave after arguments had commenced, was also viewed skeptically, especially given the significant time gap (three years) between the two work orders. The court stated that the evaluation committee's conclusion, considering the time gap and scope, could not be deemed perverse, illegal, or irrational.

Regarding the discrimination claim, the court found it difficult to accept prima facie that the eligibility conditions and scope of work for other plants were identical to the present bid. The court stressed it could not scrutinize and interpret every detail of multiple tender documents with a "fine-toothed comb."

For legal professionals seeking rapid comprehension, CaseOn.in offers concise 2-minute audio briefs that distill the essence of rulings like these, providing crucial insights into the court's reasoning and the application of tender law principles. These briefs are invaluable for busy practitioners needing quick, accurate summaries.

Ultimately, the court found no evidence of mala fides, arbitrariness, or procedural impropriety. The decision-making process was fair and transparent, even if the petitioner disagreed with the outcome. The court reiterated that a mere disagreement with an administrative decision or its interpretation is not grounds for intervention unless it is perverse or intended to favor a particular bidder.

The Court's Ruling

Based on its analysis, the Jharkhand High Court concluded that the impugned decision of SAIL to declare the petitioner technically ineligible was neither perverse nor actuated by mala fides, discrimination, or undue favouritism. The court found no compelling reason to interfere with the expert committee's decision, especially given the limited scope of judicial review in such contractual matters.

Consequently, the petition was dismissed, upholding SAIL's rejection of the petitioner's bid.

Why This Judgment is Essential Reading for Lawyers and Students

This judgment serves as a powerful reminder of the principles of judicial restraint in reviewing tender processes. For lawyers advising clients on public procurement, it underscores:

  • The primacy of tender conditions: Strict adherence to the letter and spirit of eligibility criteria is paramount.
  • Limited scope of judicial review: Courts generally defer to the expertise of evaluation committees unless there's clear evidence of arbitrariness, mala fides, or irrationality.
  • Importance of clear documentation: Bidders must ensure their experience is clearly and unambiguously presented in compliance with bid requirements, avoiding post hoc explanations or attempts to combine disparate works.
  • No substitution of judgment: The court will not replace the administrator's decision with its own, even if a different interpretation seems plausible.

For law students, it's an excellent case study on the application of administrative law principles, particularly the Wednesbury unreasonableness test and the constraints of judicial oversight in contractual disputes involving state instrumentalities.

Disclaimer

All information provided in this article is for general informational purposes only and does not constitute legal advice. While efforts have been made to ensure accuracy, readers should not rely solely on this content for making legal decisions. Consultation with a qualified legal professional is strongly recommended for specific legal concerns.

Legal Notes

Add a Note....

Advance Search Tool

💡 How to Get the Best Legal Answers:

1. Keep it simple: Frame your question in plain language.

2. Add scope: Tag @ a court, judge, year, or act section for accurate results.

3. Attach files: Upload a PDF only if you are using a private document.

🌍 Ask in your language: English • Hindi • Assamese • Bangla • Gujarati • Kannada • Malayalam • Marathi • Odia • Punjabi • Tamil • Telugu • Urdu


💡 New Advocate? Don’t worry! Working without senior support today? Turn on Client Advisory to get instant legal strategies, practical angles, and precedent-backed options for your client.

Add research context Type to filter