As per case facts, the Petitioner, a real estate developer, entered into a Lease Deed with the Respondent, a hotel operator, for a commercial complex. The Petitioner paid an advance ...
ARB.P. 1678/2025 Page 1 of 18
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Reserved on: 20
th
January, 2026
Pronounced on: 29
th
January, 2026
+ ARB.P. 1678/2025
OMAXE NEW CHANDIGARH DEVELOPERS PRIVATE
LIMITED .....Petitioner
Through: Mr. Karanjot Singh Mainee, Mr. Sahil
Chopra, Ms. Manya Kaushik,
Advocates
(M:9717413994)
versus
ATHARVA HOTEL SUPERFLUITIES INDIA PVT .
LTD. .....Respondent
Through: Mr. Vishal Bhatnagar and Mr. Veer
Pratap Singh, Advocates
(M:9313674756)
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
JUDGMENT
MINI PUSHKARNA, J.
1. The present petition has been filed on behalf of the petitioner under
Section 11(6) of the Arbitration and Conciliation Act, 1996 (“Arbitration
Act”) seeking appointment of a Sole Arbitrator in terms of the arbitration
clause, i.e., Clause 15 (b) of the Lease Deed dated 15
th
November, 2022
(“Lease Deed”), which provides for adjudication of disputes between the
parties by arbitration.
2. Facts of the case, as canvassed in the petition, are as follows:
2.1 The petitioner is a private limited company engaged in the business of
real estate development, including, construction of integrated townships,
ARB.P. 1678/2025 Page 2 of 18
residential apartments, commercial spaces, hotels and related infrastructure
across India.
2.2 The respondent is a private company engaged in the business of
operating and managing hotels in association with third party brands in the
hospital sector.
2.3 The petitioner is in the process of constructing and developing a
commercial complex in the name and style of „Beacon Street‟, on
approximately seven acres of land situated at Village Bharonjian, Tehsil-
Kharar, S.A.S. Nagar, Mohali-160055, Punjab (“Project”). For the purposes
of the said Project, the respondent approached the petitioner, seeking lease
of approximately, 1,75,000 sq. ft. of super area being Unit no. S. Suite
Floors Nos. 19
th
to 28
th
of the Project (“Demised Portion”), to operate and
manage the said area as a branded hotel.
2.4 In view of the above, the parties entered into a Lease Deed dated 15
th
November, 2022, by way of which, the Demised Portion was leased to the
respondent, and the respondent was to enter into another agreement with a
reputed hotel for operation of the same in the Demised Portion of the
Project.
2.5 As per Clause 4.1 and Annexure-II of the Lease Deed, the respondent
was to provide technical and pre-opening services, and towards the same,
the petitioner had agreed to pay a onetime lump sum amount of Rs.
3,30,00,000/- to the respondent, towards applicable sign-up fees, including,
brand association fees and for the technical and pre-opening services.
2.6 Consequently, as per Clause 8 (I)(a) of the Lease Deed, the petitioner
paid to the respondent a sum of Rs. 1,65,00,000/- along with applicable
ARB.P. 1678/2025 Page 3 of 18
Goods and Service Tax (“GST”) of Rs. 29,70,000/-, totalling to Rs.
1,94,70,000/-, as an advance payment.
2.7 Due to the non-performance of obligations by the respondent, the
petitioner sought for refund of the advance amount, i.e., Rs. 1,94,70,000/-,
paid to the respondent, towards which only Rs. 50,00,000/-, was refunded
and an amount of Rs. 1,44,70,000/- remained to be refunded by the
respondent.
2.8 Due to the continuous breach of the Lease Deed and on account of
non-payment of pending advance amount, the petitioner issued a notice
dated 22
nd
August, 2025 and sought for refund of the remaining advance
amount along with damages. Since, the said amounts were not paid to the
petitioner, the petitioner was constrained to invoke arbitration under Section
21 of the Arbitration Act.
2.9 The respondent has not replied to the notice dated 22
nd
August, 2025.
Admittedly there exists a clear dispute between the parties, therefore, as per
the valid arbitration clause, i.e., Clause 15 of the Lease Deed, and there
being no alternative remedy, the petitioner has filed the present petition.
3. The present petition has been opposed by the respondent on the
ground that the notice invoking arbitration and the present petition are
premature, as the petitioner has not followed the procedure prescribed for
appointment of an Arbitrator in consonance with Clause 15 of the Lease
Deed, which requires the parties to attempt to first settle the disputes by way
of negotiation and conciliation. Therefore, as per the respondent, the
unilateral waiving of the dispute resolution mechanisms prior to arbitration
is barred, as per the terms of the Lease Deed. The respondent has relied
ARB.P. 1678/2025 Page 4 of 18
upon the judgement dated 18
th
January, 2023, passed by this Court in
ARB.P. 782/2022, titled as M/s Chabbras Associates Versus M/s HSCC
India Limited & Anr., in support of their submissions.
4. Another objection raised by the respondent is that the agreement was
not terminated in consonance with the terms of the Lease Deed, and there is
no material breach of the agreement by the respondent which has been
demonstrated by the petitioner. Further, as per the terms of the Lease Deed,
the agreement has a lock-in period of 20 years, and only when a material
breach is shown and a written notice or any communication through letter or
mail is received from the petitioner, can the agreement be terminated,
however, the said conditions are not satisfied.
5. As per the respondent, the present petition has been filed only as the
respondent availed its statutory remedies under Section 9 of the Arbitration
Act by filing a petition, i.e., OMP (I)(COMM) 196/2025, with respect to
another project, i.e., Omaxe, Hazratganj, Lucknow, 540-key Hotel Project,
wherein, the sister concern of the petitioner has committed material
breaches.
6. The refund of Rs. 50,00,000/- paid to the petitioner by the respondent
is portrayed in a false, misleading and mala fide manner by the petitioner.
Further, as per the respondent, the present dispute is not arbitrable.
7. I have heard learned counsel for the parties and perused the record.
8. At the outset, this Court notes that the scope of Courts under Section
11(6) of the Arbitration Act has been well defined, and restricted to the
purposes of reference of disputes to arbitration and an examination of the
existence of an arbitration agreement. In this regard, the Supreme Court in
ARB.P. 1678/2025 Page 5 of 18
the case of Managing Director Bihar State Food and Civil Supply
Corporation Ltd. and Another Versus Sanjay Kumar, 2025 SCC OnLine
SC 1604, held as follows:
“xxx xxx xxx
23. Section 11 of the Act has perhaps been the only provision which
would have been interpreted and re-interpreted by the Supreme Court
for the longest time ever. After two decades of its interpretation
commencing from 1996, Parliament intervened and supplied sub-
section (6A) to Section 11 of the Act as per which the consideration
by a referral court shall be confine(d) to the examination of the
existence of an arbitration agreement.
xxx xxx xxx
27. The curtains have fallen. Courts exercising jurisdictions under
Section 11(6) and Section 8 must follow the mandate of sub-section
(6A), as interpreted and mandated by the decisions of this Court and
their scrutiny must be “confine(d) to the examination of the
existence of the arbitration agreement”.
28. We have examined the matter in detail. There is an arbitration
agreement. The matter must end here. While we agree with Mr.
Ranjit Kumar submissions that his client has much to say, let all
that be said before the arbitral tribunal. It is, as we have said
elsewhere, just as necessary to follow a precedent as it is to make
one.
xxx xxx xxx”
(Emphasis Supplied)
9. Further, it is settled law that the extent of inquiry under Section 11(6)
of the Arbitration Act is limited, and the Courts cannot exceed its scope by
undertaking a detailed examination of the factual matrix. Thus, the Supreme
Court in the case of Goqii Technologies Private Limited Versus Sokrati
Technologies Private Limited, (2025) 2 SCC 192, held as follows:
“xxx xxx xxx
19. The scope of inquiry under Section 11 of the 1996 Act is limited
to ascertaining the prima facie existence of an arbitration
agreement. In the present case, the High Court exceeded this limited
scope by undertaking a detailed examination of the factual matrix.
ARB.P. 1678/2025 Page 6 of 18
The High Court erroneously proceeded to assess the auditor's report
in detail and dismissed [Goqii Technologies (P) Ltd. v. Sokrati
Technologies (P) Ltd., 2024 SCC OnLine Bom 3530] the arbitration
application. In our view, such an approach does not give effect to the
legislative intent behind the 2015 Amendment to the 1996 Act which
limited the judicial scrutiny at the stage of Section 11 solely to the
prima facie determination of the existence of an arbitration
agreement.
20. As observed in Krish Spg. [SBI General Insurance Co.
Ltd. v. Krish Spg., (2024) 12 SCC 1: 2024 SCC OnLine SC 1754:
2024 INSC 532], frivolity in litigation too is an aspect which the
referral court should not decide at the stage of Section 11 as the
arbitrator is equally, if not more, competent to adjudicate the same.
xxx xxx xxx”
(Emphasis Supplied)
10. Thus, for the purposes of the present petition under Section 11(6) of
the Arbitration Act, this Court is only required to form a prima facie view,
as to existence of an arbitration clause/agreement between the parties. All
disputes between the parties, including, any objections by the respondent,
are to be adjudicated in the arbitral proceedings.
11. In the present case, the parties have entered into a Lease Deed dated
15
th
November, 2022, in which the parties sought to pursue the dispute
resolution mechanism envisaged under Clause 15 of the said Lease Deed,
which contains an Arbitration Clause, which is set out in the following
manner:
“xxx xxx xxx
15. DISPUTE RESOLUTION
a. Amicable Resolution
Any and All disputes or differences arising out of or in connection
with this Lease Deed or its performance, including its existence,
validity, scope, meaning, construction, interpretation or application
hereof, (a dispute) shall at the first instance, to the extent possible,
be settled amicably by negotiation and discussion between the
Parties, it being understood that the Parties may agree to appoint
any representative(s) or Expert(s) they consider useful to settle the
ARB.P. 1678/2025 Page 7 of 18
dispute.
b. Arbitration
i. Any dispute not amicably settled within thirty (30) days of the
Dispute submitted by a party, or such a longer period as may be
agreed by the Parties during the period of negotiation and
conciliation, shall be referred to arbitration in accordance with
the Arbitration and Conciliation Act, 1996 or any amendment or
re-enactment thereof by either party.
ii. All proceedings of such arbitration shall be in the English
language and the seat, place and venue of arbitration shall be New
Delhi/Lucknow. The arbitration proceeding pursuant to this clause
shall be strictly confidential.
iii. The arbitral panel shall consist of a sole arbitrator to be mutually
appointed by the parties within 30 days from the date either party
calling upon the other to appoint an arbitrator in terms of this
agreement.
iv. In an event there is no concurrence, arbitrator to be appointed by
the Competent Court. The Appointment of arbitrator and the
arbitration shall be conducted in accordance with the provisions of
the Arbitration and Conciliation Act, 1996 along with the Rules
thereunder and any amendments thereto. The decision/award of the
arbitrator shall be final/conclusive and binding on the parties.
v. The costs of the arbitration shall be borne by the Parties in such
manner as the arbitrator shall direct in their arbitral award.
vi. When any dispute is under arbitration, except for the matters under
dispute, the Parties shall continue to exercise their remaining
respective rights and fulfil their remaining respective obligations
under this Lease Deed.
xxx xxx xxx”
(Emphasis Supplied)
12. Thus, the aforesaid clause envisages dispute resolution in the first
instance through amicable settlement by way of negotiation and discussion
between the parties. The Clause further envisages that in case the dispute is
not amicably settled within 30 days, or such a longer period as may be
agreed between the parties during the course of negotiation and conciliation,
the same shall be referred to arbitration.
13. The respondent has raised an objection that the present petition is
ARB.P. 1678/2025 Page 8 of 18
premature, as the process of amicable resolution as per the terms of the
Lease Deed has not been exhausted by the petitioner. However, the said
contention is found to be totally untenable. It is to be noted that there were
various correspondences between the parties over a period of time, from the
date of the Lease Deed, wherein, the petitioner has flagged issues to the
respondent with respect to the Project and its commencement thereof. Thus,
it is apparent that the parties have attempted to resolve the issues in the
present matter, and due to failure of the same, the Lease Deed has been
terminated by way of the Notice dated 22
nd
August, 2025 sent by the
petitioner to the respondent, wherein, the petitioner had listed all issues and
correspondences between the parties.
14. Moreover, the parties admittedly have other pending disputes between
them with regard to similar arrangement in another agreement between the
respondent and sister concern of the petitioner for a project in Lucknow.
Vide order dated 26
th
May, 2025 in O.M.P.(I)(COMM.) 196/2025, the
respondent had categorically stated before the Court in the petition filed by
the respondent itself, that they were ready and willing to have the disputes
between the parties referred to arbitration. The said order recording the
willingness of the respondent as petitioner in the said petition, for reference
of similar disputes with sister concern of the petitioner herein to an
Arbitrator, reads as under:
“1. Upon steps being taken by the Petitioner, issue notice to the
Respondent through all modes. Reply be filed within two (2) weeks from
receipt of notice.
2. Learned counsel for the Petitioner states that the Petitioner remains
ready and willing to have the disputes referred to arbitration.
3. The Petitioner is directed to take instructions with respect to the
ARB.P. 1678/2025 Page 9 of 18
appointment of the Arbitral Tribunal, before the next date of hearing.
4. List on 29.07.2025.”
(Emphasis Supplied)
15. With regard to the aforesaid Lucknow Project with the sister concern
of the petitioner, the sister concern of the petitioner had filed a petition for
appointment of an Arbitrator, being ARB.P.1340/2025. The respondent
herein, who was also a respondent in the said petition, indicated its no
objection to appointment of an Arbitrator for adjudication of disputes
between the parties. Accordingly, a Sole Arbitrator under Section 11(6) of
the Arbitration Act was appointed by this Court vide order dated 03
rd
November, 2025 in ARB.P.1340/2025. Relevant portion of the said order
recording the consent of the respondent herein for appointment of an
Arbitrator with respect to disputes with the sister concern of the petitioner
for a similar project, reads as under:
“xxx xxx xxx
7. Counsel appears on behalf of the respondent and submits that he has
no objection if a Sole Arbitrator is appointed by this Court.
xxx xxx xxx”
(Emphasis Supplied)
16. Furthermore, this Court notes the submission made by learned counsel
for the petitioner that if conciliation/settlement has to happen, it will have to
be a comprehensive exercise, in relation to all the projects between the
parties, including, the sister concern.
17. Therefore, in view of the facts and circumstances of the present case
and the submissions made before this Court, and considering the fact that
similar dispute with the sister concern of the petitioner is already pending
adjudication before an Arbitrator, this Court finds no justification in
ARB.P. 1678/2025 Page 10 of 18
directing the parties to first undergo negotiation/conciliation proceedings, as
the same would be a futile exercise.
18. In similar circumstances, considering the elaborate correspondence
between the parties involved therein, the Supreme Court was of the view
that any attempt to resolve the disputes at that stage between the parties by
mutual discussions and Mediation would be an empty formality. Thus,
overruling the objection with regard to appointment of an Arbitrator being
premature, Supreme Court in the case of Demerara Distilleries Private
Limited and Another Versus Demerara Distillers Limited, (2015) 13 SCC
610, held as follows:
“xxx xxx xxx
5. Of the various contentions advanced by the respondent Company to
resist the prayer for appointment of an arbitrator under Section 11(6) of
the Act, the objections with regard the application being premature; the
disputes not being arbitrable, and the proceedings pending before the
Company Law Board, would not merit any serious consideration. The
elaborate correspondence by and between the parties, as brought on
record of the present proceeding, would indicate that any attempt, at this
stage, to resolve the disputes by mutual discussions and mediation would
be an empty formality. The proceedings before the Company Law Board
at the instance of the present respondent and the prayer of the petitioners
therein for reference to arbitration cannot logically and reasonably be
construed to be a bar to the entertainment of the present application.
Admittedly, a dispute has occurred with regard to the commitments of the
respondent Company as regards equity participation and dissemination of
technology as visualised under the Agreement. It would, therefore, be
difficult to hold that the same would not be arbitrable, if otherwise, the
arbitration clause can be legitimately invoked. Therefore, it is the
objection of the respondent Company that the present petition is not
maintainable at the instance of the petitioners which alone would require
an in-depth consideration.
xxx xxx xxx”
(Emphasis Supplied)
19. Likewise, in the case of Visa International Limited Versus
Continental Resources (USA) Limited, (2009) 2 SCC 55, Supreme Court
ARB.P. 1678/2025 Page 11 of 18
held as follows:
“xxx xxx xxx
Whether invocation of Article VI providing for arbitration is premature?
38. It was contended that the pre-condition for amicable settlement of
the dispute between the parties has not been exhausted and therefore the
application seeking appointment of arbitrator is premature. From the
correspondence exchanged between the parties at pp. 54-77 of the paper
book, it is clear that there was no scope for amicable settlement, for both
the parties have taken rigid stand making allegations against each other.
In this regard a reference may be made to the letter dated 15-9-2006
from the respondent herein in which it is inter alia stated “… since
February 2005 after the execution of the agreements, various
meetings/discussions have taken place between both the parties for
furtherance of the objective and purpose with which the agreement and
the MoU were signed between the parties. Several correspondences have
been made by CRL to VISA to help and support its endeavour for
achieving the goal for which the abovementioned agreements were
executed”. In the same letter it is alleged that in spite of repeated
requests the petitioner has not provided any funding schedules for their
portion of equity along with supporting documents to help in convincing
OMC of financial capabilities of the parties and ultimately to obtain
financial closure of the project. The exchange of letters between the
parties undoubtedly discloses that attempts were made for an amicable
settlement but without any result leaving no option but to invoke the
arbitration clause.
xxx xxx xxx”
(Emphasis Supplied)
20. In this regard, reference is also made to the case of Jhajharia Nirman
Ltd. Versus South Western Railways through Dy. Chief Engineer/IV
Construction & Connected matter, 2024 SCC OnLine Del 7133, wherein, it
was held as follows:
“xxx xxx xxx
18. In numerous judicial precedents, this Court has taken the view
that any pre-condition in an arbitration agreement obliging one of
the contracting parties to either exhaust the pre-arbitral amicable
resolution avenues or to take recourse to Conciliation are directory
and not mandatory.
19. In this regard, reference may be made to Oasis Projects
ARB.P. 1678/2025 Page 12 of 18
Ltd. v. National Highway & Infrastructure Development Corporation
Limited, (2023) 1 HCC (Del) 525, wherein the Court has observed as
under:
“12. The primary issue to be decided in the present
petition is, therefore, as to whether it was mandatory for the
petitioner to resort to the conciliation process by the Committee
before invoking arbitration. Though Article 26.2 clearly states
that before resorting to arbitration, the parties agree to explore
conciliation by the Committee, in my opinion, the same cannot be
held to be mandatory in nature. It needs no emphasis that
conciliation as a dispute resolution mechanism must be encouraged
and should be one of the first endeavours of the parties when a
dispute arises between them. However, having said that,
conciliation expresses a broad notion of a voluntary process,
controlled by the parties and conducted with the assistance of a
neutral third person or persons. It can be terminated by the parties
at any time as per their free will. Therefore, while interpreting
Article 26.2, the basic concept of conciliation would have to be
kept in mind.”
[Emphasis supplied]
xxx xxx xxx
21. This Court in Subhash Infraengineers (P) Ltd. v. NTPC Ltd., 2023
SCC OnLine Del 2177 has held as under:—
“21. In this regard, it is relevant to note that in terms of
Section 62(3) of the Act, it is open for a party to reject the
invitation to conciliate. Further, in terms of Section 76 of the Act,
the conciliation proceedings can be terminated by a written
declaration of a party and there is no legal bar in this regard. In
the present case, Clause 7.2.5 of the GCC expressly provides that
“parties are free to terminate Conciliation proceedings at any
stage as provided under the Arbitration and Conciliation Act,
1996.”
***
28. In the present case, the clause/pre arbitral mechanism
contemplates mutual consultation followed by conciliation. As
noticed in Abhi Engg. and Oasis Projects, conciliation is a
voluntary process and once a party has opted out of conciliation,
it cannot be said that the said party cannot take recourse to
dispute resolution through arbitration.”
xxx xxx xxx”
(Emphasis Supplied)
ARB.P. 1678/2025 Page 13 of 18
21. Reference is also made to the case of Coach Com Through its Sole
Proprietor Smt. Lalita Devi Sureka Versus DME, Northern Railway, 2025
SCC OnLine Del 8055, wherein, the Court has held that exhaustion of pre-
arbitral mechanisms, and its recourse is only directory and not mandatory in
nature. Thus, it was held as follows:
“xxx xxx xxx
9. In Jhajharia Nirman v. South Western Railways, 2024 SCC OnLine
Del 7133, a Coordinate Bench of this Court, dealing with a
similar arbitration clause in a Railway Contract, has observed that
any pre-condition in an arbitration agreement binding one of the
contracting parties to either exhaust the pre-arbitral amicable
resolution procedures or to take recourse to conciliation are
directory, and not mandatory in nature.
10. In view of the facts noted above, in my view, the reference of the
dispute between the parties to the conciliation and thereafter DAB
would be an exercise of futility.
11. In the aforesaid facts and circumstances, this Court is of the
view that the present petition is not premature and a Sole Arbitrator
is required to be appointed to adjudicate the disputes between the
parties.
xxx xxx xxx”
(Emphasis Supplied)
22. The judgment in the case of M/s Chabbras Associates Versus M/s
HSCC India Limited (Supra), as relied upon by the respondent, is clearly
distinguishable and not applicable to the facts and circumstances of the
present case. The said case dealt with a specific procedure for reference of
the disputes to specified authorities as per the contract in the said case.
However, in the present case, the Clause pertaining to dispute resolution
does not specify reference of disputes to any specified authorities, and only
makes reference to amicable settlement by negotiation and discussion
ARB.P. 1678/2025 Page 14 of 18
between the parties, which aspect has already been dealt by this Court in the
preceding paragraphs.
23. Significantly, the same Bench in a subsequent case titled as Oasis
Projects Limited Versus Managing Director, National Highway and
Infrastructure Development Corporation Limited, 2023 SCC OnLine Del
645, has taken the view that conciliation proceedings are a voluntary process
which are not mandatory in nature. Thus, it was held as follows:
“xxx xxx xxx
12. The primary issue to be decided in the present petition is,
therefore, as to whether it was mandatory for the petitioner to resort
to the conciliation process by the Committee before invoking
arbitration. Though Article 26.2 clearly states that before resorting
to arbitration, the parties agree to explore conciliation by the
Committee, in my opinion, the same cannot be held to be mandatory
in nature. It needs no emphasis that conciliation as a dispute
resolution mechanism must be encouraged and should be one of the
first endeavours of the parties when a dispute arises between them.
However, having said that, conciliation expresses a broad notion of
a voluntary process, controlled by the parties and conducted with the
assistance of a neutral third person or persons. It can be terminated
by the parties at any time as per their free will. Therefore, while
interpreting Article 26.2, the basic concept of conciliation would
have to be kept in mind.
xxx xxx xxx
15. In Ravindra Kumar Verma case [Ravindra Kumar Verma v. BPTP
Ltd., 2014 SCC OnLine Del 6602], this Court had stated that any
doubt on the aspect of whether conciliation proceedings, as required
by the arbitration clause, is directory or mandatory in nature, is
removed when reference is placed on Section 77 of the Act, which
reads as under:
“77. Resort to arbitral or judicial proceedings
The parties shall not initiate, during the conciliation
proceedings, any arbitral or judicial proceedings in respect of
a dispute that is the subject-matter of the conciliation
proceedings except that a party may initiate arbitral or judicial
proceedings where, in his opinion, such proceedings are
necessary for preserving his rights.”
ARB.P. 1678/2025 Page 15 of 18
(emphasis supplied)
16. Section 77 of the Act as also Clause 16 of the OM state that
where, in the opinion of a party, immediate initiation of the arbitral
proceedings is necessary to preserve the rights of the said party, the
said party may initiate arbitral or judicial proceedings even during
the conciliation proceedings. Therefore, in case of urgency, arbitral
proceedings can be initiated even when conciliation proceedings are
pending. To determine whether there is such an urgency or it is
necessary to immediately invoke arbitration, it is the opinion of the
party concerned which is the relevant and the governing factor. This
is so because conciliation, as noted hereinabove, is a voluntary
process and by its very nature directory. It can be terminated at any
point of time by any party.
xxx xxx xxx”
(Emphasis Supplied)
24. Reference in this regard is also made to the case of Hindustan
Unilever Limited Versus Jagdish Kumar Sole Proprietor of Hari Ram
Dharam Pal, 2024 SCC OnLine Del 7522, wherein, the Court has reiterated
that resolution of disputes through mediation, conciliation or similar
mechanisms, is directory and not mandatory. Thus, it was held as follows:
“xxx xxx xxx
7. This Court in its catena of judgments has taken a view that any
pre-arbitral mechanism making it obligatory to seek resolution of
disputes through mediation or conciliation or the like, is directory
and not mandatory.
8. In the case of Oasis Projects Ltd. v. National Highway &
Infrastructure Development Corporation Limited, (2023) 1 HCC (Del)
525, it was held as under:—
“12. The primary issue to be decided in the present
petition is, therefore, as to whether it was mandatory for the
petitioner to resort to the Conciliation process by the
Committee before invoking arbitration. Though Article 26.2
clearly states that before resorting to arbitration, the parties
agree to explore Conciliation by the Committee, in my
opinion, the same cannot be held to be mandatory in nature.
It needs no emphasis that Conciliation as a Dispute
Resolution Mechanism must be encouraged and should be
ARB.P. 1678/2025 Page 16 of 18
one of the first endeavours of the parties when a dispute
arises between them. However, having said that, Conciliation
expresses a broad notion of a voluntary process, controlled by
the parties and conducted with the assistance of a neutral
third person or persons. It can be terminated by the parties at
any time as per their free will. Therefore, while interpreting
Article 26.2, the basic concept of Conciliation would have to
be kept in mind.”
(emphasis supplied)
9. In Kunwar Narayan v. Ozone Overseas Pvt. Ltd. 2021 : DHC : 496,
it was held as under:—
“5. Ms. Pahwa, learned Counsel for the respondents
submitted that her only objection, to the petition, was that the
petitioner has not exhausted the avenue of amicable resolution,
contemplated by Clause 12 of the Share Buyback Agreement. I
am not inclined to agree with this submission. The recital of
facts, as set out in the petition, indicate that efforts at trying to
resolve the disputes, amicably were made, but did not succeed.
Even otherwise, the Supreme Court in Demarara Distilleries
Pvt. Ltd. v. Demerara Distilleries Ltd. and this Court, in its
judgment in Ravindra Kumar Verma v. BPTP Ltd., opined
that relegation of the parties to the avenue of amicable
resolution, when the Court is moved under Section 11(6) of
the 1996 Act, would be unjustified, where such relegation
would merely be in the nature of an empty formality. The
arbitration clause in the present case does not envisage any
formal regimen or protocol for amicable resolution, such as
issuance of a notice in that regard and completion of any
stipulated time period thereafter, before which arbitral
proceedings could be invoked. In the absence of any such
stipulation, I am of the opinion, following the law laid down
in Demarara Distilleries Pvt. Ltd. and Ravindra Kumar
Verma v. BPTP Ltd. nothing worthwhile would be achieved,
by relegating the parties to explore any avenue of amicable
resolution. Besides, the appointment of an arbitrator by this
Court would not act as an impediment in the parties resolving
their disputes amicably, should it be possible at any point of
time.”
xxx xxx xxx”
(Emphasis Supplied)
25. At this stage, it is noted that the petitioner has invoked the arbitration
ARB.P. 1678/2025 Page 17 of 18
clause, i.e., Clause 15 (b) of the Lease Deed by way of notice dated 22
nd
August, 2025 under Section 21 of the Arbitration Act, to which there has
been no reply by the respondent.
26. In view of the above, this Court is satisfied that there exists a valid
arbitration clause and there are disputes between the parties, which need to
be adjudicated through arbitral mechanism.
27. It is to be noted that during the course of hearing, the respondent
expressed that disputes in the present case be referred to another Arbitrator,
other than the one already appointed in dispute related with the sister
concern of the petitioner. Further, this Court notes that the arbitration
proceedings between the respondent herein and the sister concern of the
petitioner in a similar agreement, are being held under the aegis of the Delhi
International Arbitration Centre (“DIAC”).
28. Accordingly, the dispute between the parties arising out of the Lease
Deed is referred to the Arbitral Tribunal, comprising of a Sole Arbitrator.
The following directions are issued in this regard:
i. Justice (Retd.) Shalinder Kaur, former Judge, Delhi High Court,
(Mobile No.: 9910384702) is appointed as a Sole Arbitrator to
adjudicate the disputes between the parties.
ii. The arbitration proceedings shall be held under the aegis and Rules of
DIAC, Delhi High Court, Sher Shah Road, New Delhi.
iii. The remuneration of the learned Arbitrator shall be in terms of DIAC
(Administrative Cost and Arbitrators’ Fees) Rules, 2018.
iv. The learned Arbitrator is requested to furnish a declaration in terms of
Section 12 of the Arbitration Act prior to entering into the reference.
ARB.P. 1678/2025 Page 18 of 18
In the event of any impediment to the Arbitrator’s appointment on
that Count, the parties are given liberty to file an appropriate
application before this Court.
v. It shall be open to the respondent to raise counter-claims, if any, in
arbitration proceedings.
vi. It is made clear that all the rights and contentions of the parties,
including, as to the arbitrability of any of the claim, any other
preliminary objection, as well as claims/counter-claims and merits of
the dispute of either of the parties, are left open for adjudication by
the learned Arbitrator.
vii. The parties shall approach the learned Arbitrator within two (02)
weeks from the date of appointment of the Arbitrator.
29. It is made clear that this Court has not expressed any opinion on the
merits of the case.
30. Accordingly, the present petition is disposed of in the aforesaid terms.
31. The Registry is directed to send a copy of this order to the Secretary,
DIAC for information and compliance.
MINI PUSHKARNA
(JUDGE)
JANUARY 29, 2026/KR
Legal Notes
Add a Note....