As per case facts, a project by NMMC awarded to Pratibha for pipeline laying under a deferred payment scheme faced significant delays in obtaining right of way, extending a one-year ...
J-ARA-9-2021-04.02.26.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
ARBITRATION APPEAL NO. 9 OF 2021
Pratibha Industries Limited (In Liquidation) Thr its
Liquidator, Mr. Anil Mehta
…Appellant
Versus
Navi Mumbai Municipal Corporation, Through Its
Executive Engineer (Morbe)
…Respondent
Ms. Ridhi Nyati, a/w Kunal Naik, Vanshika Jain, i/b Ashwin
Shanker, for the Appellant.
Mr. Tejesh Dande, a/w Bharat Gadhvi, Sarvesh Deshpande,
Mansi Dande, Trusha Shah, for Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
DATE : FEBRUARY 6, 2026
JUDGEMENT:
Context and Factual Background:
1. This is an Appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (“the Act”) impugning an order dated December
10, 2020 (“Impugned Judgement”) passed by the Learned Principal
Page 1 of 32
February 6, 2026
Aarti Palkar
AARTI
GAJANAN
PALKAR
Digitally
signed by
AARTI
GAJANAN
PALKAR
Date:
2026.02.06
14:35:54
+0530
J-ARA-9-2021-04.02.26.doc
District Judge, Thane, setting aside the arbitral award dated November
05, 2015 passed by a Learned Sole Arbitrator (“Arbitral Award”). The
arbitral award partly allowed certain claims of the Appellant, Pratibha
Industries Limited, Mumbai (in liquidation) (“Pratibha”) in its claims
against the Respondent, Navi Mumbai Municipal Corpora tion
(“NMMC”).
2. The disputes between the parties relate to a project awarded
by NMMC to Pratibha by a Contract dated April 04, 2005 (“Contract”)
entailing laying of pipelines in Navi Mumbai under a deferred payment
scheme (“Project”). All payments for the Project were required to be
made after completion of the Project. The cost of the Project was
approximately Rs. 200 crores. Right of way over land on which pipelines
had to be laid,– for over a 30-kilometer stretch – was necessary, but the
last parcel of land was actually received after approximately two years,
while the Project was to be completed within one year.
3. There is no dispute between the parties on the quantification
of the claimed amounts. Suffice it to say that Pratibha had claimed
Rs.~20.8 crores towards increase in financing costs on account of
delayed release of instalment payments, but was awarded only Rs.14.68
crores. Pratibha also made a claim for price escalation during the
Page 2 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
extended contract and also for the cost of extended stay for the Project
in the sum of Rs.8.56 crores and Rs.7.27 crores respectively, but was
awarded sums of Rs.3.07 crores and Rs.3.11 crores respectively. The
length of the pipeline was increased, and Pratibha made a claim for such
increase in length in the sum of Rs.1.74 crores, which was disallowed.
Finally, interest had been claimed until the date of the award, in the
sum of Rs.15.51 crores but the Learned Arbitrator granted interest
which amounted to Rs.5.41 crores. No costs were awarded in the
Arbitral Award. The aggregate amount awarded by the Learned Arbitral
Tribunal was in the sum of Rs.26.29 crores along with interest at the
rate of 18% per annum from the date of the Arbitral Award until
realisation.
Contentions of the Parties:
4. I have heard Ms. Ridhi Nyati, Learned Advocate for Pratibha
and Mr. Tejesh Dande, Learned Advocate for NMMC and with their
assistance, examined the record.
5. It is seen from the material on record that the quantification
of the claims is not subject matter of dispute between the parties. The
core question that arises for consideration in the adjudication of this
Page 3 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
Appeal is whether the Section 34 Court was right in its intervention,
quashing and setting aside the Arbitral Award.
6. Ms. Nyati would contend that the Section 34 Court has
adjudicated the facts and the evidence afresh, re-appreciating the
evidence to effectively carry out fresh trial. In other words, the
contention is that the Section 34 Court has not been mindful of the
scope of jurisdiction under Section 34 of the Act and has instead chosen
to conduct the proceedings as if it were a first appeal with full
consideration of facts as well as the Contract involved in the matter. Ms.
Nyati would contend that the Learned Arbitral Tribunal had interpreted
the Contract between the parties to return an eminently plausible and
reasonable view, and that the Section 34 Court ought not to have
substituted such a plausible view with another view that was considered
more plausible and more appropriate by the Section 34 Court.
7. Ms. Nyati would also contend that the Section 34 Court, in
adopting the aforesaid approach, has gone so far as to rule on the entire
material on record, even relying upon points that had never been
pressed into service by NMMC either in the arbitral proceedings or in
the Section 34 proceedings. Ms. Nyati would submit that the Impugned
Judgement is also perverse because the Section 34 Court alluded to
Page 4 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
evidence which does not exist. She would further submit that the
Impugned Judgement is also inherently contradictory in holding that
there is no ambiguity in the contractual terms even while noting that
there were two competing sets of conditions, with the Section 34 Court
choosing to reconcile such competing sets of conditions in a manner
that appealed more to the Section 34 Court.
8. Mr. Tejesh Dande on behalf of NMMC would counter the
foregoing submissions to contend that the Section 34 Court has been
mindful of the scope of review available under Section 34 of the Act and
has arrived at a considered view that the Arbitral Award was against the
fundamental policy of Indian law. He would point to Paragraphs 20 to
26 of the Impugned Judgement to justify the approach of the Section 34
Court and contend that the Learned Arbitral Tribunal had completely
ignored the priority and relevance of the constituent documents
constituting the Contract between the parties. Therefore, since the
Arbitral Award had applied incorrect parameters of assigning priorities
to multiple documents constituting the Contract, the Section 34,
according to Mr. Dande, has rightly interfered with findings that were
contrary to contract.
Page 5 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
9. Mr. Dande would submit that the Learned Arbitral Tr ibunal
had erred in appreciating the exact controversy between the parties in
connection with breach of the escrow arrangement put in place and it
was the Section 34 Court that has correctly interfered on this count. He
would submit that it was Pratibha's obligation to pursue and obtain all
necessary permissions to secure the right of way and the General
Conditions of Contract (“GCC”) had specifically stipulated that no
compensation can be granted for delay in obtaining of sanctions. Since
the Learned Arbitral Tribunal has wrongly interpreted this issue, Mr.
Dande would submit, the Section 34 Court was entitled to interfere and
set aside the arbitral award.
10. Mr. Dande would also submit that the grant of a claim for
price escalation was also wrongly granted by the Learned Arbitral
Tribunal. Pratibha had sought extension of time for completion of
milestones and each time NMMC granted such extension, it imposed a
categorical condition that the extension was granted without any
compensation or cost escalation. Therefore, the Learned Arbitral
Tribunal was perverse in allowing claims in this regard.
Page 6 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
Core Issues:-
11. Having heard the parties, it is evident to me that the core
issue that needs to be dealt with for adjudication of this Appeal is
whether the Learned Arbitral Tribunal had erred in its interpretation of
the interplay between the terms of the Fédération Internationale Des
Ingénieurs-Conseils (“FIDIC Conditions”) and the GCC, which form part
of the tender document (“Tender Terms”). Should a conflict arise
between the FIDIC Conditions and the Tender Terms, which one would
prevail, is the question that arose. The Learned Arbitral Tribunal held
that the Contract between the parties is to be interpreted in a manner
that the FIDIC conditions and the Escrow Agreement would override
the Tender Terms where a conflict emerged, whereas the Section 34
Court held that the Tender Terms would override the FIDIC conditions
and the Escrow Agreement, in its interpretation of the precedence and
priority in the contract-forming instruments.
12. The implications for the delay in obtaining the right of way
for timely completion of the Project is the other key broad issue that
falls for consideration. The Arbitral Award returns a finding that NMMC
was entirely responsible for providing the right of way at its own cost
and time, and in the event of delay, Pratibha would be entitled to time
Page 7 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
extension and cost compensation for such delay. The Section 34 Court
held that NMMC was only required to make the applications and pay
the requisite fees towards the right of way, but securing the right of way
was entirely Pratibha's obligation with cost implications for its own
account in the event of delay. Therefore, Section 34 Court held that
while NMMC was entitled to grant extension of time to Pratibha, the
Arbitral Tribunal ought not to have awarded any costs or damages in
favour of Pratibha.
Scope of Review:-
13. The scope of review of Section 34 Court is now quite clear
and has been laid down in multiple judgements of the Supreme Court
including Dyna Technologies
1
, Associate Builders
2
, Ssyangyong
3
,
Konkan Railway
4
and OPG Power
5
. The arbitral award having been
passed on November 5, 2015, there can be no quarrel that the Act as
amended in 2015 would apply in the instant case.
14. The principles of law laid down in Ssyangyong, to the extent
it overwrote the principles declared earlier in Associate Builders would
1 Dyna Technologies Private Limited v. Crompton Greaves Ltd – (2019) 20 SCC 1
2 Associate Builders vs. Delhi Development Authority – (2015) 3 SCC 49
3 Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of
India – (2019) 15 SCC 131
4 Konkan Railways v. Chenab Bridge Project Undertaking – 2023 INSC 742
5 OPG Power vs. Enoxio – (2025) 2 SCC 417
Page 8 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
apply. In a nutshell, it must be remembered that the Section 34 Court
must not lightly interfere with arbitral awards. The Section 34
jurisdiction lends itself to disturbing arbitral awards strictly within the
parameters legislated within Section 34 of the Act. It cannot be
forgotten that arbitral tribunals are the master of the evidence and
therefore, the best determinants of the quality and the quantity of the
evidence. Indeed, it is quite right that if the findings of the arbitral
tribunal are plausible, the Section 34 Court ought not to re-appreciate
the evidence, re-interpret the contract and return its own view on what
ought to have been the arbitrator's view so long as the arbitrator's view
is a plausible one.
15. For the Section 34 Court to interfere with an arbitral award, it
must come to a view that the arbitral award suffers from unpardonable
perversity in a manner that cuts to the root of the matter with no
possibility of another view.
16. To avoid prolixity, each of the aforesaid judgements need not
be extracted from, but the following extract from Dyna Technologies
would suffice:
“24. There is no dispute that Section 34 of the Arbitration Act limits a
challenge to an award only on the grounds provided therein or as in-
Page 9 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
terpreted by various courts. We need to be cognizant of the fact that
arbitral awards should not be interfered with in a casual and cavalier
manner, unless the court comes to a conclusion that the perversity of
the award goes to the root of the matter without there being a possibil-
ity of alternative interpretation which may sustain the arbitral
award. Section 34 is different in its approach and cannot be equated
with a normal appellate jurisdiction. The mandate under Section 34 is
to respect the finality of the arbitral award and the party autonomy to
get their dispute adjudicated by an alternative forum as provided un-
der the law. If the courts were to interfere with the arbitral award in
the usual course on factual aspects, then the commercial wisdom be-
hind opting for alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have cat-
egorically held that the courts should not interfere with an award
merely because an alternative view on facts and interpretation of con-
tract exists. The courts need to be cautious and should defer to the
view taken by the Arbitral Tribunal even if the reasoning provided in
the award is implied unless such award portrays perversity unpardon-
able under Section 34 of the Arbitration Act .”
[Emphasis Supplied]
17. In Dyna Technologies, the Supreme Court also ruled on the
scope of jurisdiction of the Section 37 Court to remind that the
jurisdiction of Section 37 Court is akin to the jurisdiction of Section 34
Court. The scope of interference by the Section 37 Court in examining
an order under Section 34 would be to see whether the review of the
Page 10 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
Arbitral Award was effected in the manner stipulated iun Section 34 of
the Act. If the Section 34 Court did not discharge its powers consistent
with its jurisdiction, the Section 37 Court would play the role the Section
34 Court ought to have played. If the Section 34 Court had exercised its
jurisdiction accurately, the Section 37 Court ought not to interfere with
the Section 34 Court’s view.
18. Specifically, dealing with the facets of interpretation of
contract, in Konkan Railway the Supreme Court ruled thus:
14. Analysis: At the outset, we may state that the jurisdiction of the Court under Sec -
tion 37 of the Act, as clarified by this Court in MMTC Ltd. v. Vedanta Ltd., is
akin to the jurisdiction of the court under Section 34 of the Act . Scope of inter-
ference by a court in an appeal under Section 37 of the Act , in examining an
order, setting aside or refusing to set aside an award, is restricted and subject
to the same grounds as the challenge under Section 34 of the Act .
[Emphasis Supplied]
19. Specifically, on the subject of re-interpretation of contracts,
the Supreme Court has cautioned that reinterpretation to arrive at an
alternate view is impermissible. This ought to be remembered both by
the Section 34 Court and the Section 37 Court.
Page 11 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
20. The upshot is that the Supreme Court has specifically
cautioned time and again against re-interpreting a contract on the
ground that a different alternate view was felt to be more appealing than
how the arbitral tribunal interpreted it.
Analysis and Findings:-
21. Against this aforesaid backdrop, it would be necessary for
this Court to examine whether the Section 34 Court had exercised its
jurisdiction consistent with the scope of review contemplated under
Section 34 of the Act.
22. To begin with, it is apparent, even from a plain reading of the
submissions made by NMMC in defence of the Impugned Judgement,
that NMMC's robust defence is entirely based on interpretation of the
evidence, finding fault with the Learned Arbitral Tri bunal's
interpretation. It is important to examine the issue of the conflict
between the FIDIC Conditions and the Tender Terms. The Impugned
Judgement indeed recognizes that there was an ambiguity and conflict
between the FIDIC Conditions and the Tender Terms. Thereafter, the
Section 34 Court has proceeded to delve deep into the merits to return a
finding as to what was a more appropriate interpretation for resolving
such conflict.
Page 12 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
23. The Project, which entailed a laying of a pipeline passing
through land belonging to various third parties, including authorities
such as the Railways. This necessitated obtaining permission for right of
way from such parties to lay the pipelines in their land. At the time of
the Tender, since the right of way was not readily available for the entire
stretch of the Project and the Project was covered by a deferred payment
scheme, financial closure was a challenge. The contractor’s payments
would not be made from time to time, but only after due completion of
the Project of pre-agreed milestones. Therefore, the contractor, had to
achieve financial closure for the Project in advance on its own. In other
words, there could have been no reliance on any cash flows emanating
from NMMC (i.e. the client) for Pratibha (i.e. the contractor) to manage
its cash flows, although the Project is the client’s project and never the
contractor’s project. Therefore, even before the Contract was awarded,
the uncertainty as to how this facet would be handled came up for
discussion in pre-bid meetings. It was pointed out that the Tender
Terms led to financial uncertainty and therefore in discussions between
NMMC and the bidders for the Project, it was clarified that although the
tender stipulated that NMMC would provide the right of way and that
there shall be only a time extension without compensation for delay,
FIDIC Conditions would be adopted. The record bears out the fact that
Page 13 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
the parties had agreed in the pre-bid stage itself that to make the Project
bankable it would be appropriate to adopt the FIDIC Conditions.
24. Once the evidence on record reasonably and plausibly
pointed to the adoption of FIDIC Conditions, which provide that the
contractor would be entitled to compensation on account of delay in
right of way being made available, the Arbitral Award cannot be faulted
in its analysis of the consequences of delay. It is also apparent that the
financial uncertainty in sequencing and timing of release of payments
under the deferred payment scheme had to be addressed for which the
escrow arrangement was also contracted although never envisaged in
the original Tender Terms.
25. It is in this context, that the submissions made by Ms. Nyati
on behalf of Pratibha are quite accurate inasmuch as the Statement of
Defence on behalf of NMMC specifically pleaded that NMMC had
allowed suggestions from the bidders in relation to the conditions of
contract at the pre-bidding stage. It is clear that based on suggestions
from bidders, NMMC
“had agreed to adopt FIDIC”. In view of such
pleading by NMMC, it would follow that to the extent the FIDIC
Conditions entailed any conflict with the Tender Terms, the FIDIC
Conditions would apply. Indeed, even while the Tender Terms were not
Page 14 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
wholly substituted, lock stock and barrel with the FIDIC Conditions,
what was certainly achieved is that wherever there was a conflict, it
would be the FIDIC Conditionsthat would prevail.
26. Therefore, the contract-forming provisions governing the
relationship between the parties was an amalgam of the Tender Terms
and the FIDIC Conditions, and to the extent there was any conflict
between the two, it would not be unreasonable to conclude that the
FIDIC Conditions would govern the area of conflict between the two
instruments. Under the FIDIC Conditions, the delay in providing right
of way would lead to an extension of time coupled with compensation
whereas under the Tender Terms the delay in right of way would lead to
only extension of time without compensation.
27. Likewise, if the FIDIC Conditions were to be applied, while
Pratibha was to obtain permits and licences in relation to the design,
execution and completion of the Project, it would follow that the risk
and reward of the permissions being secured would lie in the domain of
NMMC.
28. Indeed, as Ms. Nyati would rightly point out, there also are
terms contained in the Tender Terms which would not stand displaced
Page 15 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
by the FIDIC Conditions – for example, the dispute resolution
procedure or the period of limitation for raising claims.
29. It cannot be forgotten that the discussion and adoption of the
FIDIC Conditions in the pre-bid meetings was essentially centered
around the financial uncertainty that emerged from the Project being
implemented on a deferred payment basis. Indeed, under Section 28(3)
of the Act, the Arbitral Tribunal must rule not only in accordance with
the terms of the contract, but also in accordance with customs and trade
usages applicable to the transactions in question. It goes without saying
that against this backdrop, when parties applied their mind to the
problems that would emerge in achieving financial closure, and for
timely execution of the contract, adopted the FIDIC Conditions, the
view returned by the Learned Arbitral Tribunal cannot be considered to
be an unreasonable, arbitrary or perverse view. Therefore, interference
with the Arbitral Award on this count does not appear to be a correct,
specifically bearing in mind the scope of review envisaged under Section
34 of the Act.
30. As regards the escrow agreement, there is again a conflict and
ambiguity that has emerged in the contract-forming documentation
between the parties. Under the original tender, the commencement date
Page 16 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
of the Project would have been May 20, 2006 whereas under the escrow
agreement the commencement date was July 14, 2006. The escrow
agreement was in fact executed between Pratibha and NMMC and State
Bank of Mysore on June 14, 2006, well after the date of commencement
envisaged under the Tender Terms. Under the escrow agreement, the
pleaded case of NMMC acknowledges that the commencemen t date
would be the date following 60 days from the date of issuance of the
letter of acceptance and therefore, the scheduled commencement date
for the Project would be July 14, 2006. While this is an admitted
position in the statement of defence of NMMC, the Impug ned
Judgement has taken a view contrary to the pleadings of NMMC.
31. Reference may be made to Paragraph 4 in the tender notice
pursuant to which the Project was awarded. In this paragraph, it was
explicitly envisaged that a pre-bid conference of all interested bidders
would be held. The bidders would be allowed to seek clarifications and
suggest “
suitable modifications in specifications, conditions of contract,
etc.
”. This paragraph squarely provided that queries about the Project
would need to be communicated in writing well prior to the conduct of
the pre-bid conference and such suggestions which are accepted by
NMMC would be communicated to all. Only the changes that are so
communicated would bind NMMC and the bidders.
Page 17 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
32. It is in this backdrop, that one must note that the Tender
Terms explicitly provide that the contract-forming documentation
would include the tender notice and instructions given to the bidders.
Paragraph 4 is an integral part of the tender notice, and the pre-bid
discussions, which led to the adoption of the FIDIC Conditions, which
then become a part of the Tender Terms. The minutes of the meeting
which contained the pre-bid clarifications were communicated by
NMMC by a letter dated January 30, 2006, also calling upon the bidders
to duly sign the same in acceptance. Specifically, in the pre-bid meeting,
it was agreed between the parties that FIDIC Conditions would be
adopted and the parties would need to execute the FIDIC Conditions
and return the same to NMMC.
33. In response to the FIDIC suggestion from another bid der
namely, IVRCL Infrastructure and Projects Ltd. (“IVRCL”), the decision
communicated by NMMC stated, “
We agree to adopt FIDIC conditions.
However, the agency has to submit FIDIC document duly signed and
accepted
”.
34. Likewise, in response to a query raised by Pratibha ,
suggesting that NMMC must pool all its revenues into an escrow
account with a designated bank and release payments to the contractor
Page 18 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
through that account, and suggested that a tripartite agreement for the
purpose, NMMC provided its decision stating that “
Escrow Account
Procedure can be considered
”. Other bidders too had raised queries in
relation to escrow procedures for the milestone-based payments to be
released to the contractor and NMMC has replied that “
Deposit can be
escrowed
”. The execution of a signed copy of the pre-bid minutes of
meeting and of the FIDIC conditions is a matter of record. The actual
execution of an escrow agreement is also a matter of record.
35. When these terms are explicitly executed as provisions
governing the parties, based on the decision taken even prior to the
award of the project, it would be completely plausible that these
additional measures adopted by the parties would form part of Item
No.3 of Clause 3(e) of the Tender Terms in the “
order of precedence in
case of discrepancies
” stipulated in the GCC.
36. The order of precedence in the GCC places the tender notice
and bidder instructions at Item 3 of Clause 3(e); special conditions of
contract at Item 4 and the GCC at Item 5. The issue before the Arbitral
Tribunal was to examine whether the FIDIC Conditions cou ld
reasonably be regarded as forming part of the tender notice and
instructions given to bidders.
Page 19 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
37. Since the decision to adopt FIDIC Conditions, and the
decision to adopt an escrow mechanism was taken prior to award of the
Project and in modification of the Tender Terms themselves, it is
completely plausible for the Learned Arbitral Tribunal to treat them as
having priority over the special conditions of contract and the general
conditions of contract in the order of precedence.
38. That apart, to my mind, since Section 28(3) of the Act
requires the arbitrator, (that too in the facts of this case, an arbitrator
with expertise in the domain) to rule not only in accordance with the
terms of the contract, but also in accordance with customs and trade
usages applicable to the transactions in question, one cannot lose sight
of the context in which FIDIC Conditions and the escrow agreement
were introduced into the contract-forming documentation – the core
objective being to make the Project bankable and amenable to a smooth
financial closure. This being the objective for which the parties
consciously agreed to move away or to improve upon the originally
stipulated Tender Terms, in my opinion, it would be very difficult to
take a view that the Learned Arbitral Tribunal had adopted a perverse
view, not supported by the terms of contract between the parties.
Page 20 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
39. What complicated the matter further for the Section 34 Court
is that the FIDIC Conditions themselves also contain a sequence and
order of priority among the contract-forming documents. Clause 1.5 of
the FIDIC Conditions stipulates a priority whereby the contract
agreement would have priority over particular conditions which would
then have priority over general conditions, and the tender and other
documents forming part of the contract would come in last in the order
of priority.
40. The Section 34 Court has concluded that the tender Terms,
which included the GCC and the special conditions of contract, would
fall within the ambit of “particular conditions” under Clause 1.5 and that
the FIDIC Conditions, would fall under the category “gen eral
conditions”, with a lower precedence. Without intending to comment on
the accuracy of such reading, what becomes abundantly clear is that the
Section 34 Court has waded deep into the ambit of interpretation of
contract to substitute its reading of the contract for the reasonable
reading adopted by the Learned Arbitral Tribunal. Even assuming such
a view were plausible, it was not open to the Section 34 Court to replace
a plausible view already taken by the Learned Arbitral Tribunal with
another view that appeared more plausible to the Section 34 Court.
Page 21 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
41. That apart, it appears that treating the FIDIC Conditions as
forming part of the tender conditions under Clause 1.5(e) of the FIDIC
conditions or to indicate that the general conditions and the special
conditions would fall within the ambit of “particular conditions” under
Clause 1.5(b) of the FIDIC Conditions, one would necessarily need to
conclude that there were conflicting terms of priority, even while
treating the FIDIC Conditions themselves as forming part of one of the
competing instruments in such priority. This would lead to a circular
and irrational conflict within a conflict.
42. The upshot of this situation is that evidently the contract
contains an ambiguity requiring a forum interpreting the contract to
adopt the business efficacy test to give true meaning to the situation at
hand and interpret the same in a commercially logical and rational
manner.
43. In Nabha Power
6
the Supreme Court noticed various earlier
judgements on how to give commercial sense to terms in a contract that
may not lend themselves to a clear unequivocal meaning, in the
following terms:
6 Nabha Power Ltd. v. Punjab SPCL – (2018) 11 SCC 508
Page 22 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
49. We now proceed to apply the aforesaid principles which have
evolved for interpreting the terms of a commercial contract in
question. Parties indulging in commerce act in a commercial sense. It
is this ground rule which is the basis of The Moorcock [The Moorcock,
(1889) LR 14 PD 64 (CA)] test of giving “business efficacy” to the
transaction, as must have been intended at all events by both business
parties. The development of law saw the “five condition test” for an
implied condition to be read into the contract including the “business
efficacy” test. It also sought to incorporate “the Officious Bystander
Test” [Shirlaw v. Southern Foundries (1926) Ltd. [Shirlaw v. Southern
Foundries (1926) Ltd., (1939) 2 KB 206 : (1939) 2 All ER 113 (CA)] ].
This test has been set out in B.P. Refinery (Westernport) Proprietary
Ltd. v. Shire of Hastings [B.P. Refinery (Westernport) Proprietary
Ltd. v. Shire of Hastings, 1977 UKPC 13 : (1977) 180 CLR 266 (Aus)]
requiring the requisite conditions to be satisfied: (1) reasonable and
equitable; (2) necessary to give business efficacy to the contract; (3) it
goes without saying i.e. the Officious Bystander Test; (4) capable of
clear expression; and (5) must not contradict any express term of the
contract. The same penta-principles find reference also in Investors
Compensation Scheme Ltd.v. West Bromwich Building
Society [Investors Compensation Scheme Ltd. v. West Bromwich
Building Society, (1998) 1 WLR 896 : (1998) 1 All ER 98 (HL)]
and Attorney General of Belize v. Belize Telecom Ltd. [Attorney
General of Belize v. Belize Telecom Ltd., (2009) 1 WLR 1988 (PC)]
Needless to say that the application of these principles would not be to
substitute this Court's own view of the presumed understanding of
commercial terms by the parties if the terms are explicit in their
expression. The explicit terms of a contract are always the final word
with regard to the intention of the parties. The multi-clause contract
inter se the parties has, thus, to be understood and interpreted in a
Page 23 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
manner that any view, on a particular clause of the contract, should
not do violence to another part of the contract.
[Emphasis Supplied]
44. In coming to the foregoing view, the Supreme Court endorsed
and reiterated what had been stated in a long line of judgements that
had endorsed these principles including in the cases of Dhanrajamal
Gobindram
7
(paragraph 19); D.N. Revri
8
(paragraph 7); and Satya Jain
9
(paragraphs 33 to 35).
45. In my opinion, the view returned by the Learned Arb itral
Tribunal can also be upheld on the premise that it was a rational, logical
and fair manner of giving business efficacy to the contract between the
parties. Effectively, what the Learned Arbitral Tribunal has found is
clearly justifiable on the aforesaid parameters since its formulation of
the interpretation is responsive to the business efficacy test.
46. It is also well-settled law that if an arbitral award returns a
fair finding, and could be justified by any logical reasons that may not
have been explicitly set out by the arbitrator, then too, the Section 34
7 Dhanrajamal Gobindram v. Shamji Kalidas and Co. – (1961) 3 SCR 1020 : AIR
1961 SC 1285
8 Union of India v. D.N. Revri & Co. – (1976) 4 SCC 147
9 Satya Jain v. Anis Ahmed Rushdie – (2013) 8 SCC 131
Page 24 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
Court must lean in favour of giving deference to such logical and fair
outcome rather than look for reasons to set aside the arbitral award.
47. In addition to the foregoing, it must also be noted that the
reliance by the Learned Arbitral Tribunal on trade practice, to
supplement its reasoning, with particular regard to the facet of
obtaining permissions for right of way, ought not to have been faulted
by the Section 34 Court. It is undisputed that the time taken for
obtaining the right of way took way beyond the 12 months within which
the Project was to be completed. The Section 34 Court has criticized the
invocation of practice and usage by the Learned Arbitral Tribunal by
stating that this was not a matter of any technical or scientific issues
having to be examined to necessitate any expert knowledge of the
arbitrator. The Section 34 Court disagreed with the Learned Arbitral
Tribunal in its view on taking into account usage of trade applicable to
the transaction.
48. Section 28(3) of the Act squarely requires the arbi tral
tribunal to take into account usages of trade applicable to the
transaction. The Learned Arbitral Tribunal was manned by a former
Chief Engineer of City and Industrial Development Corporation of
Maharashtra Limited (“CIDCO”) and was in fact a unilateral appointee
Page 25 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
of NMMC. He has taken a view on what it entails to secure the right of
way and that too from other government agencies such as the Railways,
Development Authorities, Public Works Departments and CIDCO. In
my view, there was no need to find fault with the Arbitral Award on this
count. An instrumentality of the State would be best placed to engage
with other instrumentalities of the State in obtaining approvals as
serious as the right of way to dig up land and lay pipelines. It is
reasonable and plausible to interpret Pratibha’s obligation to obtain the
right of way as the obligation to engage with the requisite officials of
these State agencies to facilitate securing the right of way. Such a role
would be a role of interacting on behalf of NMMC. It also cannot be
forgotten that the principal in the contract is NMMC while Pratibha is
the agent.
49. It is in this light that when parties have agreed to a specific
timeframe for completion of the contract and the very basic requirement
i.e. obtaining the right of way, took far longer than the envisaged Project
timeline, it was only logical and fair for the arbitrator, having examined
the evidence on record, to return the view that he did.
50. Equally, it is a matter of record that even in disallowing
Pratibha’s claim for additional costs for the additional pipeline, it is
Page 26 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
trade usage that the arbitrator has relied upon to dismiss that
component of Pratibha’s claim in favour of NMMC.
51. Therefore, in my opinion, it would be inappropriate to second
guess the findings of the Learned Arbitrator and effect a whole-scale
substitution at the Learned Arbitrator's view. This is not a a permissible
approach for the Section 34 Court’s review of the Arbitral Award.
52. The tender notice itself specifically provided Clause 55 of the
GCC that NMMC would give the contractor possession of the site. To
give possession of the site and possession of further portions of the site,
as required from time to time, the NMMC had contracted that it would
do so with due dispatch. Clause 56 of the GCC provided that in the event
of failure to give possession, it was the contractor's obligation to plan his
work commensurate with the handing over of the site. If handing over of
the entire site itself was well after the scheduled period for completion
of the Project, it cannot be said that there would be no scope whatsoever
for the time extension obliterating scope for compensation for the delay.
In this regard, it is noteworthy that the contract indeed envisaged that
NMMC would make all necessary applications for right of way and pay
the administrative charges while the contractor would be responsible
“
for follow up and getting all types of permissions”. This too was the
Page 27 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
outcome of the pre-bid meeting clarifications issued by NMMC in
response to a query raised by IVRCL.
53. Likewise, similar answers were given to another bid der
Petron Civil Engineering Pvt. Ltd., which had highlighted that Project
execution could be exorbitantly delayed and that the contractor may at
the most be asked to liaison with the concerned authorities. The
assurance give by NMMC was that “
NMMC will give right of way to
agency
”.
54. Pratibha itself had raised a query seeking clarification on
whether the time period for completion would commence from the
placement of the work order or from handing over of the site, to which
NMMC replied that “
time limit will be considered from the date of work
order or date of handing over of the site whichever is later
”. If the
handing over of the entire site took nearly two years, Pratibha had a
strong case to be compensated.
55. Pratibha had also raised a query with specific regard to the
delay in allocation of sections of the site and the absence of
compensation, which would lead to loading of excessive interest burden
for the idle period when a contractor would have mobilized in all
respects and would simply be waiting for the site to be provided for
Page 28 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
lying the pipeline. In response, NNMC replied that “tender conditions
shall prevail. Will be paid on actuals
”.
56. This again leads to the relevance of the FIDIC Conditions. If
there were any provisions in the FIDIC Conditions that would be in
conflict with the Tender Terms that originally occupied such field of
conflict, it would follow that the FIDIC Conditions would prevail.
Towards this end, it is submitted on behalf of Pratibha that Clause 1.13
of the FIDIC Conditions provides that the employer shall have obtained
the planning, zoning or similar permission for the permanent works and
the employer shall indemnify the contract from the consequences of any
failure to do so. This certainly can be considered to be a head on conflict
between the FIDIC Conditions and the Tender Terms which stipulate
that there would be no compensation for a delay.
57. On this count too, it would be reasonable to hold that the
Learned Arbitral Tribunal can simply not be said to have returned an
implausible view in its interpretation of the various contract terms. It
becomes evident that the interpretation given by the Learned Arbitral
Tribunal is harmonious, plausible, and quite logical and reasonable.
Therefore, in my opinion, there was no basis for the Section 34 Court to
wade into how the Learned Arbitral Tribunal has interpreted the
Page 29 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
evidence, and to replace the Learned Arbitral Tribunal’s plausible
interpretation with a competing plausible view.
58. For the aforesaid reasons, in my opinion, the interference by
the Section 34 Court is not sustainable. Indeed, what was meant to be a
12-month project was finished in 26 months with the last parcel of land
on which the pipeline was to be laid, having been handed in 24 months.
59. The Learned Arbitral Tribunal, in my opinion, has returned a
reasonable, logical and harmonious reading of multiple constituent
instruments that on a combined basis, represent the contract between
the parties.
60. Once it is clear that evidently the Section 34 Court had
overstepped the scope of review as envisaged in the law governing
challenges to arbitration, in my opinion, there is no scope for sustaining
the Impugned Judgement.
61. It must also be mentioned before concluding, that th e
approach while assessing an Arbitral Award is not to examine whether it
can be set aside or whether it is accurate, but to examine whether the
grounds specified in Section 34 of the Act are at all made out to warrant
a decision to set it aside. What is clear from a plain reading of Section
Page 30 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
34 of the Arbitration Act is that the Section 34 Court must not set aside
an arbitral award unless the ingredients of Section 34(2) are available.
The opening line of Section 34(2) provides that an arbitral award may
be set aside by the Court only if the ingredients of the provisions get
attracted. There is nothing in the material on record to indicate that
the ingredients of Section 34(2) have been attracted.
62. For the reasons already articulated above, in my opinion, the
Arbitral Award does not return any decision beyond the scope of what
was submitted to arbitration. It also cannot be said to not be in
accordance with the agreement between the parties. The analysis
relating to the conflict between the FIDIC Conditions and the Tender
Terms eminently fell within the domain of interpretation of contract
that formed subject matter of the Learned Arbitrator's jurisdiction. Such
analysis being a reasonable, logical and plausible one, the Section 34
Court ought not to have substituted the views of the Learned Arbitrator
Tribunal with its own views to set aside the arbitral award.
63. For the aforesaid reasons, in my opinion, the Impu gned
Judgement is hereby set aside and the Arbitral Award is hereby revived.
64. Deposits, if any, made in the course of the challenge under
Section 34 and the further challenge under Section 37 shall be released
Page 31 of 32
February 6, 2026
Aarti Palkar
J-ARA-9-2021-04.02.26.doc
to Pratibha along with accruals, if any thereon, within a period of six
weeks from the date of upload of this judgement on the website of this
Court.
65. In the peculiar circumstances of the case, I refrain from
imposing costs in the matter.
66. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this Court’s
website.
[ SOMASEKHAR SUNDARESAN, J.]
Page 32 of 32
February 6, 2026
Aarti Palkar
Legal Notes
Add a Note....