As per case facts, the Petitioner challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The Respondent had placed a purchase order for switches on ...
O.M.P. (COMM) 249/2023 Page 1 of 15
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 19 January 2026
Judgment pronounced on: 2/2/26
+ O.M.P. (COMM) 249/2023 & I.A. 14284/2025
ZREYAH SEMICONDUCTORS PVT. LTD. .....Petitioner
Through: Mr. Ashish Dholakia, Sr. Adv.
with Mr. Gautam Bajaj, Mr.
Akash Panwar, Ms. Meghna
Jandu, Mr. Lakshay Nagpal &
Ms. Saumya, Advs.
versus
OYO HOTELS AND HOMES PVT. LTD. .....Respondent
Through: Mr. Sumant Nayak, Mr. Ankit
Premchandani & Ms. Smriti
Shukla, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. M/s Zreyah Semiconductors Private Limited has filed the
petition under Section 34 of the Arbitration and Conciliation Act,
1996 (for short „the Act‟) aggrieved of the arbitral award dated
03.04.2023.
FACTS
2. The brief facts are that the petitioner is engaged in the business
of manufacturing and supply of electronic components. The
respondent is a Private Limited Company engaged in the business of
managing hospitality establishments. The respondent placed a
O.M.P. (COMM) 249/2023 Page 2 of 15
purchase order dated 26.09.2019 upon the petitioner (hereinafter „the
PO‟) for supply of 52360 switches valuing Rs.10,34,89,540/-,
inclusive of taxes. Subsequent to the placement of the PO, the parties
entered into a vendor agreement dated 23.12.2019 (hereinafter „the
VA‟). The PO though prior in time was governed by the terms and
conditions of the VA. After the placement of the PO the respondent
paid an advance of fifty percent of the invoice value.
2.1 Prior to the placing of the PO, the parties had business
transactions wherein the petitioner was assembling switches for the
respondent and the entire material was being supplied by the
respondent. The scenario changed and pursuant to the PO the
petitioner had to procure the components for the switches and five
major components were to be procured from vendors specified by the
respondent in Schedule „A‟ to the VA.
2.2 A dispute arose between the parties due to non-delivery of the
switches and arbitration proceedings as provided under the VA were
initiated at the instance of the respondent. The arbitrator framed the
following issues:
(i) Whether the respondent has committed the breach of the Vender
Agreement dated 23.12.2019? If so, its effect.
(ii) Whether the respondent has committed the breach of the P.O.s
dated 26.09.2019 and 22.09.2020? If so, its effect.
(iii) Whether the claimant is entitled to the reliefs as claimed in the
SOC?
2.3 The arbitrator after considering the pleadings and appreciating
the evidence adduced directed the petitioner to deliver 11000 switches
O.M.P. (COMM) 249/2023 Page 3 of 15
claimed to be ready and to pay Rs.2,84,00,000/- along with interest at
the rate of nine percent per annum.
CONTENTIONS
3. Learned counsel for the petitioner relies upon clauses 2.1, 2.3
and 3.1 of the VA to contend that the petitioner was an assembler and
not a manufacturer, the arbitrator erred in holding that the petitioner
was a manufacturer. Reliance is placed upon the correspondence
between the parties to show that the terms and conditions of the
Chinese vendors (hereinafter „the vendors‟) were provided by the
respondent to the petitioner. It is submitted that clause 12.1 of the VA
relied upon by the arbitrator deals with liability of petitioner towards
employees and not with the nature of relationship between the parties
and it was wrongly recorded that there was a principal to principal
relationship between the parties.
3.1 It is argued that the arbitrator relying on clause 14.10 concluded
that all prior discussions, negotiations and agreements were
superseded by the VA, if this is taken to its logical end the PO no
longer existed and consequently no liability could be casted upon the
petitioner.
3.2 The averment is that some of the components were to be
procured from the vendors identified by the respondent and the
advance amount was to be paid by the respondent for these
procurements. On failure of the respondent to make hundred percent
advance payment the components could not be procured and the
switches were not supplied. It is stated that there was no fault on the
part of the petitioner and the fifty percent advance paid by the
O.M.P. (COMM) 249/2023 Page 4 of 15
respondent was utilised for procuring components from which 11000
switches were made. Reliance is placed upon the cross-examination of
CW-1 Nikhil Ranjan to fortify the contention that prior to the PO the
advance payments were made to the vendors.
3.3 The plea is that the delay in supply was not attributable to the
petitioner. The revised purchase order for 11000 switches was a
unilateral action of the respondent and was not issued at the request of
the petitioner. Rather the petitioner refused to accept the revised
purchase order on the existing terms and conditions.
4. Per contra the interpretation of the arbitrator of the terms of the
contract is plausible and a possible second view cannot be a ground
for interference under Section 34 of the Act. It is admitted that the
petitioner was an assembler and not a manufacturer but had to procure
the components.
4.1 The plea taken is that the VA superseded all prior discussions,
negotiations, agreements and there was no clause for payment of
hundred percent advance to the petitioner. Further that payment of
fifty percent advance was merely a goodwill gesture. The cross-
examination of RW-4 Rajesh V.K. is relied upon to submit that no
advance was to be paid yet the respondent paid fifty percent advance.
RW-1 Sujan Nailady admitted in cross-examination that the advance
payment to the vendors was to be made by the petitioner.
4.2 The email dated 20.10.2020 is relied upon to substantiate that
the petitioner failed to supply 52360 switches and that the revised
purchase order was issued at the request of the petitioner.
4.3 Lastly it is submitted that the petitioner failed to comply with
O.M.P. (COMM) 249/2023 Page 5 of 15
the PO for more than one year and three months and thereafter the
termination notice was issued on 06.01.2021.
5. Heard learned counsel for the parties at length and perused the
record with their able assistance.
ISSUE
6. The main controversy involved is as to whether the respondent
had to pay hundred percent advance to the petitioner for procurement
of components.
CLAUSES OF VENDOR AGREEMENT
7. The relevant clauses of the VA are reproduced below:
“H. Based on the representations made by the Vendor, the
Client is desirous of purchasing the Products from the
Vendor on the terms and conditions set out in this
Agreement.
xxx xxx xxx
2. AGREEMENT TO SELL
2.1 The Vendor agrees to sell such number of Products as
detailed in Schedule-A and the Client agrees to purchase
the Products, as may be specified in one or more purchase
orders issued by the Client to Vendor in accordance with
this Agreement.
xxx xxx xxx
2.3 The Vendor agrees to purchase the 5 (five) major
components for assembling of the Product from the
supplier identified by the Client. The Vendor will
assemble all the components and supply the product as
detailed in Schedule A to this agreement.
xxx xxx xxx
3.2 Delivery and Delays: Unless, otherwise agreed in
writing by the Parties, the Products shall be delivered at
the place set out in the Purchase Order. The delivery date
O.M.P. (COMM) 249/2023 Page 6 of 15
stated in the Purchase Order shall be the agreed delivery
date ("Agreed Delivery Date") and time for delivery shall
be of the essence, unless Vendor notifies the Client in
writing within 5 (five) days of issuance of a Purchase
Order that it cannot, using best efforts, meet the delivery
date specified in the Purchase Order. In the event that
Vendor is unable to meet the delivery conditions under
the Purchase Order, the Client may, without prejudice to
its rights for refund of the amounts paid and at its sole
option, (a) negotiate in good faith for an alternative
Agreed Delivery Date, or (b) may cancel the Purchase
Order(c)Procure the Products in from a third Party, costs
of which shall be borne by the Vendor on account of non
performance of obligations.
xxx xxx xxx
3.4 Defects and Returns: The Client will be liable to
accept the Products only if the Products comply fully
with the specifications set out by the Client and with
other requirements of this Agreement. The Client shall
notify the Vendor in writing within 15 (Fifteen) business
days following the receipt by the Client of such Products
of any deficiencies in the Products, including any defects
in the Products or of any failure of the Product to comply
with the required specifications in the Purchase Order and
the Agreement. Where the Client provides such notice to
the Vendor, the Vendor shall rectify such deficiencies in
the Products within 10 (ten) days from the date of receipt
of such notice and if the Vendor fails to rectify such
deficiencies, the Client shall be entitled to return the
Products and obtain full refund from the Vendor for the
same if this is attributable to the assembling of the
product or on the component procured from the Vendor's
direct source. If the product is deficient due to the failure
of the components supplied by the Supplier identified by
the Client then the refund will be based on the back to
back refund from that Supplier. The Parties in accordance
with this Agreement shall mutually resolve any
disagreement relating to the defici encies.
O.M.P. (COMM) 249/2023 Page 7 of 15
Notwithstanding anything to the contrary, failure by the
Client to give notice of or particularize the Deficiencies
within the Inspection Period shall not constitute the
Client‟s acceptance of the Products.
xxx xxx xxx
4. PAYMENT TERMS
4.1 For the Products purchased under this Agreement, the
Vendor shall raise invoices on the Client for the amounts
specified in the Purchase Orders executed between the
Parties from time to time and in accordance with the
terms of this Agreement and the relevant Purchase Order.
Subject to Clause 3.2 below, all undisputed invoices shall
be paid by the Client within thirty (30) working days of
the receipt of the undisputed invoice. In case of any delay
then the Client agrees to pay @2% (two percent) for
every week of delay. All invoices shall be mandatorily
submitted to the Client in hard copy. The Client may,
without limiting any other rights and remedies that it may
have under applicable law, contract and equity, set off
any amounts owed to it by the Vendor against either the
amount payable to Vendor by the Client under the subject
Purchase Order, or against any other invoice raised under
any future. Purchase Orders with Vendor, at the Client‟s
discretion. The Client may ask Vendor to submit
necessary documentary proof in order to make the
payment of the invoices. If Vendor fails to fulfil its
obligations under this Agreement and the relevant
Purchase Order, the Vendor may be liable to pay damages
to the Client amounting to up to 2% (two percent) per
week of the latest invoice raised under this Agreement for
such delay, in addition to other remedies available to the
Client. Such damages shall be deducted in accordance
with this Clause.
4.2 If the Client disputes an invoice raised by the Vendor,
it may withhold any disputed sum until the dispute is
resolved, but shall pay the undisputed portion as per the
terms of this Agreement. The Vendor shall not be
O.M.P. (COMM) 249/2023 Page 8 of 15
excused from performing its obligations under this
Agreement while an invoice is disputed by the Client.
xxx xxx xxx
4.4 The Vendor shall raise an invoice for supply of the
Products purchased under the relevant Purchase Order as
per invoice rules applicable under GST Laws after
appropriate communication of acceptance on the Products
is given by the Client to the Vendor. However, in case of
continuous supply or provision of Products/ Services, the
invoices shall be raised at the end of the agreed payment
cycle as per the terms of this Agreement. In addition to
the above, if any advance payments apply under this
Agreement, Vendor shall issue an advance receipt note
(''ARN").”
ANALYSIS
8. From perusal of the VA, it emerges that the respondent on the
basis of the representations made by the petitioner desired to purchase
products. The petitioner agreed to sell the products detailed in
Schedule „A‟ and in accordance with the terms of the VA. The
petitioner agreed to procure five major components from the vendors
identified by the respondent.
8.1 As per clause 3.2, the delivery date of the PO was to be agreed
and the time for delivery was of the essence. The petitioner was
entitled within five days of issuance of the PO to notify the respondent
that the delivery date cannot be met. In such circumstances, the
respondent without prejudice to the right to seek refund of the amount
could negotiate for an alternative delivery date, cancel the PO or
procure the product from a third party and the cost was to be borne by
the petitioner.
O.M.P. (COMM) 249/2023 Page 9 of 15
8.2 Clause 3.4 deals with defects and return of the goods. It states
that acceptance of the goods by the respondent was subject to
compliance of the products with the specifications prescribed. The
respondent shall notify the deficiencies in the products within fifteen
days of receipt of the goods. The petitioner had to rectify the
deficiencies within ten days of receipt of notice. Failure on the part of
the petitioner to remove the defects entitled the respondent to return
the product and seek refund in case deficiencies were attributable to
assembly or to products directly procured by the petitioner from direct
sources. In case of defect in a component procured by the petitioner
from the vendors identified by the respondent, the refund was based
on a back-to-back refund from the vendors. Failure of the respondent
to notify the deficiencies within fifteen days of receipt of the goods
shall be treated to be acceptance of the product.
8.3 Clause 4 deals with the payment terms. The petitioner subject to
clause 3.2 had to raise invoices for the amounts specified in the PO.
The payment of undisputed invoices was to be made by the
respondent within thirty working days of receipt of the invoices.
Clause 4.4 provides that the invoice for the PO shall be issued after
communication of acceptance of the products by the respondent.
9. The only possible interpretation of the VA is that payment was
to be made by the respondent to the petitioner after acceptance of the
goods. The respondent had to point out deficiencies in the products
within fifteen days of receipt of goods and thereafter the petitioner had
to rectify the defects within ten days. Failure of the respondent to
particularise the deficiencies within a period of fifteen days of receipt
O.M.P. (COMM) 249/2023 Page 10 of 15
of the goods would be deemed to be acceptance of the products. It is
not disputed that in the case in hand no products were supplied.
10. In view of the undisputed fact that the petitioner had to procure
components and make switches, the issue as to whether the petitioner
was a manufacturer or an assembler and whether there was principal
to principal relationship between the parties or not loses relevance.
11. The petitioner set up a case that prior to the PO hundred percent
advance was being paid by the respondent and the VA would not
affect the PO placed prior in time. None of the parties raised an issue
that clauses of the VA were not applicable to the PO rather for
resolving the dispute submitted to arbitration in consonance with
clause 13.1 of the VA. The arbitrator rightly concluded that there was
no clause for payment of hundred percent advance payment by the
respondent. Moreover, earlier all components were being supplied by
the respondent but now for the PO the components were to be
procured by the petitioner with the condition that five components
were to be procured from vendors specified by the respondent.
12. Be that as it may the petitioner failed to substantiate that even
under the PO there was a term or condition providing for payment of
hundred percent advance to the petitioner for procurement of
components. The finding recorded by the arbitrator suffers from no
factual or legal error much less perversity.
13. The emails dated 25.07.2019 and 28.10.2019 sent by the
respondent mentioning the terms and conditions between the vendor
and the respondent and instructing the petitioner to proceed with
procurement of the components as the advance had been paid, does
O.M.P. (COMM) 249/2023 Page 11 of 15
not come to the rescue to take home the claim that the respondent had
to make hundred percent advance payment.
14. It is not the case of the petitioner that 52360 switches were
ready or the petitioner was in a position to comply with the PO, rather
the non-payment of hundred percent advance by the respondent is
stated to be the reason for non compliance of PO. Vide email dated
13.08.2020 the petitioner requested the respondent to pick up the
inventory procured for the manufacture of switches which was lying
in its stores. There is no mention in the email that the switches as per
the PO were ready for delivery.
15. The argument that in view of the clause 14.10, if all prior
discussions, negotiations and agreements have come to an end then the
PO does not survive, lacks merit. Clause 14.10 is reproduced below:
“14.10 Entire Agreement. This Agreement and the
schedules hereto shall constitute the entire and final
statement of the Agreement between the Parties with
respect to the subject matter hereof and supersedes all
prior and contemporaneous discussions, communications,
negotiations and agreements, written or oral, with respect
to the subject matter hereof.”
From the reading of the clause it is evident that it does not cancel the
purchase orders placed earlier but settle the terms and conditions for
supply of material.
16. The challenge to the findings of the arbitrator that the products
were not to be procured from the identified vendors and that no
advance was to be given to the petitioner, lacks merit. The
identification of the vendors for procurement of five components does
not lead to the conclusion that hundred percent advance was to be paid
O.M.P. (COMM) 249/2023 Page 12 of 15
by the respondent. In cross-examination, the CW-1 Nikhil Ranjan
stated that the respondent while procuring the components used to
make advance payments to the vendors, it was admitted that the
petitioner was aware that advance payment was to be made to the
vendors. There is no deposition by the witness that the hundred
percent advance payment was to be paid by the respondent.
17. The issue as to whether the revised purchase order for 11000
switches was a unilateral decision of the respondent or was issued at
the request of the petitioner need not be dilated upon. The dispute
referred to the arbitrator arose out of the termination of the PO and for
refund of fifty percent advance paid to the petitioner.
18. It cannot be lost sight of that the 11000 switches claimed by the
petitioner to be ready were directed by the arbitrator to be supplied to
the respondent and while allowing the claim proportionate deduction
of value of 11000 switches was made in the award.
SCOPE UNDER SECTION 34 OF THE ACT
19. It is trite law that upon re-appreciation of evidence a possible
second view cannot be a ground for interference under Section 34 of
the Act unless the conclusion arrived at is perverse. The interpretation
of the terms of the contract by the arbitrator in normal course is not to
be interfered with. Reliance in this regard be placed on the following
decisions of the Supreme Court:
19.1 In Prakash Atlanta (JV) v. National Highways Authority of
India 2026 INSC 76 held as under:-
“59. (vi) If an arbitral tribunal‟s view is found to be a
possible and plausible one, it cannot be substituted
O.M.P. (COMM) 249/2023 Page 13 of 15
merely because an alternate view is possible.
Construction and interpretation of a contract and its terms
is a matter for the arbitral tribunal to determine. Unless
the same is found to be one that no fair-minded or
reasonable person would arrive at, it cannot be interfered
with. If there are two plausible interpretations of the
terms of a contract, then no fault can be found if the
arbitrator accepts one such interpretation as against the
other. To be in conflict with the public policy of India,
the award must contravene the fundamental policy of
Indian law, which makes it narrower in its application.”
19.2 In Ramesh Kumar Jain v. Bharat Aluminium Company
Limited (BALCO) 2025 INSC 1457 held as under:-
“28. The bare perusal of section 34 mandates a narrow
lens of supervisory jurisdiction to set aside the arbitral
award strictly on the grounds and parameters enumerated
in sub-section (2) & (3) thereof. The interference is
permitted where the award is found to be in contravention
to public policy of India; is contrary to the fundamental
policy of Indian Law; or offends the most basic notions of
morality or justice. Hence, a plain and purposive reading
of the section 34 makes it abundantly clear that the scope
of interference by a judicial body is extremely narrow. It
is a settled proposition of law as has been constantly
observed by this court and we reiterate, the courts
exercising jurisdiction under section 34 do not sit in
appeal over the arbitral award hence they are not
expected to examine the legality, reasonableness or
correctness of findings on facts or law unless they come
under any of grounds mandated in the said provision. In
ONGC Limited. v. Saw Pipes Limited
14
, this court held
that an award can be set aside under Section 34 on the
following grounds: “(a) contravention of fundamental
policy of Indian law; or (b) the interest of India; or (c)
justice or morality, or (d) in addition, if it is patently
illegal.”
O.M.P. (COMM) 249/2023 Page 14 of 15
19.3 In Parsa Kente Collieries Limited. v. Rajasthan Rajya
Vidyut Utpadan Nigam Limited (2019) 7 SCC 236 held as under:-
“9.1. In Associate Builders [Associate Builders v.
DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , this
Court had an occasion to consider in detail the
jurisdiction of the Court to interfere with the award
passed by the Arbitrator in exercise of powers under
Section 34 of the Arbitration Act. In the aforesaid
decision, this Court has considered the limits of power of
the Court to interfere with the arbitral award. It is
observed and held that only when the award is in conflict
with the public policy in India, the Court would be
justified in interfering with the arbitral award. In the
aforesaid decision, this Court considered different heads
of “public policy in India” which, inter alia, includes
patent illegality. After referring Section 28(3) of the
Arbitration Act and after considering the decisions of this
Court in McDermott International Inc. v. Burn Standard
Co. Ltd. [McDermott International Inc. v. Burn Standard
Co. Ltd., (2006) 11 SCC 181] , SCC paras 112-113 and
Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran
[Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran,
(2012) 5 SCC 306] , SCC paras 43-45, it is observed and
held that an Arbitral Tribunal must decide in accordance
with the terms of the contract, but if an Arbitrator
construes a term of the contract in a reasonable manner, it
will not mean that the award can be set aside on this
ground. It is further observed and held that construction
of the terms of a contract is primarily for an Arbitrator to
decide unless the Arbitrator construes the contract in such
a way that it could be said to be something that no fair-
minded or reasonable person could do. It is further
observed by this Court in the aforesaid decision in para
33 that when a court is applying the “public policy” test
to an arbitration award, it does not act as a court of appeal
and consequently errors of fact cannot be corrected. A
O.M.P. (COMM) 249/2023 Page 15 of 15
possible view by the Arbitrator on facts has necessarily to
pass muster as the Arbitrator is the ultimate master of the
quantity and quality of evidence to be relied upon when
he delivers his arbitral award. It is further observed that
thus an award based on little evidence or on evidence
which does not measure up in quality to a trained legal
mind would not be held to be invalid on this score.”
(emphasis supplied)
CONCLUSION
20. The view taken by the arbitrator is plausible and is not vitiated
by patent legality, perversity or conflict with the public policy of
India. No case is made out for interference by this Court under Section
34 of the Act.
21. The petition is dismissed. Pending application stands dismissed.
AVNEESH JHINGAN ,J.
FEBRUARY 02, 2026
‘ha’
Reportable:- Yes
Legal Notes
Add a Note....