As per case facts, a Collaboration Agreement for property development between the owner (Appellant) and developer (Respondent) encountered disputes when the owner allegedly failed to sanction building plans on time ...
FAO(OS) (COMM) 246/2023 Page 1 of 25
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 27.01.2026
Judgment pronounced on: 16.02.2026
Judgment uploaded on: 16.02.2026
+ FAO(OS) (COMM) 246/2023
M/S MILLENIUM REALTECH PVT. LTD. .....Appellant
Through: Mr. Jugal Bagga, Mr. Sumit
Kaushik, Mr. Charanjit Khatana
& Mr. Chet Ram Kaushik,
Advs .
versus
M/S OPAQUE INFRASTRUCTURE PVT. LTD.
.....Respondent
Through: Mr. Harish Malhotra Senior
Advocate with Mr. Rajender
Agarwal and Mr. Anoop
Kumar, Advs.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE AMIT MAHAJAN
J U D G M E N T
ANIL KSHETARPAL , J.:
1. The present Appeal has been filed assailing the correctness of
the judgment dated 14.08.2023 [hereinafter referred to as „Impugned
Judgment‟], passed by the learned Single Judge [hereinafter referred
to as „LSJ‟], through which the petition filed by the Appellant
(Respondent before the Arbitral Tribunal) under Section 34 of the
Arbitration and Conciliation Act, 1996 [hereinafter referred to as „Act
of 1996‟], challenging the Arbitral Award dated 20.11.2020
[hereinafter referred to as „Impugned Award‟], was dismissed.
FAO(OS) (COMM) 246/2023 Page 2 of 25
2. For the sake of clarity, consistency and ease of reference, the
parties in the present appeal shall be referred to in accordance with
their respective status before the learned Sole Arbitrator [hereinafter
referred to as „LSA‟].
FACTUAL BACKGROUND:
3. In order to comprehend the issues involved in the present case,
the relevant facts in brief are required to be noticed.
4. The present proceedings trace its genesis to the Collaboration
Agreement dated 07.11.2011 [hereinafter referred to as „Agreement‟],
with respect to a land admeasuring 1148 sq. yds. situated in Ishwar
Nagar, Mathura Road, New Delhi [hereinafter referred to as „subject
property‟]. Admittedly, the Respondent (Appellant before this Court)
is the owner of the subject property, and approached the Claimant
(Respondent before this Court), who is in the business of promotion,
development and construction of real estate, to engage it in the
development and construction of the subject property.
5. Under the Agreement, the Claimant was to bear the entire cost
of construction and, in addition, pay a total consideration of Rs. 5.20
crores to the Respondent in stages; Rs. 25 lakhs payable at the time of
execution, with additional Rs. 25 lakhs payable within 30 days of
execution, Rs. 1.50 crores payable upon the Respondent obtaining
sanction of building plans from the competent authority (to be done
within 60 days), and the balance Rs. 3.20 crores were to be paid in
four equal instalments within 120 days of intimation of sanction of the
building plans. In accordance with the terms of the Agreement, the
FAO(OS) (COMM) 246/2023 Page 3 of 25
responsibility to set out the building sanction was to be undertaken by
the Respondent within 60 days from the date of signing of the
Agreement.
6. Further, the Agreement contemplated execution of a registered
Special Power of Attorney by the Respondent in favour of the
Claimant upon sanction of building plans and receipt of Rs. 2 crores,
with a right reserved to the Claimant to rescind the Agreement in case
of default and repossess the property along with refund of the amounts
received.
7. As per the case set out by the Claimant before the LSA, after
payment of Rs. 50 lakhs in terms of the Agreement, the Respondent
failed to take timely steps to obtain sanction of the building plans and
also failed to intimate the Claimant about such sanction, compelling it
to address a communication dated 07.03.2013 enquiring about the
sanction and requesting supply of the original Agreement. It is the
case Claimant‟s case that, for the first time on 22.03.2014, the
Respondent required the Claimant to furnish credentials evidencing its
ability to execute the project, while simultaneously returning a
photocopy of a cheque for Rs. 50 lakhs purporting to refund the
advance.
8. The Respondent, on the other hand, asserted that it had
terminated the Agreement by notice dated 22.03.2014 on account of
the Claimant‟s failure to furnish documents showing its experience
and financial capacity. It was also set out that the cheque of Rs. 50
lakhs issued in favour of the Claimant was deliberately not encashed.
FAO(OS) (COMM) 246/2023 Page 4 of 25
It was further the case of the Respondent that the amount of Rs. 50
lakhs were thereafter deposited with the Registrar General of this
Court pursuant to an order passed in proceedings between the parties,
however it was ultimately withdrawn by the Claimant.
9. It was also pleaded that the Agreement, being unregistered and
having been signed by two directors without a Board resolution amidst
inter se disputes among the directors, which had led to proceedings
before the Company Law Board and an order restraining creation of
third-party interests or execution of collaboration agreements without
consent of all directors, was unenforceable in law.
10. Following the disagreements, the Claimant sent another letter
dated 02.07.2014 to the Respondent, reiterating its readiness and
willingness to perform its obligations under the Agreement, along
with a request for supply of building sanction plans, alternatively, the
Claimant invoked the arbitration clause of the Agreement. In response
to the said letter, the Respondent, by reply dated 14.07.2014, stated
that the sum of Rs. 50 lakhs stood returned pursuant to an arrangement
with one Mr. Taskeen Hussain Siddique, former director of the
Claimant, who also returned the original Agreement and as such no
occasion for appointment of an arbitrator survived. The Claimant
thereupon filed a petition under Section 9 of the Act of 1996, in which
interim orders were passed. Subsequently, a petition under Section
11(6) of the Act of 1996 came to be filed, and LSA was appointed to
adjudicate the disputes.
11. The Claimant, before the LSA, sought specific performance of
FAO(OS) (COMM) 246/2023 Page 5 of 25
the Agreement and, in the alternative, monetary compensation
representing the difference between the value of the subject property
at the time of the Agreement and at the time of the award, together
with refund of Rs. 50 lakhs with interest. The Respondent resisted the
claim, inter alia, contending that specific performance is a
discretionary relief and was barred under Sections 14(b) and (d) of the
Specific Relief Act, 1963 [hereinafter referred to as „Act of 2963‟];
that the Agreement had been validly terminated by notice dated
22.03.2014 on account of the failure of the Complaint to furnish the
requisite credentials; that the amount of Rs. 50 lakhs had been duly
returned, and that the unregistered Agreement was unenforceable in
law.
12. Pertinent to note that during the arbitral proceedings, on
18.09.2017, the LSA recorded that counsel for both parties stated that
the matter stood fully and finally settled. Additionally, it was noted
that the Respondent in its documents also filed a copy of sanction
letter dated 24.01.2013 issued by the South Delhi Municipal
Corporation (SDMC) in respect of the subject property on the basis of
their application dated 26.06.2012, however, the same only came to be
disclosed during the course of arbitration, and no intimation with
respect to the said approval was made to the Claimant. In view of the
continuing disputes amongst the Respondent‟s directors and its
inability to produce a valid Board resolution authorising the
settlement, the LSA declined to pass a consent award and directed the
parties to lead evidence. It is to note that none of the Respondent‟s
directors thereafter challenged the recording of the settlement.
FAO(OS) (COMM) 246/2023 Page 6 of 25
Nevertheless, in the absence of a duly authorised resolution, the
arbitral proceedings continued on merits.
13. By the award dated 20.11.2020, the LSA, upon consideration of
the terms of the Agreement, the conduct of the parties, including the
settlement recorded on 18.09.2017, and the evidence on record,
declined the relief of specific performance on the ground that the
Agreement contemplated performance of a continuous nature not
amenable to supervision. At the same time, the LSA held that the
Agreement was a concluded, valid and enforceable collaboration
agreement and was not compulsorily registrable under Section
17(2)(v) of the Registration Act, 1908.
14. The LSA rejected the Respondent‟s defences relating to alleged
non-supply of financial and experience-related documents, an alleged
prior settlement with Mr. Siddiqui, and the alleged return of the
original Agreement along with payment of sum of Rs. 50 lakhs.
Having regard to the aforesaid, the LSA awarded damages in favour
of the Claimant in the sum of Rs. 1.65 crores, inter alia, having regard
to the conduct of the parties and the amount of settlement recorded on
18.09.2017, along with interest @12% per annum on the awarded sum
from 30.12.2017, the date on which the last payment was to be made
by the Respondent in terms of the aforesaid settlement. Additionally, a
further post-award interest @12% per annum on the total sum of
Award were also granted, from the date of the Impugned Award till
the date of its recovery. Further, the Claimant was also held entitled to
recover the amount of Rs. 22 lakhs towards the cost of litigation and
expenses from the Respondent.
FAO(OS) (COMM) 246/2023 Page 7 of 25
15. Aggrieved by the award dated 20.11.2020, the Respondent
instituted a petition under Section 34 of the Act of 1996 before this
Court, challenging, inter alia, the refusal of specific performance, the
findings on readiness and willingness, the rejection of its defences on
termination and refund, and the award and quantification of damages
in favour of the Claimant. However, the said petition was dismissed
by way of the Impugned Judgment.
16. Accordingly, dissatisfied by the findings rendered by the LSJ in
the Impugned Judgment, the Respondent by way this Appeal has
sought the indulgence of this Court in examining the correctness of
the findings thereof.
CONTENTIONS OF THE PARTIES:
17. Learned counsel for the Appellant (Respondent before the
Arbitral Tribunal), while controverting the findings of the Impugned
Judgment, has made the following submissions:
17.1. It has been argued that the LSJ failed to appreciate that the
Claimant has failed to lead any cogent evidence to establish its
continuous readiness and willingness to perform its obligations under
the Agreement, as mandatorily required under Section 16(c) of the Act
of 1963.
17.2 It has been argued that the LSJ failed to take into consideration
that continuous readiness and willingness is a condition precedent for
the grant of relief of specific performance, and the absence thereof
disentitles a party to such relief. Reliance in this regard was placed on
FAO(OS) (COMM) 246/2023 Page 8 of 25
the decision of the Supreme Court in N.P. Thirungnanam v Dr. R.
Jagan Mohan Rao & Ors
1
.
17.3 It has been further argued that the LSJ failed to take into the
categorical admission made by the Director of the Claimant during his
cross examination, wherein he stated that the Claimant is willing to
comply with the terms of the Agreement only subject to the revision
of all prices. As per the learned counsel, the same clearly evinced the
Claimant‟s lack of intention to perform the Agreement as executed
and demonstrated an absence of the requisite readiness and
willingness in law.
17.4 Learned counsel also submitted that even while upholding the
award of damages, the LSJ failed to notice that the LSA had
overlooked the express stipulation contained in Clause (v)(d) of the
Agreement, which contemplated imposition of penalty for delay solely
upon the Claimant. It was argued that the Agreement did not envisage
any penalty or damages being levied upon the Respondent and
therefore, the award of damages against the Respondent was contrary
to the contractual framework.
17.5 Lastly, it is argued that the LSJ failed to take note of the fact
that the LSA did not even frame any specific issue with respect to the
Claimant‟s readiness and willingness, which was a fundamental and
determinative issue for adjudication of the dispute, particularly in the
context of the claim for specific performance. The absence of such an
issue, it was argued, vitiated the arbitral findings as well as the
1
(1995) 5 SCC 115
FAO(OS) (COMM) 246/2023 Page 9 of 25
Impugned Judgment.
18. Per contra, learned senior counsel for the Respondent/Claimant
has made the following submissions:
18.1 It has been argued that the LSJ has rightly upheld the Impugned
Award, and no ground is made out for interference by this Court,
especially in exercise of its limited appellate jurisdiction under
Section 37 of the Act of 1996.
18.2 It has further been argued that the Respondent is estopped from
raising any dispute with regard to the readiness and willingness of the
Claimant to perform the Agreement at this stage. Reliance in this
regard has been placed on the unequivocal statement made by the
learned counsel for the Respondent before the LSA, which reads as
under:
(iii) Mr. Jugal Bagga, learned counsel for the Respondent at the
outset argued, that the Respondent has no objection if the award for,
specific performance of the Collaboration Agreement/MoU) dated
07.11.2011 is passed and the Respondent is directed to get the date for
completion of the construction on the plot in question extended from
the concerned Municipal authorities. This was opposed by Mr. B.R.
Sharma, Advocate for Mr. S.K. Mittal, the director of the Respondent.
Relying on the aforesaid, it has been argued that the Respondent did
not dispute the readiness and willingness of the Claimant to perform
its contractual obligations.
ANALYSIS:
19. This Court has heard the learned counsel for the parties at
considerable length and has also undertaken a thorough and
comprehensive examination of the entire appeal record, including the
FAO(OS) (COMM) 246/2023 Page 10 of 25
Impugned Judgment by the LSJ and the Impugned Award passed by
the LSA.
20. The core issue that falls for the consideration of this Court is
whether, within the narrow confines of interference permissible under
Sections 34 and 37 of the Act of 1996, the Respondent has made out
any ground to set aside the Impugned Award dated 20.11.2020, as
upheld by the Impugned Judgment of the LSJ, in so far as the Award
(i) declines the relief of specific performance of the Collaboration
Agreement dated 07.11.2011, and (ii) holds the termination of the
Agreement by the Respondent to be illegal and consequently grants
the Claimant damages in the sum of Rs. 1.65 crores along with
interest.
21. At the outset, it is pertinent to highlight that this Court, while
sitting in an appeal under Section 37 of the Act of 1996, is conscious
about the limited scope of interference that can be exercised in such
proceedings. An appeal under Section 37 of the Act of 1996, is narrow
in its compass and is confined to examining the legality of findings
rendered by the Court exercising jurisdiction under Section 34 of the
Act of 1996. The appellate jurisdiction under Section 37 of the Act of
1996 is akin to, and cannot travel beyond, the restrictions imposed
upon the Court under Section 34 of the Act of 1996; it does not confer
a general appellate power to reassess the merits of the Impugned
Award.
22. Both Sections 34 and 37 of the Act of 1996 are structured to
ensure minimal judicial interference with the Arbitral Awards, in
FAO(OS) (COMM) 246/2023 Page 11 of 25
order to preserve the time-efficient and expeditious nature of
arbitration as an alternative dispute resolution mechanism.
Consequently, the Court is precluded from re-appreciating evidence,
re-assessing factual findings, or sitting in appeal over the Arbitrator‟s
interpretation of the contract, so long as the view adopted by the
Arbitrator is a plausible one founded on the material available on
record. Interference is permissible only on the limited grounds
statutorily enumerated in Section 34 of the Act of 1996, including
where the award is in conflict with the public policy of India or is
vitiated by patent illegality going to the root of the matter, and even
then, re-appreciation of evidence is expressly impermissible.
23. The Supreme Court has consistently affirmed that a Court under
Section 34 of the Act of 1996 does not sit in appeal over an Arbitral
Award, and that an appellate court under Section 37 of the Act of
1996 has an even more circumscribed jurisdiction, being confined to
testing whether the Court acting under Section 34 of the Act of 1996
has kept its findings within the bounds of the limited statutory power
vested in it. Consequently, this Court, in the present appeal under
Section 37 of the Act of 1996, cannot undertake an independent
reassessment of the merits of the dispute, nor can it substitute its own
view for that of the Arbitrator, merely because another view is
possible.
24. The Supreme Court in the judgment of Punjab State Civil
Supplies Corpn. Ltd. v. Sanman Rice Mills
2
, contemplated upon the
limited and supervisory nature of an appeal under Section 37 and has
2
2024 SCC OnLine SC 2632
FAO(OS) (COMM) 246/2023 Page 12 of 25
observed that:
“11. Section 37 of the Act provides for a forum of appeal inter-alia
against the order setting aside or refusing to set aside an arbitral
award under Section 34 of the Act. The scope of appeal is naturally
akin to and limited to the grounds enumerated under Section 34 of the
Act.
12. It is pertinent to note that an arbitral award is not liable to be
interfered with only on the ground that the award is illegal or is
erroneous in law that too upon reappraisal of the evidence adduced
before the arbitral trial. Even an award which may not be reasonable
or is non-speaking to some extent cannot ordinarily be interfered with
by the courts. It is also well settled that even if two views are possible
there is no scope for the court to reappraise the evidence and to take
the different view other than that has been taken by the arbitrator. The
view taken by the arbitrator is normally acceptable and ought to be
allowed to prevail.
13. In paragraph 11 of Bharat Coking Coal Ltd. v. L.K. Ahuja, it has
been observed as under:
“11. There are limitations upon the scope of interference in
awards passed by an arbitrator. When the arbitrator has
applied his mind to the pleadings, the evidence adduced before
him and the terms of the contract, there is no scope for the
court to reappraise the matter as if this were an appeal and
even if two views are possible, the view taken by the arbitrator
would prevail. So long as an award made by an arbitrator can
be said to be one by a reasonable person no interference is
called for. However, in cases where an arbitrator exceeds the
terms of the agreement or passes an award in the absence of
any evidence, which is apparent on the face of the award, the
same could be set aside.”
14. It is equally well settled that the appellate power under Section 37
of the Act is not akin to the normal appellate jurisdiction vested in the
civil courts for the reason that the scope of interference of the courts
with arbitral proceedings or award is very limited, confined to the
ambit of Section 34 of the Act only and even that power cannot be
exercised in a casual and a cavalier manner.
15. In Dyna Technology Private Limited v. Crompton Greaves
Limited, the court observed as under:
“24. There is no dispute that Section 34 of the Arbitration Act
limits a challenge to an award only on the grounds provided
therein or as interpreted by various courts. We need to be
cognizant of the fact that arbitral awards should not be
interfered with in a casual and cavalier manner, unless the
court comes to a conclusion that the perversity of the award
goes to the root of the matter without there being a possibility
FAO(OS) (COMM) 246/2023 Page 13 of 25
of alternative interpretation which may sustain the arbitral
award. Section 34 is different in its approach and cannot be
equated with a normal appellate jurisdiction. The mandate
under Section 34 is to respect the finality of the arbitral award
and the party autonomy to get their dispute adjudicated by an
alternative forum as provided under the law. If the courts were
to interfere with the arbitral award in the usual course on
factual aspects, then the commercial wisdom behind opting for
alternate dispute resolution would stand frustrated. 25.
Moreover, umpteen number of judgments of this Court have
categorically held that the courts should not interfere with an
award merely because an alternative view on facts and
interpretation of contract exists. The courts need to be cautious
and should defer to the view taken by the Arbitral Tribunal even
if the reasoning provided in the award is implied unless such
award portrays perversity unpardonable under Section 34 of
the Arbitration Act.”
16. It is seen that the scope of interference in an appeal under Section
37 of the Act is restricted and subject to the same grounds on which
an award can be challenged under Section 34 of the Act. In other
words, the powers under Section 37 vested in the court of appeal are
not beyond the scope of interference provided under Section 34 of the
Act.
17. In paragraph 14 of MMTC Limited v. Vedanta Limited, it has
been held as under:
“14. As far as interference with an order made under Section
34, as per Section 37, is concerned, it cannot be disputed that
such interference under Section 37 cannot travel beyond the
restrictions laid down under Section 34. In other words, the
court cannot undertake an independent assessment of the merits
of the award, and must only ascertain that the exercise of power
by the court under Section 34 has not exceeded the scope of the
provision. Thus, it is evident that in case an arbitral award has
been confirmed by the court under Section 34 and by the court
in an appeal under Section 37, this Court must be extremely
cautious and slow to disturb such concurrent findings.”
18. Recently a three-Judge Bench in Konkan Railway Corporation
Limited v. Chenab Bridge Project Undertaking referring to MMTC
Limited (supra) held that the scope of jurisdiction under Section 34
and Section 37 of the Act is not like a normal appellate jurisdiction
and the courts should not interfere with the arbitral award lightly in a
casual and a cavalier manner. The mere possibility of an alternative
view on facts or interpretation of the contract does not entitle the
courts to reverse the findings of the arbitral tribunal.
CONCLUSION:
20. In view of the above position in law on the subject, the scope of the
intervention of the court in arbitral matters is virtually prohibited, if
FAO(OS) (COMM) 246/2023 Page 14 of 25
not absolutely barred and that the interference is confined only to the
extent envisaged under Section 34 of the Act. The appellate power of
Section 37 of the Act is limited within the domain of Section 34 of the
Act. It is exercisable only to find out if the court, exercising power
under Section 34 of the Act, has acted within its limits as prescribed
thereunder or has exceeded or failed to exercise the power so
conferred. The Appellate Court has no authority of law to consider the
matter in dispute before the arbitral tribunal on merits so as to find
out as to whether the decision of the arbitral tribunal is right or
wrong upon reappraisal of evidence as if it is sitting in an ordinary
court of appeal. It is only where the court exercising power under
Section 34 has failed to exercise its jurisdiction vested in it by Section
34 or has travelled beyond its jurisdiction that the appellate court can
step in and set aside the order passed under Section 34 of the Act. Its
power is more akin to that superintendence as is vested in civil courts
while exercising revisionary powers. The arbitral award is not liable
to be interfered unless a case for interference as set out in the earlier
part of the decision, is made out. It cannot be disturbed only for the
reason that instead of the view taken by the arbitral tribunal, the other
view which is also a possible view is a better view according to the
appellate court.
21. It must also be remembered that proceedings under Section 34 of
the Act are summary in nature and are not like a full-fledged regular
civil suit. Therefore, the scope of Section 37 of the Act is much more
summary in nature and not like an ordinary civil appeal. The award
as such cannot be touched unless it is contrary to the substantive
provision of law; any provision of the Act or the terms of the
agreement.”
(emphasis supplied)
25. It is in this backdrop that we now proceed to examine the
arguments advanced by the Respondent in the present Appeal, thereby
questioning the evaluation of readiness and willingness by the LSA,
and his assessment of damages.
26. It has been argued by the learned counsel for the Respondent
that the LSA failed to frame issues with respect to the readiness and
willingness of the Claimant to perform its obligations. However, a
holistic reading of the Impugned Award, particularly the segment
styled as “CONCLUSION (I)–(VII)”, makes it evident that the prayers
FAO(OS) (COMM) 246/2023 Page 15 of 25
and claims articulated in the statement of claim were themselves
treated as the central questions for determination.
27. The Impugned Judgment correctly records that the LSA, in
substance, addressed whether specific performance of the Agreement
dated 07.11.2011 ought to be granted (Conclusion I); whether the
Agreement attracted compulsory registration under Section 17(2)(v)
of the Registration Act, 1908 (Conclusion II); whether the Agreement
constituted a concluded and enforceable contract (Conclusion III);
whether the termination vide letter dated 22.03.2014 was legal and
justified (Conclusions IV and V); and whether, in consequence, the
Claimant was entitled to damages and interest, and in what quantum
(Conclusion VI).
28. A reference is also to be made to the prayers of the Claimant
through which, it sought for specific performance, for a declaration as
to the validity and enforceability of the Agreement, and, in the
alternative, for damages with interest. The said prayer thus stood
adopted as the real issues in controversy and was answered through
reasoned conclusions. In these circumstances, the mere absence of a
separately numbered “issue” on readiness and willingness or on
damages cannot be elevated to a violation of natural justice or to a
ground seeking interference under Section 34 of the Act of 1996, so
long as the underlying controversies were factually and legally
addressed with reasons, which they indisputably were.
29. Turning now to the effect of rejection of specific performance on
the entitlement to damages, the LSA declined the discretionary relief
FAO(OS) (COMM) 246/2023 Page 16 of 25
of specific performance after a close scrutiny of the contractual terms,
the nature and duration of the construction obligations, and the
necessity of continuous supervision over quality, materials, timelines
and allied aspects. Taking the aforesaid into consideration, it was
concluded that the Agreement fell within the class of contracts
involving performance of continuous duties which a court or tribunal
cannot effectively supervise, as contemplated by Section 14 (c) of the
Act of 1963.
30. Notably, the aforesaid conclusion was not reached in vacuo by
the LSA, on the contrary while reaching to such conclusion, he took
into account the pleadings of both parties, their conduct including the
settlement recorded on 18.09.2017, and the nature of the obligations
under the Agreement, which envisaged construction of a multi-storey
project over 18 months with ongoing design, quality and construction
supervision. The LSJ rightly held that this was, at the very least, a
plausible view on the application of Section 14 of the Act of 1963 to
the facts and the contract and hence lay beyond the narrow zone of
interference under Section 34 of the Act of 1996.
31. It is pertinent to highlight that once specific performance was
declined, the residual inquiry, as correctly recognised by both the LSA
and LSJ, was whether either party had committed breach of the
contract and, if so, whether the innocent party was entitled to
monetary compensation. The Impugned Award, as accurately
summarised in the Impugned Judgment, records clear findings that the
Agreement was a concluded and enforceable collaboration agreement;
and the plea of the Agreement being pending for want of financial or
FAO(OS) (COMM) 246/2023 Page 17 of 25
experience documents along with an alleged settlement with a former
director by return of the original Agreement and Rs. 50 lakhs were
unsupported by cogent evidence as such stood rejected; and that the
termination vide letter dated 22.03.2014 was illegal and unsustainable
in law, entitling the Claimant to recover damages for the losses
suffered.
32. In this regard, a reference is also made to the discussion of the
LSA in the Impugned Award with respect to the wrongful and illegal
termination of the Agreement on account of the Respondent, thereby
acting in violation of the agreed terms of the Agreement, which is set
out hereinafter. Undisputedly, the parties entered into the Agreement
on 07.11.2011, after which the Respondent failed to perform its
obligations stipulated under Clause (v)(c) of the Agreement, which
required the Respondent to apply and attain the building sanction plan
within a period of 60 days from the date of signing of the Agreement.
Relying upon the SDMC letter dated 24.01.2013, sanctioning the
building plans, it was noted that the said letter was given in response
to the application of the Respondent on 29.06.2012. In the view of the
turn of events as mentioned, it is evident that the Respondent applied
for the building sanction after a substantial delay of approximately
175 days, much beyond the prescribed period.
33. It also bears importance to note that the Respondent failed to
prove the effective steps which were taken by it to set out the building
plan approved after entering into the Agreement on receipt of Rs. 50
Lakhs. As already noted, in accordance with the Agreement, the first
step was to be taken by the Respondent to set out the building sanction
FAO(OS) (COMM) 246/2023 Page 18 of 25
plan approved, however, the Respondent miserably failed to lead
cogent evidence substantially proving its bona fide in attaining the
building plans after a substantial delay.
34. These findings squarely attract the general remedial rule in
Sections 73 and 74 of the Indian Contract Act, 1872, under which a
party who suffers loss by reason of the other‟s breach is entitled to
compensation for the loss naturally arising in the usual course of
things from such breach, subject to any contractual stipulation. The
LSJ has expressly endorsed this approach, noting that there is neither
any legal nor any contractual bar to the grant of monetary
compensation once the owner‟s (Respondent‟s) breach stood
established. The contention of the Respondent that the LSA, having
refused specific performance, was thereafter precluded from awarding
damages is not only contrary to the basic remedial structure of
contract law, but, more significantly, amounts to an attack on the
merits of the arbitral determination and not on any recognised ground
under Section 34(2) or 34(2A) of the Act of 1996. Within the settled
jurisprudence on Sections 34 and 37 of the Act of 1996, such an
argument is plainly inadmissible.
35. The contractual argument based on Clause (v)(d) of the
Agreement is also devoid of merit. The Respondent invoked the said
clause to contend that the Agreement envisaged a penalty or forfeiture
only against the builder (Claimant) in the event of delayed payments
and imposed no reciprocal liability on the owner to pay damages,
thereby rendering the award of damages contrary to the bargain. This
submission was advanced before the LSJ, who noted the contention
FAO(OS) (COMM) 246/2023 Page 19 of 25
that the Agreement did not contemplate any penalty or damages
payable by the owner, and that Clause (v)(d) of the Agreement
stipulated only a penalty upon the builder. However, the LSJ rejected
this “contractual bar” theory, holding that the Agreement, when
properly read, contained no prohibition against damages being
awarded in favour of the Claimant once the owner‟s breach was
found, and that the contrary reading propounded by the Respondent
rested on a convoluted and strained construction of the clause.
36. Whether Clause (v)(d) of the Agreement operates as a one-sided
stipulated consequence or is but one facet of a broader risk-allocation
within the collaboration framework is quintessentially a matter of
contractual interpretation, committed primarily to the Arbitral
Tribunal. As repeatedly emphasised by the Supreme Court,
construction of contractual terms is a subject matter of adjudication by
the Arbitrator, and a court exercising jurisdiction under Sections 34
and 37 of the Act of 1996, cannot supplant a reasonably possible view
with what it may regard as a more attractive interpretation. In the
absence of any demonstration that the LSA‟s view was perverse,
irrational, or wholly unmoored from the text and scheme of the
Agreement, the challenge founded upon Clause (v)(d) of the
Agreement cannot succeed in an appeal filed under Section 37 of the
Act of 1996.
37. With respect to readiness and willingness and the effect of the
parties‟ conduct and the subsequent settlement, the Respondent has
contended that the Claimant failed to establish continuous readiness
and willingness within the meaning of Section 16(c) of the Act of
FAO(OS) (COMM) 246/2023 Page 20 of 25
1963, and that there was a categorical admission in cross-examination,
in answer to Question 17, suggesting that the Claimant was willing to
perform only subject to price revision. These very points were urged
before the LSJ, who expressly noticed the reliance on the said
cross-examination. Nevertheless, it was held that the LSA‟s
conclusions on specific performance and liability were not founded on
a truncated reading of one answer in cross-examination, but on a
composite evaluation of the pleadings of both parties, their conduct,
especially the settlement recorded on 18.09.2017 and the nature and
structure of the Agreement. Further it was held that, a selective
emphasis on an isolated answer in cross-examination, cannot dislodge
a reasoned conclusion derived from the entire factual conspectus.
38. The LSA had, in particular, recorded that during the arbitral
proceedings the Respondent settled the matter and agreed to pay Rs.
1.65 crores towards full and final settlement, with the directors of the
Claimant-company individually assenting to those terms on oath,
although they subsequently failed to procure a Board resolution.
39. Further, the Claimant has drawn attention to the statement made
by the Respondent‟s counsel before the LSA that the owner had no
objection to an award of specific performance and would secure
requisite extensions of time from the municipal authorities. This
conduct, read with the settlement terms and the directors‟ sworn
statements, substantially undermines the Respondent‟s present
contention that the Claimant was not ready and willing. As such both
the LSA and the LSJ were entitled to regard the Respondent‟s own
conduct and its positions at the time of arbitration proceedings as
FAO(OS) (COMM) 246/2023 Page 21 of 25
highly material to the equities governing specific performance and to
the assessment of damages. Such evaluation is inherently
fact-intensive and falls squarely within the forbidden territory of
factual re-appreciation, which a court under Section 37 of the Act of
1996 cannot traverse.
40. As to the basis and quantum of damages, and the role played by
the 18.09.2017 settlement, the Impugned Award, as summarised in the
Impugned Judgment, makes it clear that after holding the termination
illegal and the Agreement to be concluded and enforceable, the LSA
turned to the Claimant‟s alternative claim for damages. He recorded
that on 18.09.2017 the parties had informed him that the disputes
stood fully and finally settled; that the directors of the owner-company
confirmed the settlement terms on oath; and that a consent award
could not be passed solely because the owner failed to place on record
a Board resolution authorising the compromise, owing to inter se
disputes among its directors.
41. Thereafter, the LSA treated the agreed figure of Rs. 1.65 crores
as the best available evidence for quantifying the Claimant‟s loss,
noting that both sides had contemporaneously accepted that figure as a
fair monetary resolution of the fallout of the Agreement and its
breach. Proceeding on this basis, the LSA awarded Rs. 1.65 crores
with pre-award interest at 12% per annum from 30.12.2017 (the outer
date stipulated for payment under the settlement) till the date of the
award, and post-award interest at the same rate till realisation. The
Impugned Judgment further notes that even during the arbitral
proceedings neither party disputed the quantum of damages or the rate
FAO(OS) (COMM) 246/2023 Page 22 of 25
of interest that had been agreed in the settlement, thereby reinforcing
the LSA‟s reliance on the figure as embodying the parties‟ own
assessment of fair compensation.
42. In doctrinal terms, Section 30 of the Act of 1996 expressly
empowers an arbitral tribunal to encourage settlement of the dispute
and, where the parties settle, to record the settlement in the form of an
award on agreed terms. However, the making of such an award is
predicated on the existence of valid authority and compliance with any
internal authorisation requirements, particularly in the case of
companies, much in the same way as Order XXIII Rule 3 of the Code
of Civil Procedure, 1908 [hereinafter referred to as „CPC‟] insists that
a lawful compromise must be in writing and signed or otherwise
validly assented to by authorised persons before a court can pass a
compromise decree.
43. In the present case, the LSA quite correctly declined to pass a
consent award under Section 30 of the Act of 1996 once it transpired
that the owner-company could not produce a Board resolution,
notwithstanding its directors having individually affirmed the
settlement and its counsel having recorded the compromise. This
approach is consonant with the cautionary requirements analogous to
those embodied in Order XXIII Rule 3 of the CPC. At the same time,
neither Order XXIII Rule 3 of the CPC nor any provision of the Act of
1963 forbids an adjudicatory forum from treating an unperfected or
formally defective settlement as a piece of evidence reflecting the
parties‟ own contemporaneous valuation of their respective rights and
liabilities.
FAO(OS) (COMM) 246/2023 Page 23 of 25
44. In the present case, the LSA did no more than adopt this
evidentiary use, he refused to confer the status of a consent award on
the 18.09.2017 settlement for want of proper corporate authority but
treated the mutually agreed sum of Rs.1.65 crores, coupled with the
absence of any subsequent dispute as to quantum, as the best indicator
of reasonable compensation for the wrongful termination. The legality
of this approach lies squarely within the domain of appreciation of
evidence; it does not offend any statutory or contractual prohibition
and hence cannot be impugned under Sections 34 or 37 of the Act of
1996.
45. Therefore, on an overall conspectus, no ground of patent
illegality or conflict with public policy, as understood in Section 34(2)
and (2A) of the Act of 1996 is made out. The Respondent‟s challenge,
both before the LSJ and in this appeal, is ultimately founded upon, an
invitation to re-weigh the evidence regarding readiness and
willingness, with undue emphasis on a single cross-examination
answer; a plea for a different construction of Clause (v)(d) of the
Agreement and of the contractual allocation of risk; and a grievance
about the absence of a separately formulated issue on readiness and
willingness.
46. The aforesaid grounds invoked for seeking interference of this
Court, even if taken at their highest, go only to the merits of the
Impugned Award without delineating any excess or failure of
jurisdiction by the LSA. Additionally, such contentions do not
disclose any breach of audi alteram partem or of the principles of
natural justice; hence, do not reveal any patent illegality going to the
FAO(OS) (COMM) 246/2023 Page 24 of 25
root of the matter in the sense elucidated by the Supreme Court, as
opposed to a mere error of law or fact.
47. Both the Impugned Award and the Impugned Judgment contain
reasoned findings on each substantial question, specific performance,
the nature and enforceability of the Agreement, the legality of
termination, and the entitlement and quantum of damages, grounded
in the pleadings, correspondences including the letters dated
22.03.2014 and 14.07.2014, the parties‟ conduct, and the settlement
recorded on 18.09.2017, and informed by the correct tests governing
interference with Arbitral Awards under Sections 34 and 37 of the Act
of 1996.
48. The submissions advanced on behalf of the Respondent, when
examined in entirety, essentially seek a re-appreciation of evidence
and reconsideration of factual and contractual findings returned by the
LSA. Such an exercise is clearly impermissible within the limited
scope of appellate scrutiny under Section 37 of the Act of 1996,
particularly when both the LSA and the LSJ have concurrently
rejected the claims after due consideration.
49. In these circumstances, this Court is of the considered view that
the Impugned Award does not suffer from perversity, patent illegality,
or violation of the fundamental policy of Indian law. The approach
adopted by the LSA is neither arbitrary nor unreasonable, and the LSJ
has rightly declined to interfere with the same.
50. Hence, no interference, is called, for keeping in view the limited
scope of interference against the Impugned Award and the concurrent
FAO(OS) (COMM) 246/2023 Page 25 of 25
findings recorded by the LSA and affirmed by the LSJ.
CONCLUSION:
51. In view of the foregoing discussion and findings, this Court
finds no infirmity in the Arbitral Award dated 20.11.2020 or in the
Impugned Judgment passed by the learned Single Judge. The
Appellant has failed to demonstrate any ground warranting
interference by this Court in exercise of its appellate jurisdiction under
Section 37 of the Act of 1996.
52. The present Appeal, being devoid of merit, is accordingly
dismissed.
ANIL KSHETARPAL , J.
AMIT MAHAJAN , J.
FEBRUARY 16, 2026
jai/hr
Legal Notes
Add a Note....